|
May 2000
Contents
Introduction
BT's
proposed pricing structure
Oftel's
initial views on BT's proposed pricing structure
Oftel's
initial conclusions
Consultation
Introduction
1.
In the November 1999 Statement "Access to Bandwidth: Delivering
Competition for the Information Age", Oftel set out a number of
high level pricing principles.
- The price of
the loop will be cost-oriented and set on the basis of reasonably
and necessarily incurred LRIC plus a mark-up to account for costs
that are common to the line and other BT services;
- Charges for other
necessary inputs, such as internal tie cables, should also be on the
basis of reasonably and necessarily incurred LRIC + mark-up;
- The starting
charge will be geographically averaged, but BT may request geographically
de-averaged prices if this can be shown to be justified by differences
in the underlying costs;
- BT should be
able to recover the costs associated with setting up co-location facilities
and order handling processes, as well as the costs incurred as a result
of dealing with operators and maintaining the service; and
- If operators
share a co-location area, the charge for co-location should be set
on the basis of average cost, and should depend on the amount of space
occupied.
2.
The basic pricing principles for unbundled local loops and associated
services have now been set out in the new licence condition Condition
83 Requirement to provide Access Network Facilities. The
following describes how Oftel intends to apply these principles.
3.
Oftel has stated that charges should be based on "reasonably and
necessarily incurred" costs. For assets in place, Oftel does not
intend to adjust for minor inefficiencies, but would adjust for major
inefficiencies if studies showed that BT were significantly less efficient
than a properly adjusted comparator group. However, on the basis of
the studies that Oftel has commissioned (due to be published shortly),
its current assessment is that is that an adjustment for efficiency
is unlikely to be required. For assets and systems that are not yet
in place, Oftel would expect charges to be set on the basis of efficiently
incurred costs.
4. Oftel expects that unbundled loops will be used
primarily to provide broadband services to customers. However, operators
are not prohibited from using loops to provide analogue voice alone.
There are two potential issues that arise from this.
5.
First - cost recovery: In the Statement, Oftel recognised that if operators
were to use loops for analogue telephony, the combination of a single
price for lines and a tariff that creates varying degrees of profitability
per line, might, in the extreme, lead to BT being unable to recover
its costs plus a reasonable return on capital. Clearly this would need
to be addressed, but it is an issue relating to voice services per se
and not just those delivered via unbundled local loops. If this circumstance
seemed likely to arise, Oftel would look at the pricing arrangements
for unbundled loops and other voice delivery mechanisms and make adjustments
to ensure that BT was able to recover its costs.
6.
Second consistency: The scenario above represents an extreme
circumstance. There is also a continuing need for overall consistency
in the approach towards price controlled BT services. In particular
Oftel needs to ensure that in pricing unbundled loops and other services
that allow the delivery voice, no distortions are created that would
give an artificial incentive for operators or service providers to use
any particular mechanism. To ensure consistency, Oftel will take account
of the effect of any changes to other mechanisms such as indirect access
on the use of unbundled loops for voice and would adjust the price to
remove any distortions if necessary.
7. Assessments on both these issues would take place
in the context of the Price Control Review. Oftel will also monitor
the use of loops and would, if it appeared that its high-level objectives
to promote competition in the provision of broadband services were not
being met, want to examine why that was the case and address any distortions
that were found.
8. Having decided on the high level pricing principles,
the next stage in the process of arriving at final prices for unbundled
loops is to look at the detail of how charges should be calculated.
This document sets out BTs detailed proposals for the structure
of charges and Oftels initial views on these proposals.
9. It should be noted that the charges appearing in
this document are BTs initial, indicative calculations. As such,
they should only be taken as an indication of the likely scale of any
charges that will eventually be levied. They should not be taken as
representing the exact charges that operators will face when requesting
unbundled loops. BT is continuing to refine the figures in order to
provide a more robust set of proposed charges by the end of June 2000.
In addition, Oftel will want to examine closely any figures that BT
produces at this time, particularly in the light of the bottom-up modelling
work that is currently taking place to establish the cost of a copper
loop and the forthcoming Consultation on BTs Financial Statements.
Barring any major discrepancies, it is intended that BTs own top
down information will be used as the starting point, with bottom
up information being used to ensure that only relevant costs are
included within the calculation.
10. Although Oftel will not be arriving at a view
of the reasonableness or otherwise of BTs proposed charges until
more robust information is made available in June, Oftel would still
welcome views on whether the scale of the indicative charges seems reasonable
or not. Oftel would be particularly interested in any evidence that
can be provided to substantiate views expressed in this area.
11. Further stages for the determination of starting
charges are:
End May 2000 -
Consultation responses received
End June 2000
- Further cost information provided by BT
- Cost information from the bottom-up model
July 2000
- Statement on pricing principles
October 2000
- Publication of indicative charge
ranges
December 2000
- Determination of charges
12. Oftel will review
regularly the price set for unbundled loops. The first review will be
12 months following the introduction of services. Thereafter there will
either be an annual determination of charges or an on-going control
for example the RPI-X form of price control
13. This consultation document looks at proposed charges
for all items. However, it is important to recognise that Oftel will
be determining some charges up-front, while other charges will only
be determined in the event of a dispute. The purpose of including those
items that fall into this second category in this Consultation Document
is that Oftel wishes to provide transparency as to the view it would
be likely to take in the event of the need to determine charges.
14. BT is required to offer the following items to
operators:
- Metallic path
facility (relevant charges will include the price of loop, system
set-up and on-going charge for order handling)
- Internal tie
cables
- Co-location facilities
(rental, set-up and maintenance) or external tie cables
- Any other ancillary
services to these products
15.
Oftels approach to the determination of charges for these items
is that determination of charges should only be made prior to a dispute
if:
- The item being
charged for is not competitively supplied; and
- Determination
is practical, in that charges are not bespoke or subject to significant
variation due to geographic location.
16.
This rationale has led to the position outlined in the licence condition,
namely that only the charge for metallic path facilities and internal
tie cables should be determined prior to any dispute. For the remaining
charges, the licence condition states that:
"The licence
shall provide Access Network Facilities
..at a charge or charges
to be agreed between the parties and in default of agreement to be
Determined by the director."
17.
The licence condition also places controls on BTs charges through
prohibiting BT showing undue preference or exercising undue discrimination.
In assessing whether either of these practices were taking place, Oftel
would need to come to a judgement about the service that should be used
as the comparator to unbundled loops. The licence condition states that:
"24. The
Licensee shall not (whether in respect of the charges or other terms
or conditions applies or otherwise) show undue preference to, or exercise
undue discrimination against, particular persons or persons of any
class or description as respects to the matters to which this condition
relates.
25.The Licensee
may be deemed to have shown such undue preference or to have exercised
such undue discrimination if it unfairly favours to a material extent
a business carried on by it in relation to the doing of any of the
things mentioned in paragraph 24 so as to place at a significant competitive
disadvantage persons competing with that business in a Relevant Market."
18.
The rationale for Oftels decision not to determine up-front the
charges for other items is that:
- Oftel considers
that external tie cables could potentially be competitively provided.
- Taking as a starting
point that co-location set-up and maintenance charges are bespoke,
Oftel considers that it would be impractical to determine these charges
in all cases prior to a dispute.
- Rental may vary
widely from exchange to exchange, so Oftel again considers that it
would be impractical to determine these charges in all cases prior
to a dispute.
19.
This is not to say that Oftel is of the view that the charge for these
items could not be determined in the event of a dispute. In such an
event Oftel retains the right to determine the exact principles that
should be followed in setting the charges, or the particular charges
themselves, or the way in which charges are structured.
Back
to contents
BTs
Proposed Charging Structure
20.
BT has presented Oftel with an initial structure of costs and some initial
figures for those costs. BT has proposed that its analysis of the costs
, as set out in this document, should be taken as indicative of its
proposals for the structure of prices.
Price of the
loop existing and spare pairs
21.
BT has proposed that charges should reflect five broad categories of
loop provision, and that there should be three charging elements for
each of these categories. This proposed structure of charges is shown
in Table 1.
Table 1: BTs
proposed structure of charges and indicative costs for the metallic
path facility
| Scenario
/ Type of connection |
Annual
Rental
£
per line
|
Connection
cost
£
per connection
|
Disconnection/Reconnection
cost
£
per line
|
| Line
transfer
-with new
NTE
|
115
|
130
190
|
20
|
| Spare
pair
-line met
from stock
-requiring
additional work
|
105
|
230
385
|
10
|
| New
line
- minor
network intervention
|
105
|
585
|
10
|
| New
line
- major
network intervention
|
105
|
775
|
10
|
| New
line
-small network
build <50 man hours
|
105
|
1,185
|
10
|
22.
Most, but not all, of the costs used to arrive at these figures reflect
the allowable return on capital of 14.5%. This figure derived from the
current average return on charge-controlled network services, and has
been adopted to ensure that the charge for loops is consistent with
that levied on other mechanisms for delivering voice. In subsequent
years, again consistent with the approach towards network services,
the allowable return on capital will be reduced on the basis of a glide
path that will bring the allowable return down to the target rate of
return for network services at the end of the 4-year period to end-June
2005.
23. If charges were to reflect the format shown in
Table 1, an operator taking over an unbundled loop would be required
to pay an annual rental charge and a connection charge for the line.
The connection charge would reflect the costs of the line test, MDF
jumpering and order handling. An operator ceasing to require an unbundled
loop would be charged for the cost of disconnecting and reconnecting
the line to BT.
24. BT has been working on a top-down model to generate
information on the CCA LRIC + mark-up rental cost of the loop. The increment
used for this modelling work is all metallic paths in BTs access
network. The rationale for this increment is that all existing metallic
loops are available to operators who wish to request them as metallic
path facilities.
25.
Of the total annual rental charge for existing loops, plant costs, drop
wire and the capital improvement programme make up 75% of the indicative
charge. The mark-up for common costs accounts for a further 13%, and
the remainder of the indicative cost is made up of LLU-specific wholesale
costs and overheads. It should be noted that the figures shown in the
table exclude the costs of fault reporting and repair (though not routine
maintenance). BT has proposed that these items be charged separately
to operators on a per occasion basis.
26.
BT has derived the annual rental costs through firstly aggregating the
relevant rental costs of all metallic paths. These costs are derived
from a combination of relevant rental costs from existing "metallic
path only" increments for Access and Private Circuit local ends
and producing a basic cost increment for the annual rental. In determining
the relevant costs of the metallic path facility BT has removed costs
from the underlying increments that are either inappropriate for the
service (eg line card or non-metallic path costs) or indicated to be
a cost not relating to the service.
27.
BT has then adjusted the base case for known additional costs relevant
to LLU. This includes a capitalised charge for the drop wire and a charge
for BTs local loop capital improvement programme. BT currently
expenses the cost of drop wires, but for the purposes of this exercise
has treated it as being capitalised with a useful economic life of ten
years.
28.
BT has informed Oftel that the capital improvement programme addresses
replenishment of line stock, refurbishment/replacement of lines that
may be fault intolerant to broadband services, replacement of line pressurisation
plant and updating of lightning protection. The programme is not national
at present, so BT has calculated the charge for this by averaging the
cost of the programme over the total number of copper pairs in the areas
covered by the programme.
29.
BT has then created a new increment to reflect the combined costs of
metallic path facilities. The LRIC costs for the new rental increment
are then calculated and the mark-up for common costs is identified.
The mark-up represents an appropriate share of all costs that are common
to the unbundled metallic path increment and other BT Services and has
been distributed on the basis of equal proportional mark-up of the appropriate
increments.
30. For spare pairs and new provide, BT has proposed
that the annual rental should not include a capitalised charge for the
drop wire, but should still include a charge for the capital improvement
programme. The cost of the drop wire would be met within the one-off
connection charge. The exclusion of the capitalised cost of the drop
wire explains why the annual rental for spare pairs and new provide
is lower than the annual rental for existing loops.
31. Some costs that might be expected to be included
in the charge for the loop are excluded from BTs proposed prices.
For example, system set-up costs and the general rental and maintenance
associated with use by operators of BTs MDF, are excluded from
this annual rental charge.
32. In addition, BT has removed fault reporting and
repair costs from the annual rental charge. BT has proposed that repair
costs be charged for on a per occasion basis. The proposal is that a
charge be levied each time that BT is required to repair a line or respond
to a reported fault. The cost of routine maintenance of the loop remains
in the annual rental charges.
33. BT has indicated to Oftel that there is an additional
scenario that could lead to costs being incurred over and above those
contained in the table. This scenario is when the customer has a line
provided through use of pair gain equipment. BT has suggested that this cost could be recovered either
as a specific charge or averaged into the charge for a line met from
stock.
34. The cost of reconnection is
lower for spare pairs and new provide than for existing loops. BT has
assumed that all reconnect will require a BT engineer to disconnect
the line from the internal or external tie cable. In the case of an
existing line, the cost is higher because BT has further assumed that
the line will be reconnected to the originating line card.
35. BT has yet to carry out robust modelling of the
wholesale costs and overheads. At the moment these have been estimated
by adjusting the retail costs for connection and rentals of all PSTN,
ISDN2 and metallic ISDN30 products to reflect the fact that not all
costs are relevant to wholesale activities. For example, marketing costs
have been excluded because these are not generally associated with wholesale
activities. In addition, provision and installation and maintenance
have been excluded on the basis that these have already been included
in cost calculations relating to drop wire capitalisation.
Price of the
loop new provide
36.
In the draft guidelines for the licence condition, Oftel stated that:
"
.Where
a single average price is set, the price determined for the MPF will
be based on an average cost of providing the lines described above,
ie those existing and spare lines that are suitable or could readily
be made to meet the required specification for an MPF. BT would be
expected to meet the obligation to supply at the determined price
for all lines where costs do not exceed [n]. Additionally,
the Director considers it reasonable for BT to supply as MPF lines
outside this requirement that may nonetheless be extended or conditioned
appropriately, but the additional costs incurred will need to be met
by the OLO. Where the costs exceed [n] or more than [n]
man hours are required, the Director does not consider that it would
in general be reasonable for BT to be required to supply the line
as an MPF."
37.
BT has now proposed what the values of [n] should be. The increment
for the loop includes only those loops that are available from stock
(ie existing loops and spare pairs). A separate charge will be levied
for new loops that involve:
- Minor network
intervention;
- Major network
intervention; and
- Small network
build.
BT has proposed
that new loops will not be supplied if provision requires over 50 man
hours of work within the access network.
Internal Tie
Cable
38.
BTs proposal is that all operators be charged for an internal
tie cable whether they are co-locating in the exchange building or are
distant co-locating. In practice this would mean that the cost of an
internal tie circuit is included within the external tie circuit price
charged to operators using distant co-location facilities.
39. BT proposes that there be a connection charge
and a rental charge for the internal tie cable. The annual rental charge
will be £170 per 100 tie cable. The connection charge will be £4400
per 100 pair tie cable. Both charges assume an average cable length
of 100m. The connection charge will cover the costs of:
- Internal tie
cabling
- MDF Ironwork
capacity
- HDF Ironwork
capacity
- MDF block
- HDF block
- Cabling costs
(to run and terminate cable ends)
40.
BT proposes that this connection charge will also be used to recover
the system set-up costs associated with implementation of the requirement
to offer metallic path facilities. BT has proposed that it recover it
system set-up costs over five years. BTs estimated system set-up
costs are:
Programme Deliver
& Management £0.6m
Training £0.1m
Spectrum Management £0.7m
OSS Development £19.5m
Testers Training £0.1m
Access Solution Design £0.2m
Total £21.1m
41.
BT has converted this total into a connection charge of £2,509 per 100
pair tie cable by the following process. Firstly, BT has forecast the
expected volume of new loops in each of the five years following introduction
of the service. BT has then apportioned system set-up costs to each
of these years by multiplying the total system set-up costs by the percentage
of new loops in the year to the total number of loops. BT has then applied
a return on capital to arrive at a total cost over the five years. This
cost is then divided by the forecast total number of tie cables to give
the system set-up element of the connection charge per cable. This calculation
is shown in Table 2. It should be noted that use of the most recent
volume forecasts from the industry would lead to a lower figure of around
£1,400 per cable.
Table 2: Recovery
of Set-up costs via connection charge
| |
Year
1
|
Year
2
|
Year
3
|
Year
4
|
Year
5
|
Total
|
| Discrete
volumes (000)
Average System
size (000)
Actual costs
Discrete
Actual costs
Cumulative
Closing capital
employed
Mean capital
employed
ROCE (14.5%
to 12.5%)
|
112
56
2.1
2.1
19.0
20.1
2.9
|
272
248
5.0
7.1
14.0
16.5
2.3
|
327
548
6.0
13.1
8.0
11.0
1.5
|
290
856
5.4
18.5
2.6
5.3
0.7
|
141
1,072
2.6
21.1
0.0
1.3
0.2
|
1,142
21.1
7.6
|
| Total
costs incl. ROCE |
5.0
|
7.3
|
7.5
|
6.0
|
2.8
|
28.7
|
Co-location
Licence Fee
42.
BT has proposed that there be two charges under this heading. The first
would be a rental charge for the dedicated space being occupied by an
OLO co-locating in a BT exchange. The second would be a rental charge
for a share of the space required for the MDF. The first of these charges
would be made only to operators who are co-locating in the exchange.
The second of these charges would be made to all operators.
43. The charge for dedicated space would depend
on the actual space being occupied by an operator. The general charge
would relate to the percentage of the MDF capacity being used by an
operator. The charge would be calculated by allocating the rental charge
for the CCA MDF footprint on the basis of the MDF capacity used by each
operator. MDF capacity used is measured in terms of the copper pairs
attached to the MDF.
44. BT has proposed that both of these charges
be based on the higher of the light industrial or alternative use market
rates. BT has proposed that this licence fee should be set on a building
by building basis. However, BT wishes to reserve the right to charge
on a regionalised basis. BT has provided Oftel with some indicative
charges for the licence fee. These are shown in Table 2. These charges
include both elements of the licence fee, but are for space only and
do not include such items as power consumption and maintenance.
Table 3: Indicative
licence fee rates.
| London
& the South East |
£50-200
per square metre |
| Wales
& the Midlands |
£20-200
per square metre |
| North
England & Scotland |
£20-150
per square metre |
| Northern
Ireland |
£20
-50 per square metre |
45. BT has proposed
that the cost of providing or converting a room for an OLO co-locating
in BTs exchange be recovered through a one-off set up charge.
BT would seek to recover these costs from the OLO when the order for
a room had been accepted and the quote from the architect had been received.
BT proposes that any adjustment to cover under or overpayments by the
OLO would either be reimbursed or invoiced within two months of the
room being ready for handover.
46. BTs view is that costs will vary depending
upon location, room size, amount of conversion required, equipment installed,
etc. BT has proposed that there should be a charge to cover the cost
of providing an OLO specific cable runway, and that this charge would
be payable whether or not and OLO chose to co-locate or use external
tie cables. BT has provided an estimate of the one-off set up costs,
and these are shown in Table 3. Under BTs charging proposal, the
exact charges would depend on the precise requirements of the operator
and will vary according to the work required at the specified building.
Table 4: BTs
estimated costs for room build
| Ventilation
/ cooling |
£5k-20 |
| Minor
Equipment * |
£8k-20 |
| Planning |
£2k-5 |
| Access
control |
£5-10 |
| Doors |
£2k-5 |
| Flooring
& Building |
£200-500
per square metre |
| Cable
runway |
£10k-25 |
* The minor equipment
would include such items as provision of separate fuse boards, smoke
detection equipment, skip hire, asbestos survey, etc.
47.
BT has proposed that the on-going maintenance costs be split into two
categories. The first would cover maintenance of the dedicated space
occupied by operators co-locating in an exchange building. The second
would cover maintenance of the building itself. BT proposes to raise
this charge on an annual basis as a charge per copper pair. The charge
would be calculated by apportioning the cost of maintaining the building
by the percentage of the capacity of the MDF. It is currently BTs
intention that this charge would be building specific, but BT wishes
to reserve the right to charge for certain buildings on a regional basis.
48. Both maintenance charges would cover activities
such as general maintenance of the fabric of the building, painting
and repair to both external and internal walls including the space occupied
by co-locating operators. It would exclude maintenance of equipment
installed by co-locating operators.
49. BT has indicated that the both the specific and
general maintenance charges would be in the range £10 to £20 per square
metre.
Co-location
Charge for power
50.
BT has proposed that operators should be charged on the basis of their
metered use of power. The charge for power proposed is the standard
rate charged by the electricity company providing services to BT at
the exchange. So the rate will vary from building to building depending
on the company used by BT. This rate will apply whether BT is taking
power from the electricity company or is using its own systems to provide
the electricity. The exception to this rule is that BT proposes to make
an additional charge for stand-by power that is used in the event of
an emergency.
Co-location -
Escorting services
51.
BT has not yet provided indicative figures for this item.
Back
to contents
Oftels
initial views on BTs proposed charging structure
Charge for the
loop- existing loops and spare pairs
52.
Oftel is concerned that BT is treating recovery of the cost of the drop
wire differently under LLU than has been assumed for the current price
control. Under the current price control, and in accordance with BTs
accounting policies, the cost of the drop wire is expensed. This means
that the cost of any work in this area appears as an expense in the
accounts in the year during which the work took place. The price control
allows for this approach to recovering drop wire costs. For LLU BT now
proposes to go back and work out the result of capitalising and depreciating
the drop wire. The additional capital is then added to the plant cost
base and is subject to a return on capital employed. The operating costs
are also supplemented by a depreciation charge, based on the 10 year
asset life of the drop wire.
53. It could be argued that BT has already recovered
the cost of the drop wire for existing loops under the price control,
and is proposing to recover it again through a charge for LLU. This
would suggest that in order to prevent over-recovery of costs by BT,
BT should not be allowed to include this capitalised drop wire cost
in the charge for the loop. However, if BT does not include this cost
in the charge for the loop two possible problems would result. First,
it would lead to different charges for existing and new loops. There
would be no charge for drop wire on existing loops, but new loops would
pick up this cost. While this would complicate charges, there would
be no objection in principle to such a difference if it reflected the
different costs to BT of supplying loops in different circumstances.
Second, if the cost of drop wire is not included the charge for existing
loops would be below cost and this may not appear to present appropriate
signals for competing infrastructure provision. However, another way
of considering this issue is to recognise that customers should not
be charged again for something for which they have already paid. A competitor
who attempted to sell a product to a customer which included an element
for which the customer had already paid might expect to lose sales to
a rival whose charges excluded payments for such elements.
54.
On this analysis Oftel is of the initial view that the complexities
that might arise as a result of not allowing BT to make a capitalised
charge for drop wire are not significant enough to outweigh concerns
about BT over-recovering its costs.
55. Oftels proposal is therefore that BT should
not be allowed to recover again the costs of drop wires for existing
pairs. However, the costs of providing a new drop wire for spare pairs
should be recoverable. Oftels view is that the most appropriate
mechanism would be to capitalise these costs. One issue that needs to
be addressed in this context is what happens when an unbundled loop
that is subject to a capitalised drop wire charge is transferred
either to BT or another operator. Oftel suggests that in these circumstances
the operator taking over the line should pay to the original local loop
unbundling operator a charge for the drop wire based on the depreciated
value of the capitalised cost of the drop.
56. BT has proposed that the annual rental for an
unbundled loop should include a contribution toward the cost of BTs
capital improvement programme. Oftel considers it reasonable for the
charge for the loop to take account of the improvement work BT is undertaking.
57. However, Oftel believes there is an issue of how
any improvement programme should be reflected in the charge for the
loop. In the regulatory accounts, the costs of such improvement programmes
are capitalised and reflected in a higher CCA value of the loop. Oftels
initial view is that this approach should also be taken for unbundled
loops. This would aid transparency and would also prevent issues about
non-discrimination that could arise if the programme is reflected in
different ways for unbundled loops and BTs ADSL service.
58.
BT has proposed that fault reporting and repair be charged for on a
per occasion basis. BTs rationale is that it is uncertain of the
level of fault reporting and repair activity that will apply to unbundled
loops. BTs view is that the incidence is likely to be related
to the use made of the loop and may not be related to existing fault
levels. So BT suggests that to the extent that fewer faults occurred
on loops offering narrowband rather than broadband services, operators
who offer narrowband over a loop would pay less than those offering
broadband over a loop. Equally, operators offering one broadband technology
over the loop may pay a different amount to operators using a different
broadband technology.
59. Oftel is not aware of any evidence to suggest
that the level of faults varies with use of the loop. Oftel has requested
that BT provide evidence of this from its ADSL trials and its existing
HDSL service, but Oftel has been informed that this information is not
currently available in the form requested. Oftels main concern
with this proposal is it will lead to uncertainty for operators who
are taking unbundled local loops. These operators will have no visibility
of the cost of repair associated with any given loop. Oftel is also
concerned that operators are not in as strong a position as BT to absorb
the risk that certain loops may due to their inherent nature rather
than any use made of them, require a high level of repair.
60. As a result of this concern, Oftel believes that
the best approach is for BT to include an estimate of the repair costs
in the annual rental charge for the loop. Repair costs should be estimated
to reflect the requirement to repair the loop to the specification for
metallic path facilities. If BT does not have the information necessary
to do this for unbundled loops, it should use existing fault information
and Oftel would review the charge for the loop once sufficient information
was available to assess whether unbundled loops are likely to attract
additional repair costs by virtue of their use.
61.
BT had indicated that an additional cost will be incurred where loops
are currently served using pair gain equipment. In such circumstances
the DACS system would need to be removed before the loop could be unbundled.
The likely result of DACS removal is the requirement to provide a new
line. There are two ways of dealing with this to charge on a
per occasion basis or to set an average charge for rental of the loop,
based on an assumption of how many loops use DACS.
62. Oftel is of the view that the best approach is
to average the expected cost of DACS across all loops. While a separate
charge better reflects how the costs arise, an operator requesting a
local loop for unbundling will have no visibility of whether the customer
is served under DACS and so cannot respond to this price signal. In
addition, without visibility of the customers or areas served using
DACS, a separate charge would lead to uncertainty for operators taking
loops by preventing them from having a clear idea of their cost base.
63. Oftel believes that this approach should also
be adopted for charging when customers have old NTEs. Again, separate
charges would provide a better price signal, but operators do not have
visibility of whether or not a customer has the correct NTE so cannot
respond to this price signal. So BT should have an average price for
the loop that assumes a certain number of loops are either supplied
using DACS or have an incompatible NTE.
Charge for the
loop- new provide
64. As discussed above, BT has proposed a level
of work above which it will charge an additional fee. BT has also proposed
three different categories of additional charges and a level of work
above which it would not provide new loops. Oftels initial view
is that BTs proposals in this are reasonable
Internal tie
cable
65.
BT has proposed that the system set-up costs associated with the metallic
path facility service be recovered through a connection charge for internal
tie cables. System set-up costs need to be recovered on a service that
is purchased by all operators taking unbundled loops. The two options
are therefore to recover system set-up costs through the annual rental
or connection of the loop or through the internal tie cable.
66. Oftel sees significant disadvantages with BTs
approach. A major impact of recovering system set-up costs on internal
tie cables is to bring forward the payment that operators have to make
for the system set-up costs. For example, an operator entering the market
would have to pay the full £2,509 under BTs system even if it
only had a single loop. Oftels view is that instead, operators
should pay for set-up costs in proportion to the number of lines they
are using. Given the one-off nature of the system set-up costs, it would
be appropriate for these costs to be recovered as a one-off payment.
This would lead to the conclusion that the system set-up costs should
be recovered through the loop connection charge.
Co-location
general
67.
It is Oftels understanding that BT has proposed that areas for
shared co-location should only be set aside if operators make a joint
request for shared co-location space. It is also Oftels understanding
that other operators have agreed to this system when the service is
initially launched, but are requesting that general co-location areas
be made available as soon as possible after launch.
68. Oftel strongly believes that it is reasonable
for operators to expect BT to set up general co-location areas without
the need for a joint request from the initial launch of unbundling.
This is standard practice in other countries where unbundled local loops
are available, and Oftel believes it should also be standard practice
here. The policy currently being pursued by BT would have the effect
of raising the costs of operators taking unbundled local loops. Most
operators will be forced to pay for a survey and building work even
though many, if not all, of them would not object to having caged or
open areas in a general co-location room. This could act as a barrier
to entry. It will also limit the flexibility an operator has to expand
or contract the space it wishes to occupy.
69. In Annex D of the Access to Bandwidth statement,
Oftel discussed how charges for shared co-location should be set. The
conclusion was that charging should be on an average cost basis. This
could be done either through a system where the first operator in the
room pays the full costs and subsequent operators pay the first operator,
or a system where BT adjusts the charge to reflect the number of operators.
The second of these options would appear to be the simpler to administer.
Co-location
licence fee
70. BT has proposed that operators who choose
to physically locate in a BT exchange will be charged a licence fee
involving a charge for the dedicated co-location space and a charge
for rental associated with use of the MDF.
71. The methods by which BT values its property
are contained in the Detailed Valuation Methods (DVM). The area inside
BTs exchange buildings is often much greater than the space required
to house BTs equipment. This is because these buildings were designed
to house relatively old equipment. New equipment requires a smaller
footprint. To take account of this effect, BT values its buildings on
the basis of the current footprint occupied. This means that BT does
not receive a return on its investments in unoccupied space. This is
justified because this space is not used in providing services to customers.
However, if an operator wished to rent space from BT that was currently
unoccupied it would seem appropriate for BT to receive a rental based
on market rates which reflected the space occupied.
72. One potential problem with BTs proposal
to charge the market value for rental would be that it would allow it
to recover the costs of fully depreciated buildings again. Oftel believes
that not allowing BT to charge for either currently unoccupied space
or depreciated buildings could provide the wrong signals for investment
and could distort competition. However, allowing BT to recover these
charges could be discriminatory if BTs ADSL service is not required
to make a payment where the building is fully depreciated. It is Oftels
view that concern about discrimination between unbundled loops and BTs
ADSL serivce outweighs concerns about providing incorrect signals for
investment. BT should therefore set its rental charges to be equal to
the lower of the charges paid by its own ADSL service and the properly
assessed cost of the space occupied.
73. BT proposes that the general rental charge
for use of the MDF will be included in the licence fee and charged for
on a building by building basis. Oftel can see some benefit to this
proposal, in that it allows charges to better reflect the underlying
costs. However, it would also be possible to include the general rental
charge in the annual rental charge for the loop. This would have the
advantage of allowing operators greater certainty over their cost base.
Including this charge in the annual rental for the loop would also allow
Oftel to determine this charge prior to launch of the service.
74. Oftel is of the view that operators taking
unbundled loops should have knowledge of the licence fee before making
a decision about co-location. To this end, BT should publish a list
of the licence fee charges for each exchange building prior to operators
making a decision about co-location. If this were to take place, the
uncertainty caused by the general rental charge being included in the
licence fee would be alleviated.
Co-location set-up
and on-going costs
75.
BT has proposed that all co-location set-up charges should be treated
as bespoke, either because of geographical differences or as a result
of allowing operators to choose the features of any co-location area.
The bespoke nature of costs, BT argues, prevents it from producing a
standard price list for co-location. While Oftel recognises that some
costs will vary in this way, it is concerned that the lack of a standard
price list will cause uncertainty for operators. In addition, operators
will not be in a good position to judge the reasonableness of any charges.
76. Oftel considers that these concerns could be met
in two ways. Firstly, operators could be allowed to either propose their
own sub-contractors for the work or could have access to the full documentation
associated with the tendering process. Oftels view is that it
would be impractical for BT to deal with a large number of sub-contractors,
but that it would be practical for BT to supply documentation to operators
taking unbundled loops. Secondly, BT could produce a standard price
list for room build. This may not cover all items, but Oftel believes
that it should be possible to produce a standard price list for items
such as the cost of caging material or the cost of floor covering.
77. BT has proposed that an operator choosing to physically
locate in a BT exchange will pay both a specific and a general annual
maintenance charge. An operator choosing distant co-location will only
pay the general annual maintenance charge.
78. BT argues that a general maintenance charge is
required because whether or not an operator is physically co-located,
the operator is using the MDF, and the MDF requires a building that
must be maintained. Oftels initial view is that it is reasonable
for BT to charge for maintenance of the size of building that is required
for the CCA footprint of the MDF.
79. However, Oftel feels that there is an issue about
how BT recovers this cost. As with the general rental charge BT proposes
to include in the licence fee, BTs proposal has the advantage
that charges will better reflect the underlying costs. However, there
is again the alternative for including this general maintenance in the
annual rental of the loop. This has the benefit of allowing pre-determination
of the charge and aids operators to have certainty of costs and increases
transparency. As with the general rental charge, the issue of uncertainty
could be alleviated if BT were to publish a list prior to launch of
the service that includes the general rental charge for each building.
80. One issue that has not been addressed in BTs
proposals is the charge to operators if BTs construction of co-location
facilities leads to BT being required to remove asbestos from the building.
One could argue that operators should pay for the cost of removing asbestos
because their decision to co-locate has caused the cost of removing
the asbestos. However, one could also argue that BT would be the long-term
beneficiary of the removal of asbestos from its buildings, since BT
will benefit from future use of the asbestos-free area and its removal
is likely to increase the value of the buildings. Thus one might assume
that it is likely that BT would want to arrange for asbestos disposal
at some stage for its own purposes. On this basis Oftels view
is that BT should meet the cost of removing asbestos.
Co-location -
the charge for power
81.
BTs proposal is that operators in any exchange building pay the
standard rate for electricity charged by the electricity company supplying
that building. The main issue here is whether there is a significant
difference between the standard rate and the rate that either BT is
offered or that an operator could obtain if it were to purchase power
separately. If there is, BT may be significantly over-recovering power
costs. One factor that could prevent over-recovery is that BT has also
proposed that this rate apply to BT generated power if BT were to choose
to switch away from the electricity company supply for a period of time.
It is not clear to Oftel whether this power is more or less expensive
to supply than the standard charge. If it is more expensive, and is
used for a significant proportion of time, then the standard charge
may not lead to over-recovery. While BT was using the electricity company
it would be over-recovering, but while BT was using its own power it
would be under-recovering.
82. Oftel is of the view that more investigation is
required into this area in order to establish whether BTs proposal
would lead to over-recovery.
Back to contents
Oftels
initial conclusions
83.
Oftel has made an initial analysis of the principles underlying BTs
pricing proposals. Oftel is of the view that while BTs proposals
are generally reasonable, they do raise some areas of concern.
Charge for the
loop
84. Oftel
is of the initial view that:
- BTs proposals
could lead to it over-recovering the costs of drop wire for existing
loops. This should be remedied by removing this charge from the price
levied for existing loops. However, BT should be able to recover the
cost of new drop wires where these are needed to create spare pairs
or new loops. Oftel is of the initial view that BT should include
a capitalised charge for drop wire in the annual rental of new
loops.
- BT should reflect
its capital improvement programme through the CCA value of the loop.
- BT should include
an estimate of the repair costs in the annual rental charge for the
loop. If BT does not currently have the information available to do
this specifically for unbundled loops, it should include the repair
costs allocated to its existing loops. This would be reviewed if more
information were to become available.
- BT should deal
with DACS and non-compatible NTEs by averaging these costs over all
metallic paths and including the cost in the annual rental charge.
Internal tie
cable
85.
Oftels initial conclusion is that recovery of system set-up costs
through an annual charge for internal tie cables is not appropriate.
This treatment of system set-up costs will reduce transparency, and
will also bring forward the time at which operators contribute to the
system set-up costs. Instead, system set-up costs should be recovered
through charges for the metallic path facility. This charge should be
included in the connection charge for individual loops.
Co-location
86.
Oftels initial conclusions on co-location are that:
- It is reasonable
for operators to expect BT to set up general co-location areas without
the need for a joint request. The charge should be set on the basis
of average cost with rental charged only for the space occupied by
the operator.
- Oftel considers
it reasonable that BT should set its rental charges to be equal to
the lower of the charges paid by its own ADSL service or the properly
assessed cost of the space occupied.
- The two options
for recovery of the general rental charge and the general maintenance
charge are to charge separately for these items or to include them
in the annual rental charge for the loop. Oftel can see advantages
to each option.
- It would be reasonable
for operators to expect some transparency about the costs of room
build. This could be achieved either by a standard price list or through
access to tender documents.
Back
to contents
Consultation
87. Oftel seeks
the views of operators, service providers and consumers on the initial
views contained in this consultation document by Tuesday 22nd
June 2000. It is intended that a document setting out Oftels final
views on pricing principles is published in July 2000.
Views and comments should be made in writing and sent to:
Penny Hierons
Economic Adviser
Regulatory Policy Directorate
Oftel
50 Ludgate Hill
London, EC4M 7JJ
Tel: 020 7634 8972
Fax: 020 7634 8848
Alternatively, please
email
Written comments
will be made publicly available in Oftels Research and Intelligence
Unit except where respondents indicate that their response, or parts
of it, are confidential. Respondents are therefore asked to separate
out any confidential material into a confidential annex which is clearly
identified as containing confidential material. In the interests of
transparency, respondents are asked to avoid confidentiality markings
wherever possible. Appointments to view written comments in Oftels
Research and Intelligence Unit, which must be made in advance, can be
arranged by ringing: 020 7634 8761.

Back
to contents
|