IPStream
to DataStream Migration / Equal terms for DataStream
Complainants:
Tiscali UK Limited and Thus plc
Complaint against: BT
Case opened: 15 August 2003 (submitted to Oftel on 4
June 2003)
Relevant instrument: The Director intends to resolve
the dispute under Chapter 3 of Part 2 of the Communications
Act 2003 as from 25 July 2003. In resolving this dispute, to
the extent the Director decides to consider the matter retrospectively
and in relation to any period before 25 July 2003, he intends
to do so under regulation 6 of the Telecommunications (Interconnection)
Regulations 1997, by virtue of paragraph 22 of Schedule 18 of
the Communications Act 2003.
Update
note - 4 December 2003
This dispute
involves a request to determine a reasonable charge for BT's
IPStream to DataStream migration product. The market definitions
and access obligations imposed under the Communications Act
2003 which relate to this issue are currently being considered
as part of the wholesale broadband market review. Therefore,
in the interests of efficient resource allocation and regulatory
certainty, this dispute will be dealt with following the conclusion
of the wholesale broadband market review consultation.
As a result,
the dispute will not be concluded within four months from the
date Oftel accepted the dispute. Therefore the dispute will
not be handled within Oftel's standard dispute resolution timetable
as set out in the Oftel and Radiocommunications Agency document
Dispute resolution under the new EU Directives (http://www.oftel.gov.uk/publications/eu_directives/2003/eud0203.htm).
The Director considers that the circumstances surrounding this
dispute are exceptional circumstances and that, in accordance
with Section 188(5) of the Communications Act 2003, Oftel is
not bound by the requirement to resolve this dispute in four
months. However, the Director is aiming, at present, to complete
his investigation and resolve this dispute by the end of April
2004.
Issue
Tiscali and Thus have requested that BT make available a reasonably
priced automated migration product for migration from IPStream
to DataStream. Tiscali and Thus allege that the proposed price
for IPStream to DataStream migrations is too high, and does
not reflect actual costs of provision. Further, it has been
alleged that BT is obstructing customer migration by imposing
excessive network downtime, refusing to work at off-peak times
to minimise disruption or to automate the process such that
it operates effectively.
Tiscali
and Thus have also requested that BT align the minimum contract
terms for IPStream and DataStream.
Background
At present, operators who want to move users across from IPStream
to DataStream are required to cancel an existing service and
place a new order with BT, which incurs the standard connection
charge and results in more downtime for the end user. It has
been alleged that BT is obstructing customer migration by imposing
excessive network downtime, refusing to work at off peak times
to minimise disruption or to automate the process such that
it operates efficiently.
BT has indicated
that it is developing an automated service for IPStream to DataStream
migrations. However, Tiscali and Thus argue that the proposed
target price (£30) is neither fair nor reasonable for
the following reasons:
1. The proportion
of migrations which would incur re-jumpering is smaller than
suggested by BT;
2. Even where re-jumpering is required at BT's exchanges, BT
could reduce the costs associated with the migrations by processing
operators' orders in bulk;
and
3. BT has charged £50 for activiations since the IPStream
service was launched, and the actual costs to provide this service
must have decreased over time as the proportion of connections
has increased. It is suggested that BT's recent offer of a reduced
activiation charge of £25 for IPStream demonstrates that
the actual cost to deliver the service is probably much lower
than £50.
In addition,
Thus and Tiscali argue that BT is discriminating in favour of
IPStream against DataStream by offering a one month minimum
contract term for IPStream, compared to three months for DataStream.
BT has argued
that there is no dispute, as it is developing an automated migration
process, and discussions with Tiscali and Thus are continuing.
Further, BT argues that the assumptions underlying Thus and
Tiscali's claim that the proposed migration charge is unreasonable
are flawed. BT has also argued that both issues fall outside
the Interconnection Regulations.
The Director
considers that there is clearly a failure for the parties to
reach agreement regarding the pricing of a migration product,
and on the minimum term for DataStream, and therefore proposes
to investigate this dispute as set out below. He considers that
this dispute concerns interconnection and is in relation to
Network Access and therefore falls within his powers to resolve.
Scope
of the dispute
To determine whether BT is obstructing customer migrations between
IPStream to DataStream. As part of this assessment, Oftel will
examine whether BT should be required to provide an automated
migration product for migrations between IPStream to DataStream.
If the Director
concludes that BT should be obliged to make such a product available,
the Director will determine a reasonable price for both single
migrations and bulk migrations.
The Director
will also determine whether the minimum term for DataStream
should be aligned to the minimum term for IPStream.
Procedural
matters
The resolution of the dispute is subject to the procedures set
out in the joint statement by Oftel and the Radiocommunications
Agency "Dispute resolution under the new EU Directives"
of 28 February 2003.
All representations
on the scope of the dispute should be submitted to Oftel by
27 August 2003.
Stakeholders
interested in the outcome of this dispute should notify Oftel
by 27 August 2003 describing the relevance of the outcome of
the dispute to their business.
Stakeholders
with relevant information and evidence in respect of this dispute
should submit this to Oftel by 10 September 2003.
Case
Leader: Ruth Gibson (020 7634 8976 e-mail:
ruth.gibson@oftel.gov.uk)
Case Reference: CW/00626/06/03