-
Agenda
for the meeting.
-
Minutes
of the meeting.
-
Action
Points from the meeting.
Item
- Presented by: (Oftel unless otherwise
stated)
1.
Introduction and Action Points - Chris Kenny
2. BT
Changes to the April 2000 Contract Review - Keith Mitchinson
(BT)
3. BT/operator
joint working SLA Process Sub-Group - Lois Nash (Orange)
4. Oftel
Retrospective Billing for 96/97 - Sara-Jane Amey (Telewest)
5. Focus
Group updates:
- NTS - Geoff Brighton
- Mobile Number Portability - Peter Roberts (Orange)
- CPS - Karen Hardy (Energis)
- ICPS - Wendy Dodd (MCI Worldcom)
6. Forthcoming
and Recent Oftel Publications - Chris Kenny
7. AOB

Agenda
Item 1 - Introduction and Action Points
Chris
Kenny opened the meeting by referring to one action point (AP 03/3)
outstanding from the previous meeting:
- An E-mail
was sent out to all operators on 22 March 2001 by Oftel's Numbering
Unit asking opinions on the new application forms and inviting
operators to meet with Oftel if they had any particular concerns.
No operators have to date requested a meeting in response to the
E-mail. However, the invitation to operators would remain open.
- The issue
of the new numbering application forms was also raised at the
Numbering Forum on 10 April.
Other
Action points would be addressed during the meeting.
Agenda Item 2 - BT
Changes Under the April 2000 Contract Review
Keith
Mitchinson (BT):
Presentation
on BT Changes under the April 2000 Contract Review:
- Review Notices
were sent out by BT to all operators on 29 June 2000.
- Discussions
commenced with a Review team generally representative of the industry,
which was nominated by the Operator Group.
- On completion
of the discussions, on 16 February 2001 BT offered Supplemental
Agreement to operators to amend the Interconnection Agreement
between operators and BT.
- Those operators
who had not signed the Supplemental Agreements by 28 March 2001
were referred to Oftel.
- A draft tabular
summary including issues incorporated into the Supplemental, issues
being pursued further and issues which were not included in the
Supplemental were available on BTs website at: http://www.btinterconnect.com/
Discussion
Oftel:
Only
77 operators signed and returned Supplemental Agreements to BT before
the deadline of 28 March 2001. On 2nd April 2001, Oftel
wrote to all of the operators referred by BT as non-signatories
to the Supplemental Agreements. Oftel required operators' reasons
for not signing the Agreements and ultimately may take the option
of making a determination in the absence of operator agreement on
the changes to the Standard Interconnect Contract.
Those
Operators who have not yet responded to Oftel should do so as soon
as possible. Operators who did not receive Oftel's letter should
contact Andrew Walker at Oftel andrew.walker@oftel.gov.uk
tel: 020 7634 8909 as soon as possible. AP 04/1.
Agenda
Item 3 - BT/Operator Joint Working SLA Process Sub Group
Lois
Nash (Orange):
Overview
on the undertakings of BT/Operator joint working SLA process sub-group:
- The BT/operator
joint working SLA process sub-group was established to take forward
work arising out of the April 2000 Interconnect Agreement Review
relating to BT performance issues associated with the provisioning
of time-scales and processes for interconnect circuits contained
within the Interconnect Agreement.
- The sub group
aims to conclude its work by the end of August 2001 at which point,
if still unresolved, outstanding issues may be referred to Oftel
for determination.
- Further details
including the sub-group Terms of Reference and minutes of sub-group
meetings are available on the BT website at http://www.btinterconnect.com/
Discussion
Lois
Nash:
In
response to a question from Oftel, explained there was a deadline
for nominations for joining the SLA process sub-group. However,
if a non-member wished to raise a substantive issue for consideration
by the sub group then it should be referred to Lois Nash. The same
also applied at the sub-group working party (SWP) level.
Oftel:
Lois
Nash will be invited back at an appropriate time to provide a SLA
sub-group update to the OPF.
Agenda Item 4 - Retrospective
billing for 96/97
Sara-Jane
Amey (On behalf of Operators Group)
- A number
of Operators received letters from BT dated 30 March 2001 informing
of re-calculated charges for telephony and operator services for
the periods 1 April 1996 to 31 March 1997 and 1 April 1997 to
30 September 1997.
- Operators
were concerned at the time taken for BT to inform operators of
the re-calculated charges; the general elementary nature of the
calculations and the way that the amount of interest has been
calculated on the net settlement amount. As a result some operators
have requested that BT provide an explanation of the charges.
Discussion
BT:
BT
needs to ensure that operators would be furnished with a sufficient
explanation of the charges and that the re-priced charges and interest
have been calculated correctly. Any operator requesting an explanation
from BT who did not consider that they received a sufficient response
should contact Graham Lamb (BT Regulatory Affairs).
Oftel:
Essentially
this was considered to be a contractual dispute which, if no agreement
could be reached between the parties, should be settled in court.
It was noted that BT had agreed to look at operators concerns.
Agenda
Item 5 - Focus Group updates
NTS
Geoff
Brighton (Oftel) reported on behalf of the NTS Focus Group:
Report
of the NTS Focus Group that met on Thursday 19 April. Issues raised
would be put to BT not present at the meeting.
New
NTS -Price Points
- Concern was
expressed at the timescales BT applies to requests for new price
points. Operators were asked to give their views on what reasonable
timescales would be given the work involved in establishing new
price points, including the need to ‘datafill’ all of BT’s exchanges.
- BT has introduced
a new NTS pricing ladder with effect from 1 February, however,
the meeting identified the following issues:
Process
for gaining agreement for special requests not included in the
ladder guidelines;
BT
have refused to open some off-ladder price points;
Lack
of industry notification of the ladder/guidelines;
BT
Commercial Managers not briefed and do not appear to know how
to process ‘normal’ and ‘special’ requests adding to the already
extensive timescales;
BT’s
failure to complete datafills nationally by the contractual date
and faults in datafills leading to call failures.
Operators
were asked to provide specific examples of the failures listed above
so that BT could be asked to comment.
Transit
- INCA could
not distinguish between BT originated and transit calls and should
be developed to flag transit calls to OLOs;
- Apparently
BT can and will charge the originating operator for transit for
0844 and 0871 numbers, but not other NTS numbers. It is not clear
why it is possible to do so for these numbers but not others.
- CLIs from
other ONOs are not received by TNOs who can not identify the source
of calls;
- BT was applying
NCD’s to transit POLOs. The NCD used was that of the terminating
operator whereas all originating operators interconnect at single
tandem or very close to it. This incorrectly and unreasonably
reduced POLOs.
- Although
BT served transit invoices on terminating operators it rejected
invoices served on it, for calls to BT’s NTS, by other transit
operators.
INCA
- Graham Davies
(Easynet) reported that although his company had volunteered for
the INCA trial at BT’s request in October 2000 they had received
no data for the period October to December 2000. They received
some data in February but had to query it as indecipherable. Their
BT Commercial Manager was unable to explain how the charges worked.
- As a consequence
the general view was that INCA was not ready for use. OLOs could
not develop their billing systems to work with it until BT could
provide clear information. Particular problems existed with INCA’s
inability to bill for transit and number portability. An inaccurate
NCD proxy was unacceptable.
IN
Charge
- The meeting
confirmed that they were aware of BT’s policy of raising a ppm
charge for the IN dip necessary to route calls to the 1k NTS number
blocks Oftel was issuing in the interests of number conservation.
No-one had seen the charge published, certainly not in BT’s Carrier
Price list. This clearly was a Standard Charge and should be published.
Discussion
BT:
The
structure of the NTS Price point ladder was also the subject of
discussion at New Services Focus Group (BT/Operators Group). New
Services Focus Group will contact Geoff Brighton to ensure that
the two groups are not duplicating work.
Geographic
and Non Geographic Number Portability
Report
was circulated to the meeting.
Mobile
Number Portability
Peter
Roberts (Orange) reported on behalf on
the Mobile Number Portability Focus Group
ORG
- Workshop
met in March to review the MNP2 porting process manual. A new
re-draft would be presented to ORG/Focus Group.
April
quarterly ORG
- One specific
Service Provider with problems will be invited to the next ORG
in order to seek resolution.
Meetings
would now be held monthly in run up to MNP2
MNP2
Delivery
- Main focus
for April was completing the development phase, setting the web
hosting environment and agreeing the UAT plan (issuing detailed
spec tests).
- For the TDA
(Tech Design Authority), security was the current focus, including
issue and authentication of certificates, and logon security.
- IPG have
agreed the training schedule, which will include 3 venues.
- In summary,
milestanes were being met, there was no risks or issues. The effective
Go/NoGo milestone was 20th April, which should determine
if the manual MNP process would be required.
Focus
Group - Current Status
- Public launch
of MNP2 on 30 September 2001 is confirmed.
- Agreement
that if MNP encouraged bad debt, and if there was evidence of
this, then there would be a formal review.
- Orange agreed
to draft press release on behalf of the industry group. This would
then be circulated to members and agreed prior to publication.
It was agreed that it should be released through the FEI (Federation
of Electronics Industries), since they had in the past issued
joint operator statements. Oftel said they were happy to put out
their own release expressing support for industry’s initiative
MNP2
Production Manager
- Role should
be full time, and in place in time to help manage the MNP1 to
MNP2 migration, and then ongoing. General view that this should
be a specific responsibility and, probably, contracted out for
at least an initial 6 month period to assess the role. The Project
Board would further investigate costs.
New
Chair
- Peter Roberts
will be stepping down as the OPF-MNP-FG Chair and will be replaced
by Frank Stewart, one2one.
Oftel:
Chris
Kenny thanked Peter for his work during his tenure as Chair of the
OPF-MNP-FG.
Carrier
Pre-selection
Karen
Hardy reported on behalf of the CPS Focus Group
Commercial
Group
- Preparations
for CPS Phase 2 were well underway following the launch of Phase
1 in December 2000. There were concerns about the amount of work
to be completed in time for the December 2001 launch for Phase
2. Process and other CPS Groups would look at all issues in order
to understand what needs to be done for Phase 2.
- Next meeting
of the Process Group will take place on 1 May.
Process
Group
End
to End Process Manual
- Substantial
work had been completed in revising the End to End process manual
and it was hoped that a new version, probably version 7, would
soon be available on the Oftel website.
Resellers
Process
- Dialogue
was continuing between BT and Oftel on the implementation of Reseller
Process. BT has been asked for timescale for development of a
Reseller process.
New
Chair
- A new Chair
of the Process Group is sought to replace Chris Garbett (CWC)
who was due to step down.
Process
Improvement Group
- A revised
industry position would be formulated on consumer protection legislation
and if a CPS-specific cooling off period was necessary. This would
be presented at the next Consumer Group meeting on 16 May.
Triallist
Group
- CPS Phase
1 Triallist Group has been disbanded and would be replaced by
a new Triallist Group Chaired by Thus for CPS Phase 2 trials.
Three triallists have been selected for Phase 2.
PNOIG
Technical Task Group
- This Group
had previously concentrated efforts on the testing apect of Phase
1. However, this Group still needed volunteers from operators
with technical expertise. Any suitable volunteers should contact
Karen Hardy (Energis) or Caroline Wallace (Oftel).
Interim
Carrier Pre-selection
Wendy
Dodd reported on behalf of the ICPS Focus
Group
Agenda
Item 6 - Forthcoming and Recent Publications
Chris
Kenny informed the meeting of forthcoming publications:
- Decision
on Oftel's Competition Act investigation into BT Talk and Surf
Together product
- Funds for
liabilities (consultation)
- Business
consumer research
- Northern
Ireland equality scheme (consultation)
- Number portability
functional specification
- Draft determination
of price for shared loops
- Updated LLU
guidelines
- Residential
consumer research
- Internet
access market review (consultation)
- Oftel's Welsh
language scheme
- Personal
numbering (consultation)
Agenda
Item 7 - AOB
Oftel:
Two
further action points outstanding from the previous meeting:
Modem
co-location (AP 03/1)
- Now BT had
clarified that modems were not co-located in each of their local
exchanges, the situation may have changed. Oftel intends to take
no further action unless operators make submissions to BT.
FRIACO
overflow and 64k Granularity (AP 03/2)
- No responses
to date have been received on how overflow between DLE and ST
routes would work including dimensioning rules and the management
of excessive peaks.
Oftel
seeks urgent input from operators before taking this further.
IP
Interconnection
- No further
'public meetings' would be held on this but progress will be reported
back to OPF and OIF.
BT:
BT
agreed to provide update at the forthcoming OPF on BT restructuring.
NAP
04/2
BT
agreed to give a presentation at the forthcoming OPF on BT Network
congestion.
NAP
04/3
Next
Meeting
Next
meeting will be on Thursday 7 June commencing at 2:30pm

ACTION POINTS:
OPF - 26 April 2001
|
No.
|
Description
|
Status
|
Owner
|
|
04/1
|
On 2nd April 2001 Oftel wrote to all operators
who had not yet returned signed supplementary contracts to
BT under the April 2000 Contract Review. Those Operators who
have not yet responded to Oftel should do so as soon as possible.
Any operators who did not receive Oftel's letter should contact
Andrew Walker at Oftel andrew.walker@oftel.gov.uk
tel: 020 7634 8909 as soon as possible.
|
New
|
Oftel
|
|
04/2
|
BT to provide update at the forthcoming OPF on BT restructuring.
|
New
|
Oftel
|
|
04/3
|
BT to present at the forthcoming OPF on BT Network congestion
|
New
|
Oftel
|

|