9
October 2002
Contents
Introduction
Glossary
References
History
Introduction
1. The purpose of
this document is to provide criteria as mentioned in Condition 20 of
the Public Telecommunications Operator (PTO) licence, and related guidance.
A draft version of this document was the subject of a public consultation
by Oftel. After carefully considering the responses received during
this consultation, Oftel formally adopted this final version of the
document.
2. Licence Condition
20.5 states that:
"The Licensee
shall ensure that any restrictions imposed by it on access to and
use of its Fixed Public Telephone System on grounds of maintenance
of network integrity, in order to protect, inter alia, network equipment,
software or stored data are kept to the minimum necessary to provide
for normal operation of the System."
and Licence Condition
20.6 states that:
"The Licensee
shall ensure that any restrictions imposed by it on access to and
use of its Fixed Public Telephone System on the grounds of network
security or network integrity are proportionate, non-discriminatory,
and based on objective criteria identified in advance."
3. This document
should be considered in conjunction with its sister Oftel document Guidelines
on the essential requirements for network security and integrity.
4. An overview of
network management principles is provided together with a set of seven
example event types where restriction of access to the fixed public
telephone system might be applied. Criteria, objectives and influencing
factors are considered in each situation. It is the intention that these
examples should provide the basis for action in most anticipated situations,
but they are not intended to be exhaustive. Inevitably, these examples
are based on public switched telephone network (PSTN) technology. However,
the principles in this document apply to fixed public telephone systems
and are independent of the technologies used in these systems. For the
avoidance of doubt, these could include IP or other packet-based systems.
The term fixed public telephone system is defined in the PTO licence.
Legal status
5. These criteria
do not affect the scope of the licence conditions listed in this document
or any others. The Director General will take the criteria into account
in applying the relevant conditions in licences, and give reasons if
they are departed from. The Director General cannot legally fetter his
discretion and retains the ability to depart from the criteria where
the circumstances warrant it. The criteria are therefore not legally
binding on the Director General.
6. These criteria
will be subject to review and amendment following consultation with
interested parties in the light of experience of their operation, of
development in telecommunications markets and of any changes to UK or
European Community law.
Restriction of
service via the application of network management controls and actions
Network management
concepts
7. Network management
embraces a number of broad areas, including:
- network surveillance;
- fault management;
- network operation
and administration;
- statistical data
collection; and
- network traffic
management.
8. Network management
is used to optimise existing network usage and to make it possible to
detect and reduce the negative effects of fault and overload situations
in the network.
Restrictive
controls
9. Manual call gapping
– can be applied on a per route or destination number basis. This can
be based on digit length depending on circumstances. The call gap length
may be varied, typically from 0.1 seconds to infinity, depending on
how many calls can be processed at the delivery point.
10. Call gapping
applied on a route basis is usually used to protect a target unit from
an influx of calls when no particular dialled number is causing the
problem or in the first instance before a target destination number
is identified. The gap can be set to the necessary time interval to
control the situation.
11. There should
be an ability to apply manual call gapping either directly onto the
switch concerned using a man machine interface (MMI) or indirectly using
an intermediate ‘front end’ system.
12. Expansive control
actions are not considered within the scope of the document.
Control criteria
13. To aid the consistent
approach to the application of restrictive network controls, criteria
indicating under what circumstances these controls should be applied
must be detailed to aid those involved in network monitoring and control
activities.
Answer seizure
ratio (ASR)
14. This is defined
as the number of calls, having left the outgoing side of the exchange,
that have been successful in returning an answer signal.
15. Within the generality
of this document it is recognised that it is not possible to define
'normal' levels of ASR. This must be determined from historic performance
data.
Congestion
16. This can be
defined as either internal to an exchange (ie originating, terminating
or transit exchange), or route based where a lack of circuit capacity
is experienced
17. Within the generality
of this document it is recognised that it is not possible to define
‘normal’ levels of congestion. This must be determined from historic
performance data.
Event criteria
18. The following
section of the document offers a range of scenarios that network operators
may experience where they may need to consider restricting the volume
of call traffic across the network or taking other action to preserve
network security and integrity.
19. The list of
events is not definitive and the events/examples themselves should not
be considered mutually exclusive. Oftel acknowledges that in some cases,
there may be additional unforeseen circumstances that a network operator
should take into account when determining the necessary course of action.
However, Oftel considers that any such action to restrict access to
the network on the basis of security and integrity should always adhere
to the principles of proportionality and non-discrimination, and should
use the scenarios outlined in this document as a starting point for
determining what type of action might be appropriate.
20. Event type
one: Pre-planned and notified network event
|
Event
|
|
Where prior
notification of a network event, eg a 'phone-in' has taken place.
Prior notification should be in line with operations and maintenance
(O&M) Handbook standard and received at least two days prior
to the event.
Prior notification
would typically include the scale of the event, expected call
volumes, anticipated call holding time, number of answering positions,
method used to answer the calls (ie manual or automatic), etc.
Where the
event is running as planned, with expected additional call volumes
and no perceived threat to the integrity of the network.
|
|
Objective
|
|
To provide
control where there is a known risk to either the operator's own
network or to the network of another operator caused by the volume
of calls to a target number.
|
|
Criteria
|
|
These would
typically be evidenced by higher levels of congestion on a particular
routeing to a specific number than would normally be expected
at that particular time of day or night. Lower than expected ASR
may also be experienced. Control levels should be based on the
information provided by the customer hosting the event. This will
typically include:
- the method
to answer the calls, manual or automatic;
- the number
of Operators or answering positions/lines etc; and
- the duration
of the call – typically longer where financial pledging is involved.
Controls,
generally in the form of ‘manual call gapping’ should be applied
to the number string concerned.
Experience
shows that typically the control should seek to deliver four times
the answer handling capacity of the system used to receive the
calls, based on the number of positions (if manual answering)
and/or length of predicted call holding time.
For calls
terminating in the network of another operator, control actions
may need to be considered at gateway points of interconnect and
potentially, for larger events, nearer to the source generating
the call volumes eg the local exchange.
Controls should
be designed to maintain levels of service as near to normal as
possible in terms of the ASR received by other network users.
The applied control should also seek to ensure that there is no
risk to services delivered to the emergency organisations, etc.
|
|
Influencing
factors
|
|
These criteria
assume the following:
- prior notification
is in line with O&M recommendations;
- the correct
level and range of information has been provided in the notification,
and it is accurate;
- call volumes
remain as anticipated at the preplanning stage eg ASR and congestion
in line with expectations;
- controls
will seek to meet two objectives, i) protecting operators’ networks
and ii) meeting the needs of the organisation running the event;
and
- if the
estimates of key traffic parameters provided by prior notification
are not sufficiently accurate, this event shall be treated as
a type two event (see below).
|
21. Event type
two: Focused network overload
|
Event
|
|
This is the
counter scenario to that described in event type one
In this instance,
one or a combination of the following may apply:
- the event
is not previously notified in line with the O&M standard;
- the applied
control algorithm is incorrect or the event is not running to
the anticipated level of the pre-planned notification material;
and/or
- the situation
is unexpected or is developing in an unexpected way.
|
|
Objective
|
|
The objective
is to rapidly gain control of the situation whilst gaining a greater
understanding of the event in order to implement more appropriate
controls.
The difficulty
will be gaining an understanding of what is happening and knowing
at what point and at what level controls need to be applied.
|
|
Criteria
|
|
Events of
this type would typically be evidenced by:
- higher
levels of congestion; and
- lower ASR
to a particular routeing to a specific destination or area code,
than would normally be expected at that particular time of day
or night.
Network alarm
and fault data should also be considered.
Controls in
this instance should be applied as follows:
- at a level
to allow adequate network control to be gained, typically based
on either time or call volume restriction;
- data gathering
should continue and controls should be adjusted in line with
new data; and
- to prevent
the spread of congestion both to other network elements in the
owning operator's network or to the network of other operators.
Controls may
in the first instance be predominantly route based eg all calls
carried by the route in question, with the exception of 999/112,
until the target numbers are identified.
|
|
Influencing
factors
|
|
Dependent
on the situation presented, controls should be applied on a proportionate
but ‘hit hard and rein back’ basis to gain initial control of
the situation If applicable, automatic congestion controls would
be driven by this type of scenario.
Controls should
be applied for the shortest possible time, whilst investigating
the root cause.
Exchanges
in difficulty or overload may also bring into operation automatic
call shedding controls to enable processors to continue to operate
and ensure that at least some calls can be processed. In this
instance operators’ peripheral equipment and terminals may also
be subject to restricted access, which may in turn deny operators
the ability to gain control.
Congestion
and ASR levels should be monitored and the controls adjusted accordingly.
Close co-operation
between operators is essential in these instances to minimise
the impact in both networks.
|
22. Event type
three: Major network incident or failure
|
Event
|
|
Network incidents,
failure and disasters.
Incidents
of this type would include:
switch failure;
specific
platform failure;
difficulties
between different platform technologies; and
large scale
national or international problems eg flooding, hurricane, earthquake
or civil disturbance.
|
|
Objective
|
|
The objective
is to restrict traffic levels to the target exchange, platform
or area of the network to aid a graceful recovery of the switch
or platform concerned.
In the case
of national or international disaster the objective is to restrict
calls with minimal chance of completion whilst maintaining service
to the remainder of the network.
|
|
Criteria
|
|
Events of
this nature are evidenced by:
- higher
levels of congestion than normal; and
- a lowered
ASR.
Restrictive
controls should be applied to the target number(s) or number group(s),
or on a route basis at all exchanges feeding the target exchange.
Control types
will be manual call gapping (destination or route) based typically
on time intervals or call volumes and will be dependent on the
level of granularity available to the operator applying the controls.
Control levels
should be sufficient to offer graceful recovery and to gain control.
Performance should continue to be monitored and controls adjusted
accordingly.
|
|
Influencing
factors
|
- Control
levels should be determined through open discussion between
the operators involved on a network manager to network manager
basis, including operators abroad in the case of international
problems. Influencing factors are the normal level of expected
ASR;
- the normal
levels of expected congestion;
- the impact
on customer service; and
- interactions
with other network elements and operators.
|
23. Event type
four: Planned works or upgrades
|
Event
|
|
Network planned
works or upgrades, where a known engineering-based action is to
take place.
This is a
key element within network operations as networks continue to
become more complex and interrelated in nature.
|
|
Objective
|
|
To maintain
as near normal level of service as is reasonably possible under
the conditions of the outage.
|
|
Criteria
|
|
Network outages
should be planned taking the following factors into consideration:
- time of
day that the outage is targeted – ‘peak’ or busy periods should
be avoided;
- impact
on customers;
- potential
risk to life cases;
- the need
to give prior notification to other operators that may be affected;
and
- the need
to give prior notification to customers where appropriate.
Any restriction
of access to the network based on a planned network outage should
be kept to the minimum necessary consistent with carrying out
the required upgrade or maintenance activity.
|
|
Influencing
factors
|
|
In some cases
end users may be temporarily denied access to the network due
to necessary engineering based outages. Due consideration should
be given to the criteria specified above to minimise customer
impact.
Restrictive
controls may be necessary within an operator’s network to prevent
calls routeing to equipment that has been taken out of service.
The need to
maintain service at near normal levels wherever practicable.
|
24. Event type
five: Signalling system 7 protocol error
|
Event
|
|
SS7 protocol
error, where the network restriction affects a connected operator.
The following
is an example of such an event.
The incorrect
implementation of SS7 protocol on an interconnect link can cause
calls to ‘black hole’ (fail to route) or cause damage to the receiving
network. On receipt of ‘transfer prohibited’ (TFP) from a signalling
transfer point (STP) in a pair (maybe due to link outage on the
destination network) An originating network should respond by
sending further messages to the other STP of the pair. It should
then periodically send ‘route set test’ (RST) message to the unavailable
STP until such time as the previously unavailable STP sends ‘transfer
allowed’ (TFA) indicating that it is ready for service again.
If the originating
switch has an incorrect protocol implementation causing it to
ignore TFP and to continue to attempt call set-ups, then the calls
will black hole. The receiving network also risks message overload
and element failure.
|
|
Objective
|
|
Minimise the
potential for damage to the receiving network. This may lead to
disconnection of the ‘offending’ link or linkset.
Prevent calls
from failing to route and thereby reducing QoS performance and
causing customer complaints in the originating network.
Fix the protocol
error and restore service.
|
|
Criteria
|
|
Specific to
this example: Where STP working is used on an interconnect link,
compliance with BSI PD6639:2001 message transfer part (MTP) protocols
is crucial. To qualify for interdiction, the receiving network
must be in a position to prove that the protocol failure has occurred.
Proof may be obtained, for instance, by use of stand-alone protocol
analysers or SS7 probes.
Generically:
There are a number of situations where incorrect use of SS7 protocol
can cause a network to fail. An operator wishing to disconnect
from an ‘offending’ interconnect link must be in a position to
provide proof of the protocol violation, both to justify the disconnection
and to aid recovery of the situation
Wherever practicable,
the first step will be to attempt dialogue between the interconnected
parties. If a solution is not readily achievable and the network
is at significant risk, immediate temporary disconnection may
be considered, even without prior dialogue. Following disconnection,
urgent steps should be taken to initiate dialogue.
|
|
Influencing
factors
|
|
Where disconnection
of a link or linkset is undertaken as an action, the duration
of disconnection will be the minimum necessary to restore or maintain
service.
|
25. Event type
six: Denial of service to end users on grounds of network security or
integrity
|
Event
|
|
Operator denies
service to end users on grounds of network security or integrity.
|
|
Objective
|
|
To prevent
end users adversely affecting network integrity or security, or
from causing other related adverse effects for fellow end users.
|
|
Criteria
|
|
Operator has
previously notified end users that behaviour adversely affecting
network integrity or security, or causing other related adverse
effects for fellow end users may result in disconnection. It is
recognised that it may be inadvisable to give specific details
of such behaviour in advance.
Operator has
objective evidence that the end user is responsible for jeopardising
network security or integrity to a material extent, and is likely
to continue to do so in the future unless steps to deny service
are taken. Evidence may be in the form of, for example:
- switch
records;
- call trace
details;
- call logs;
- customer
complaints, etc.
Operator has
attempted to open a dialogue with the end user, and if possible
has encouraged the end user to voluntarily cease problematic behaviour.
Operator has
attempted to give the end user notice of impending denial of service
and has attempted to explain what the end user could do to prevent
this happening. Best efforts have been made to give an opportunity
to respond.
Operator has
considered any mitigating circumstances of which it is aware before
taking the decision to deny service.
Operator would
take similar steps in similar situations with other end users
on a non-discriminatory basis.
|
|
Influencing
factors
|
|
Due to the
overall impact on the network and the risks to security or service
to others, it may not always be possible or desirable to proceed
through the above in a sequential, stepped order. However all
of the above steps should at least be considered as part of the
overall process before denial of service is implemented.
|
26. Event type
seven: Risk to network physical security caused by another operator
or service provider
|
Event
|
|
Network physical
security is jeopardised by another operator or a service provider,
and operator seeks to restrict physical access to its network
by the responsible party/ies as a result.
|
|
Objective
|
|
To ensure
network physical security is not materially adversely affected.
|
|
Criteria
|
|
Operator has
previously informed all relevant operators or service providers
of behaviour likely to jeopardise the physical security of the
network. It is recognised that it may not always be advisable
to give details of all such behaviours.
Operator has
objective evidence that network physical security has been jeopardised
by the other operator or service provider ('the responsible party/ies')
in the past, and is judged likely to be on an on-going basis.
There is a pattern of systematic failure to respect the physical
security of the network.
Operator has
attempted to open dialogue with the responsible party/ies, and
has given the party/ies the opportunity to respond.
Operator has
given notice of its intention to restrict physical access to the
network, and has indicated to the other party/ies what assurances
are required to prevent this.
Operator's
action in restricting access to the network is proportionate to
the risk being caused by the responsible party/ies.
Operator would
take similar steps in similar situations with other responsible
party/ies on a non-discriminatory basis.
|
|
Influencing
factors
|
|
Due to the
overall impact on the network and the risks to security or service
to others, it may not always be possible or desirable to proceed
through the above in a sequential, stepped order. However all
of the above steps should at least be considered as part of the
overall process before denial of service is implemented.
Particular
consideration should be given to the potential impact and risk
where local loop unbundling (LLU) is deployed. Similarly the impact
of the access network facilities agreement should be considered.
|
General comments
on network restriction example scenarios
27. All of the foregoing
examples rely heavily on the co-operation of those involved in managing
the event and the open information that they can share with other Operators
affected by the incident or who may need to be involved in the pre-planning
stages.
28. There is an
over-riding element that surrounds the protection of 999/112 service
during the periods when restrictive controls are in place. This will
generally be in relation to circuit reservation levels and protection
bit application in network configuration data.
29. Circuit reservation
is the ability in network configuration data to specify the number of
circuits on a route that will be reserved for 999/112 traffic in the
event of route based congestion. It may be possible to specify this
on local-to-main switching units and main-to-main (trunk-to-trunk) routes.
Similarly the protection bit is a message header assigned to certain
call types (in data) that offers the ability to circumvent call controls
such as destination and route gapping.

Glossary
Abbreviations
ASR – Answer Seize
Ratio
LLU – Local Loop
Unbundling
MMI – Man Machine
Interface
MTP – Message Transfer
Part
NICC – Network Interoperability
Consultative Committee
O&M – Operations
and Maintenance
PSTN- Public Switched
Telephone Network
PTO – Public Telecommunications
Operator
QoS – Quality of
Service
RST – Route Set
Test
RVTD - Revised Voice
Telephony Directive
SS7 – Signalling
System 7
STP – Signalling
Transfer Point
TFA – Transfer Allowed
TFP – Transfer Prohibited

References
There are no references
in this document.
History
|
Issue
|
Date
|
Notes
|
|
Draft
|
December 2001
|
For inclusion
in consultation document.
|
|
Issue 1.0
|
October 2002
|
Incorporates
comments received during consultation.
|


|