Contents
Direction
Explanatory
Memorandum
Chapter
1 Summary
Chapter
2 Background
Chapter
3 Responses to the draft direction
Chapter
4 The Director’s final decision and reasons
Direction
relating to a dispute between Carrier1 UK Ltd and British Telecommunications
plc
Direction
pursuant to Condition 45.2 of the Public Telecommunications Licence
granted to British Telecommunications plc and Regulation 6(6) of the
Telecommunications (Interconnection) Regulations 1997
WHEREAS
1. The Secretary
of State granted to British Telecommunications on 22 June 1984 a licence
(‘the BT licence’) under section 7 of the Telecommunications Act 1984
(‘the Act’) for the running of telecommunications systems specified
in that licence;
2. By virtue of
section 109 of, and paragraph 20 of Schedule 5 to, the Act the BT licence
has effect as if granted to British Telecommunications plc (‘BT’);
3. The Secretary
of State granted to Carrier1 UK Ltd (‘Carrier1’) a licence under Section
7 of the Act for the running of telecommunications systems as specified
in that licence;
4. On 1 January
1998 the Interconnection Directive 97/33/EC came into force and was
implemented in the UK through the Telecommunication (Interconnection)
Regulations 1997 (‘the Regulations’) and conditions in the licences
of operators;
5. Carrier1 entered
into a Standard Interconnect Agreement with BT on 17 August 1998;
6. During 2001 BT
invoiced Carrier1 for payment of annual charges relating to BT’s Flat
Rate Internet
Access Call Origination (‘FRIACO’) Product;
7. Carrier1 disputed
a proportion of these charges;
8. Carrier1 referred
this dispute to the Director General of Telecommunications (‘the Director’),
in a letter of 17 January 2002. First, Carrier1 requested that the Director
determine the precise point at which the Digital Local Exchange (‘DLE’)
FRIACO virtual path charge becomes applicable. Second, Carrier1 asked
the Director to determine whether it was obliged to pay the annual pre-paid
charges where circuits are not activated and the DLE FRIACO virtual
path never used, or the ability to obtain a refund or rebate (adjusted
if appropriate) of the annual prepayment where circuits are ceased or
cancelled during the annual period;
9. For the reasons
given in these recitals and set out in more detail in the Explanatory
Memorandum to this Direction, and having considered the representations
made in response to the draft of this Direction published on 16 May
2002, and the matters set out in Regulation 6(8) of the Regulations,
the Director believes that it is appropriate to make this Direction.
THEREFORE
Pursuant
to Condition 45.2 of the BT Licence and Regulation 6(6) of the Regulations
the Director General of Telecommunications makes the following Direction:
1.
The provision of the DLE FRIACO virtual path by the Licensee to Carrier1
shall be deemed to have become active on the Ready for Service Date
(as defined in the Licensee’s standard interconnect agreement) or 30
days after the Ready for Test Date (as defined in the Licensee’s standard
interconnect agreement) whichever is the earlier, of the associated
interconnect circuit.
2.
Circuits cancelled by Carrier1 before the earlier of, the Ready for
Service Date, or 30 days after the Ready for Test Date, shall not attract
a charge for any portion of the DLE FRIACO virtual path charge.
3. For circuits
ceased by Carrier1 after the earlier of, the Ready for Service Date,
or 30 days after the Ready for Test Date, the Licensee shall grant to
Carrier1 a proportionately adjusted rebate of the DLE FRIACO virtual
path charge. Such rebate shall apply irrespective of the period for
which the DLE FRIACO product has been utilised.
4.
The Licensee shall adjust the level of Carrier1’s disputed charges in
accordance with this Direction.
5.
Except as otherwise defined in this Direction:
5.1 paragraph 4
of the BT Licence shall, with the necessary changes, apply to this Direction
as it applies to the BT Licence; and
5.2 terms defined
in the BT Licence or in the recitals hereto shall have the same meanings
for the purposes of this Direction.
6.
Unless otherwise stated this Direction shall enter into force on the
date of its publication.
CHRIS
KENNY
DIRECTOR
OF COMPLIANCE
A person authorised
under Paragraph 8 of Schedule 1 to the
Telecommunications
Act 1984
11 July 2002

Explanatory
Memorandum
Chapter 1
Summary
1.1 The Director
General of Telecommunications ("the Director") has issued a Direction
pursuant to his powers under the Telecommunications (Interconnection)
Regulations 1997 ("the Regulations"), for the resolution of a dispute
between Carrier 1 and BT under the terms of their Standard Interconnect
Agreement ("SIA").
1.2 During 2000
and 2001, Carrier1 submitted Advance Capacity Orders to BT. During 2001,
Carrier1 cancelled certain orders for circuits. BT subsequently invoiced
Carrier1 for a total of (…) charges relating to the supply of Digital
Local Exchange ("DLE") Flat Rate Internet Access Call Origination
("FRIACO"). Of these charges, Carrier1 disputed (…1).
1.3 Carrier1 referred
this dispute to the Director in a letter of 17 January 2002. In summary,
Carrier1 requested that the Director issue a determination in relation
to:
- the precise point
at which a charge for the Digital Local Exchange ("DLE")
Flat Rate Internet Access Call Origination ("FRIACO") Virtual
Path becomes active; and
- Carrier1’s obligation
to pay the annual pre-paid charges where;
- circuits are
not activated and the DLE FRIACO Virtual Path is never used; or
- the ability to
obtain a refund or rebate (adjusted if appropriate) of the annual
prepayment where circuits are ceased or cancelled during the annual
period.
1.4 Following this
referral, the Director sought the views of the parties to the dispute
and considered the submissions made by Carrier1 and BT. The Director
issued a draft Direction in respect of these disputes on 16 May 2002
to the industry as a whole for consultation. Comments were requested
and have been taken into account in making a final Direction.
1.5 The details
of the submissions made in response to the draft Direction, together
with the Director’s reasons for making his decision are set out in Sections
3 and 4. In summary, the Director General concludes that:
- the disputed
charges for the provision of the DLE FRIACO Virtual Path to Carrier1
shall be deemed to have become active on the date that the associated
interconnect circuit is Brought into Service ("BIS"), or
30 days after the Ready for Testing Date ("RFT+30"), whichever
is the earlier;
- circuits cancelled
before the earlier of the BIS date or RFT+30 do not attract a charge
for any portion of the DLE FRIACO Virtual Path charge;
- for circuits
ceased after the earlier of the BIS date or RFT+30, Carrier1 shall
be entitled to obtain a proportionately adjusted rebate of the DLE
FRIACO Virtual Path charge, which will apply irrespective of the period
for which the DLE FRIACO product has been utilised; and
- BT will adjust
the level of Carrier1’s disputed charges as appropriate.
1.6 Having considered
the facts specific to this dispute and the matters set out in Regulation
6(8) of the Telecommunications (Interconnection) Regulations 1997, this
Direction, in the opinion of the Director, represents a fair balance
between the interests of the parties in each case, having regard to
the Director’s wider duties to the development of the Telecommunications
industry in the UK and the encouragement of adequate interconnection
in a way that provides maximum economic efficiency and gives the maximum
benefit to end users.

Chapter
2
Background
2.1 FRIACO is an
unmetered interconnection product available from BT that provides virtual
capacity from originating customers to the point of connection of an
Other Licensed Operator ("OLO"). An OLO may choose to purchase
FRIACO at Digital Local Exchanges ("DLE FRIACO") or at tandem
switches ("ST FRIACO").
2.2 The creation
of this product stemmed from a dispute between MCI WorldCom plc ("WorldCom")
and BT, which was referred to the Director in December 1999. WorldCom
complained that BT was supplying unmetered products to consumers, without
making available a comparable wholesale product which would enable its
competitors to provide equivalent unmetered products. The Director subsequently
made a determination on 26 May 2000 requiring BT to provide the FRIACO
product.
Dispute
referred to the Director
2.3 Carrier1 referred
this dispute to the Director in a letter of 17 January 2002. Carrier1
stated that:
(i) it should
be entitled to cancel or cease unwanted DLE FRIACO circuits in accordance
with Carrier1’s interpretation of Annex A to BT’s Standard Interconnect
Agreement;
(ii) the payment
of the DLE FRIACO Virtual Path charge by Carrier1 to BT should be
applicable from the date of Service Activation (and not from RFT
+ 30), being the date of activation of the circuits and from which
service is provided, in accordance with Schedule 393 of BT’s Standard
Interconnect Agreement;
(iii) where
Carrier1 has cancelled or ceased circuits in advance of the date
of Service Activation, it should not be obliged to pay the DLE FRIACO
Virtual Path charge;
(iv) where circuits
are cancelled or ceased after Service Activation, an operator should
be entitled to obtain a rebate of the DLE FRIACO Virtual Path charge,
appropriately adjusted where necessary, in accordance with the determination
that the Director made on 26 May 2000 following the referral of
a dispute by MCI Worldcom;
(v) the cancellation
or cessation of the unwanted DLE FRIACO circuits should be deemed
to have occurred on dates requested in the relevant cancellation
orders, being the date that Carrier1 initially sought to cancel
the circuits, and that accordingly Carrier1 should be under no obligation
to pay the DLE FRIACO Virtual Path charge or, where appropriate,
that the rebate from BT to Carrier1 should reflect this accordingly.
2.4 On 13 February
2002 Carrier1 International S.A. announced that Ernst & Young LLP
had been appointed by the High Court as administrators of Carrier1.
The administrators confirmed that they wished to continue with the dispute.

Chapter 3
Responses to the draft Direction
3.1 The main arguments
submitted by interested parties in response to the draft Direction are
summarised below.
BT
3.2 BT agreed with
the Director’s proposed decision on when the DLE FRIACO Virtual Path
shall become liable for rental charges, and considers that it will encourage
sensible ordering behaviour and encourage Operators to submit Data Management
Amendments (‘DMA’) at the same time as ordering a link to carry FRIACO
traffic.
3.3 BT acknowledged
that it is required to provide proportionally adjusted rebates on unused
portions of FRIACO charges, and has provided for this rebate in its
amended FRIACO offer to industry. In response to further correspondence
from the Director, BT has confirmed that this rebate is calculated on
a daily basis.
3.4 BT also acknowledged
that it is required to remove any minimum contract period in relation
to the ordering of the FRIACO product, and has done so in its amended
offer to industry.
Carrier1
3.5 Carrier1 confirmed
that it is largely in agreement with the Director’s proposed decision
as set out in the draft Direction. However, Carrier1 urged the Director
to reconsider the decision regarding the point at which charges for
the DLE FRIACO Virtual Path become applicable. Carrier1 considered that
charges for the DLE FRIACO Virtual Path should become applicable at
the date when the circuits are actually activated, being the date from
which service is provided, rather than the earlier of the BIS date or
RFT+30.
3.6 Carrier1 stated
that BT has been inconsistent in advice to Carrier1 regarding when charges
become active, and refers to conflicting correspondence from BT on this
matter. Carrier1 argued that this correspondence demonstrates that BT’s
initial analysis of the key issues was the same as Carrier1’s.
3.7 Carrier1 also
stated that it refused to pay the disputed charges for a number of different
reasons, not just on the basis that no traffic had flowed. However,
Carrier1 did argue that it should not have to pay for the service where
it is not in a position to use it.
3.8 Carrier1 responded
to BT’s arguments in relation to the contractual provisions which BT
relies upon to support its position that charges for the DLE FRIACO
Virtual Path become active at the earlier of BIS or RFT +30. BT argued
that this position has long been established in Schedule 130 of the
SIA, and is also included in Schedule 396 of the SIA, which governs
the supply of Single Tandem (‘ST’) FRIACO. Carrier1 argued that BT is
construing Schedule 130 of the SIA incorrectly. Carrier1 argues that
Schedule 130 provides for the payment of connection charge, and stated
that the DLE FRIACO Virtual Path charge is not a connection charge.
3.9 Carrier1 further
asserted that even if the DLE FRIACO Virtual Path Charge were a connection
charge, then in accordance with clause 9.13.1 of Schedule 130, charges
for it should fall due on the date of the commencement of service. Carrier1
argued that this is consistent with clause 5.1 of Schedule 393 of the
SIA, where it is stated that service is to commence on a date to be
mutually agreed in writing. Carrier1 stated that it would be unfair
for BT to rely upon Schedule 396 to support its position regarding the
supply of the DLE FRIACO Virtual Path to Carrier1.
AOL
3.10 AOL asked Oftel
to use the principle being proposed in the draft Direction to clarify
how existing FRIACO circuits, which have been paid for one year in advance,
can be refunded for regulated price cuts that occur during the course
of that year.
Energis
3.11 Energis supported
the Director’s proposals set out in the draft Direction regarding the
point at which charges for the DLE FRIACO Virtual Path become applicable,
and the obligation to pay annual pre-paid charges where circuits are
not activated, or the ability to obtain a refund or rebate (adjusted
if appropriate) of the annual prepayment where circuits are ceased or
cancelled during the annual period.
3.12 However, Energis
considered that the Director’s proposals as set out in the draft Direction
would benefit from further clarification.
3.13 Energis stated
that further clarification was required on what exactly is meant by
a proportionately adjusted rebate. It argued that in order for equivalence
to be achieved for metered and unmetered FRIACO, proportionate adjustments
for ceased circuits should be applied on a daily basis.
3.14 Energis was
also concerned about the time period which applies to a request for
cessation of a FRIACO Virtual Path. In correspondence from BT to Energis
subsequent to the issuing of the draft Direction, BT advised Energis
that when a FRIACO Virtual Path is to be ceased, that cessation will
occur 30 working days after receipt of written notification. Energis
considered that a 5 working day notification period would be more appropriate.
3.15 Energis further
stated that when cancelling or ceasing a FRIACO Virtual Path service,
the associated interconnect link should be left in place. In correspondence
from BT to Energis subsequent to the issuing of the draft Direction,
BT stated that when a FRIACO service is ceased the corresponding interconnection
link must also be ceased.

Chapter 4
The Director’s
decision and reasons
4.1 The Director
has analysed all the representations made by the parties to the dispute,
as well as those representations made by other interested parties. Carrier1
has submitted two principal issues for the Director to determine. The
first concerns the exact time at which charges for the DLE FRIACO Virtual
Path become applicable, and the second relates to the obligation to
pay pre-paid charges or obtain a rebate in respect of the DLE FRIACO
Virtual Path.
The
point at which charges become applicable
4.2 The arguments
submitted by Carrier1 in response to the draft Direction do not diverge
from those proposed in its initial submission on this matter. Carrier1
has made representations in relation to when a charge for the DLE FRIACO
Virtual Path becomes active, and has stated that this charge should
be applicable when the associated interconnect circuit is activated,
being the date upon which it is intending to provide service across
this circuit. Furthermore, Carrier1 argues that this interpretation
is in line with Schedule 393 of the SIA.
4.3 Carrier1’s arguments
regarding the interpretation of BT’s relevant contractual information,
and also the lack of clarity regarding these contractual provisions,
have been considered. For example, Carrier1 refers to condition 5.1
of Schedule 393 of the SIA, which provides for commencement of service.
However, while Condition 5.1 does dictate when service is to commence
across a circuit, it does not outline when charging is to commence.
4.4 As BT argues,
the principle which outlines when charging is to commence is explicitly
outlined in Schedule 396 of the SIA, which governs the supply of ST
FRIACO. BT has already taken action to ensure that these terms are explicitly
incorporated into Schedule 393 of the SIA. The Director has noted Carrier1’s
concerns regarding BT’s conflicting advice on the issue of when a charge
for the DLE FRIACO Virtual Path becomes active, but considers that BT’s
action to clarify Schedule 393 should ensure that the charging arrangements
for the DLE FRIACO Virtual Path are now sufficiently transparent.
4.5 Therefore the
Director’s position on this matter remains the same as set out in the
draft Direction, as the Director still does not consider that Carrier1’s
interpretation of these contractual provisions would be consistent with
what would be a reasonable charging arrangement. The Director’s reasoning
behind this decision is set out below.
4.6 As set out in
the draft Direction, when assessing when a charge becomes active, BT
refers to the Ready for Test date and the BIS date. The term ‘BIS date’
has the same meaning as the ‘Ready for Service Date’. The Ready for
Test Date is the date on which capacity at the associated interconnect
link is ready for testing, and the BIS date is the time when the circuit
is ready to be used by an OLO. In this context BIS is the date when
the associated interconnect link is ready for an OLO to commence service.
The circuit cannot become operational until the completion of DMA. It
is BT’s responsibility to implement the DMA, but it first requires data
to be submitted by an OLO.
4.7 It is therefore
clear that in this process both parties (ie BT and an OLO) have the
ability to influence when service commences. It is important that the
principle that governs when a charge becomes active balances the legitimate
interests and responsibilities of the parties involved.
4.8 On certain occasions,
an OLO’s use of a new interconnect circuit is dependent on whether it
has secured the necessary business from its ISP customer. In this scenario,
an OLO can withhold the DMA until it has secured its ISP business. The
circuit would not become operational (BIS) until the DMA order has been
made, and until this time traffic would not flow along the FRIACO Virtual
Path. If this were the case, the circuit would not be brought into service
and BT would run the risk that although it had endeavoured to
provide the circuit, and incurred costs in so doing, an OLO would not
be liable for the DLE FRIACO Virtual Path charge. In this scenario an
OLO would effectively control when the charge became active.
4.9 In addition
to the scenario outlined in paragraph 4.8, another scenario might be
where BT experienced delays in implementing DMAs, and therefore took
more than 30 days to provide the interconnect circuit. If this were
the case, it would be unreasonable to expect an OLO to become liable
for the DLE Virtual Path charge when an OLO was not in a position to
utilise the DLE FRIACO Virtual Path due to delays by BT. In this scenario
BT would effectively control the completion of the work required before
the circuit could be used by an OLO.
4.10 A fair balance
has to be struck between the interests of an OLO seeking to purchase
capacity from BT, and the arrangements that BT has to make in order
to provide the requested capacity. Requests for capacity must obviously
be based on the most accurate capacity and sales forecasts available.
Clearly the purchase of capacity contains an element of risk, as OLOs
must forecast effectively in order to ensure that the correct amount
of capacity is obtained.
4.11 The Director
considers that if a charge for the DLE FRIACO Virtual Path were to become
applicable only when an OLO commences service, it would mean that OLOs
could submit artificially inflated capacity orders, in the knowledge
that no extra risk would be incurred as a result. Circuits could be
cancelled by OLOs on the basis that traffic had not flowed, and this
would transfer risk to the wholesale provider.
4.12 The Director
does not consider that it would be fair to expect the wholesale provider
to expend resources in keeping a DLE FRIACO Virtual Path open for third
parties without some degree of remuneration, as it is potentially forgoing
revenue from other parties.
4.13 Furthermore,
and as set out in paragraph 4.4, charging on the earlier of RFT+30 or
the BIS date is consistent with established practice for other similar
services, in particular ST FRIACO. In that context this rule is clarified
more explicitly, as charging commences at the Ready for Service Date
of the associated interconnect link, or 30 days after the Ready for
Test Date of the related interconnect link, whichever is the earlier.
The Director considers that a charge becoming active on the basis of
the earlier of RFT+30 or the BIS date represents a fair balance, as
long as BT has in place the appropriate mechanisms to implement DMAs
on a reasonable timescale. If it became clear to the Director that the
principle of the DLE FRIACO Virtual Path charge becoming active on the
earlier of RFT+30 or the BIS date were inappropriate on account of unreasonable
delays by BT in implementing DMAs, the Director would review the suitability
of this principle.
Additional
representations made by interested parties
4.14 As set out
in section 3, Energis submitted certain representations regarding the
point at which charges for the DLE FRIACO Virtual Path become active.
The representations that Energis made in this regard are outside the
scope of this Direction, as they concern issues on which the Director
was not asked to determine.
Obligation
to pay/rebate
4.15 In response
to the draft Direction, BT stated that it would offer a rebate on unused
portions of FRIACO charges, and that this rebate would not incorporate
any minimum contract period. BT has also confirmed that this proportionately
adjusted rebate would be calculated on a daily basis, which addresses
an issue that Energis raised in response to the draft Direction. In
conclusion, the Director considers that BT’s rebate addresses Carrier1’s
concerns in this regard.
4.16 In response
to the draft Direction, and as set out in section 3, AOL asked the Director
to clarify how existing FRIACO circuits, which have been paid for one
year in advance, can be refunded for regulated price cuts that occur
during the course of the year. However, this aspect of AOL’s response
is outside the scope of the matters that the Director was asked to determine,
and so this representation will not be addressed in this document.
The
Director’s decision
4.17 Having
considered the arguments for and against Carrier1’s request, the Director
is directing that:
- the disputed
charges for the provision of the DLE FRIACO Virtual Path to Carrier1
shall be deemed to have become active on the date that the associated
interconnect circuit is Brought into Service ("BIS"), or
30 days after the Ready for Testing Date ("RFT+30"), whichever
is the earlier;
- circuits cancelled
before the earlier of the BIS date or RFT+30 do not attract a charge
for any portion of the DLE FRIACO Virtual Path charge;
- for circuits
ceased after the earlier of the BIS date or RFT+30, Carrier1 shall
be entitled to obtain a proportionately adjusted rebate of the DLE
FRIACO Virtual Path charge, which will apply irrespective of the period
for which the DLE FRIACO product has been utilised; and
- BT will adjust
the level of Carrier1’s disputed charges as appropriate.


|