Issued
by the Director General of Telecommunications
Contents
Direction
Summary
Chapter
1 – Background
Chapter
2 – Responses to the consultation
Chapter
3 – Functionality of the Intelligent Network for FRIACO
Chapter
4 – The Director’s decision and reasoning
Chapter
5 – Proposals for industry discussion
Annex
A – List of respondents
Annex
B – Glossary
Direction
under the provisions of Regulation 6(3) of the Telecommunications (Interconnection)
Regulations 1997 regarding the Intelligent Network Charge for Flat Rate
Internet Access Call Origination
WHEREAS:
A) The Secretary
of the State granted to British Telecommunications on 22 June 1984 a
licence (the "Licence") under section 7 of the Telecommunications
Act 1984 (the "Act") for the running of the telecommunication systems
specified in Annex A to the Licence;
B) By virtue of
Section 109 of, and paragraph 20 of Schedule 5 to, the Act, the Licence
has effect as if granted to British Telecommunications plc ("BT");
C) On 26 May 2000
the Director issued a direction (the ‘First Direction’) under Regulation
6(6) of the Telecommunications (Interconnection) Regulations 1997 (the
"Regulations") requiring BT to enter into an agreement with MCI
Worldcom plc relating to the provision of Flat Rate Internet Access
Call Origination ("FRIACO"). The First Direction specified
in paragraph 4.3 that BT may make a reasonable additional charge for
any Intelligent Network ("IN") or Signalling Transfer Point
("STP") signalling services provided by BT for the purpose
of using the FRIACO service and for any service provided under paragraph
8 of the First Direction;
D) On 15 February
2001 the Director published a second direction (the "Second Direction")
amending the First Direction by inserting inter alia new paragraphs
9 and 11 to require BT to make Single Tandem FRIACO available from its
tandem exchanges;
E) On 15 May 2002
the Director published a third direction (the ‘Third Direction’) which
amended paragraph 4.3 of the First Direction to enable BT to make a
reasonable additional charge for any IN or STP signalling services provided
by BT for the FRIACO services required to be provided under the First
Direction as amended by the Second Direction (the ‘IN Charge’);
F) BT, in accordance
with Condition 45 of the Licence, has entered into interconnection agreements
with a number of Operators regarding the provision of FRIACO. The term
"Operators" in this direction shall refer to those operators that have
entered into such an interconnection agreement with BT. The terms of
those agreements reflect the terms as set out in the First Direction
as amended by the Second and Third Direction;
G) Following a complaint
made by Cable and Wireless UK Services Limited and Energis plc the Director
has been investigating the level of the IN Charge made by BT. The Director
has reached the conclusion, following responses to the consultation
on the draft Direction referred to in Paragraph K below, that BT shall
be permitted to make a charge of £42 per 64kbit/s circuit per annum
for the IN with effect from 1 August 2001 to 31 May 2002, and with effect
from 1 June 2002, BT shall not be permitted to make any IN or STP Charge;
H) The Regulations
inter alia implement Directive 97/33/EC on interconnection in telecommunications
with regard to ensuring universal service and interoperability through
application of the principles of open network provision (the ‘Directive’);
I) Regulation 6(1)
of the Regulations provides that the Director shall encourage and secure
adequate interconnection in the interests of all users and that he exercises
his functions in a way that provides maximum economic efficiency and
gives maximum benefit to end-users having regard to the matters set
out in Regulation 6(1)(a) to (g) of the Regulations.
J) Pursuant to Regulation
6(3) of the Regulations the Director may intervene at any time, in order
to make a direction specifying issues which must be covered in an interconnection
agreement, or to make a direction that specific conditions be observed
by one or more parties to such an agreement. The Director may in exceptional
circumstances make a direction that changes be made to interconnection
agreements already concluded where it is justified to ensure effective
competition or interoperability of services for users or both;
K) A draft of this
direction and the explanatory memorandum were published on 4 April 2003
and comments invited by 7 May 2003;
L) Comments were
received from a number of interested parties and these have been considered
by the Director.
THEREFORE
the Director, pursuant
to Regulation 6(3) of the Telecommunications (Interconnection) Regulations
1997 makes the following direction:
1. With effect from
1 June 2002 BT shall not be permitted to make any charge for Intelligent
Network or Signalling Transfer Point signalling services provided by
BT to the Operators for the purposes set out in Paragraph 4.3 of a direction
issued by the Director on 26 May 2000 as amended by directions published
on 15 February 2001 and 15 May 2002 (the ‘Consolidated Direction’).
2. With effect from
1 August 2001 to 31 May 2002 BT shall be permitted to make a charge
of £42 per 64kbit/s circuit per annum for Intelligent Network services
provided by BT to the Operators.
3. Paragraph 4.3
of the Consolidated Direction shall be revoked.
4. BT and the Operators
shall amend their interconnection agreements relating to the provision
of FRIACO to give effect to this direction by 28 days from the date
of this direction.
5. In respect of
any IN charge repayable by BT to the Operators in accordance with this
direction, BT shall pay to the Operators the amount repayable together
with interest calculated in accordance with paragraph 13.13 of the Standard
Interconnection Agreement.
6. The terms defined
or described in the recitals to this direction shall have the meaning
so defined or described. All other words or expressions used in this
direction shall have the same meaning as in the Directive, the Regulations,
the Act or the Licence as appropriate.
Chris Kenny
Director of Compliance
A person authorised
under Paragraph 8 of Schedule 1 to the Telecommunications Act 1984
21 July 2003

Summary
S.1 In May 2000,
the Director-General of Telecommunications (the ‘Director’) issued a
Direction relating to a dispute between British Telecommunications plc
(‘BT’) and MCI Worldcom plc (‘Worldcom’) requiring BT to provide Flat
Rate Internet Access Call Origination (‘FRIACO’) (the ‘First Direction’).
A copy of the First Direction is at www.oftel.gov.uk/publications/internet/fria0500.htm.
In the First Direction, the Director also permitted BT to make a reasonable
additional charge for the use of the Intelligent Network (the ‘IN’)
to route FRIACO calls. The additional IN charge was permitted as the
Director accepted that in comparison to calls to numbers in blocks of
10,000, the routing of FRIACO calls to numbers in blocks of 1,000 required
additional switch decode (switch resource required to analyse the dialled
number in order to route a call). This switch decode was not available,
and the use of BT’s IN was one method of carrying out the additional
processing that was required. The First Direction was subsequently amended
by further directions of 15 February 2001 and 15 May 2002.
S.2 Following a
complaint made by Cable and Wireless UK Services Limited (‘Cable and
Wireless’) and Energis plc (‘Energis’) the Director has been investigating
the level of the IN charge made by BT. The Director has reached the
conclusion that BT should not be permitted to make any charge for the
IN. A Draft
Direction (the ‘Draft Direction’) to that effect was published for consultation
on 4 April 2003. In the explanatory memorandum accompanying the Draft
Direction, the Director set out his understanding that the shortage
of switch decode was no longer a concern, as the situation was remedied
in July 2001 when there was an increase in the efficiency of use of
the existing switch decode. On the basis of this increase in resource
available, and both current and future forecast demand for FRIACO, the
Director provisionally concluded that sufficient switch decode exists
to enable FRIACO calls allocated in 1,000 number blocks to be delivered
without necessitating the use of the IN.
S.3 In the explanatory
memorandum accompanying the draft Direction, the Director also addressed
BT’s arguments that the IN was necessary to protect the Signalling Transfer
Point (‘STP’) network from focussed overload. It had been argued by
BT that the volume of call attempts that could be generated by its Digital
Local Exchanges (‘DLEs’) was greater than could be handled by BT’s STP
network. This was because the STP network originally deployed by BT
was not a purpose built STP network, but was based on System X switches
which were no longer required as Digital Main Switching Units (‘DMSUs’).
However, BT deployed purpose-built STPs in November 2001, which have
sufficient throughput to be able to handle any load likely to be generated
by the DLEs.
S.4 The Director
also considered further arguments made by BT that the IN plays a central
role in the management of network congestion. In particular, in relation
to the protection of DLEs from local overload and the protection of
interconnecting networks from focussed overload. The Director was not
persuaded that use of the IN dip to control congestion represented a
necessary or proportionate response to any specified problem. Therefore,
the Director provisionally concluded that the justification for an IN
charge fell away after November 2001, when the purpose-built STPs were
deployed.
S.5 BT has made
a number of further representations in response to the Draft Direction,
particularly with regard to the comparison between a switch based design
and use of the IN in relation to the protection of DLEs from local overload.
The Director now accepts that the use of an inferior algorithm as the
basis for call gapping prior to May 2002 prevented BT from adopting
a switch based design. However, since the end of May 2002 when the algorithm
was improved, it has been possible for BT to provide a comparable service
using call gapping. Therefore, the Director concludes that since the
end of May 2002, the use of the IN to route FRIACO calls has not been
necessary to protect the DLE from local overload. Accordingly, the Director
is removing BT’s right to make an additional charge for use of the IN
to route FRIACO calls, with effect from 1 June 2002.
S.6 The Director
notes that it was necessary for BT to use the IN to route FRIACO traffic
until the end of July 2001, due to the shortage of switch decode available
at that time. However, for the period 1 August 2001-31 May 2002, the
Director accepts that BT needed to use the IN for FRIACO as it was unable
to apply a switch based solution due to the limitations of the algorithm
in use at one particular type of DLE. However, as it was necessary for
BT to upgrade the algorithm on one type of DLE only, the Director has
considered the proportion of DLEs where it was necessary to upgrade
the algorithm in order to adopt a switch based design. The Director
believes that for that period, the charge made during that period should
be applicable only to the proportion of DLEs which required the upgrade
of the algorithm to adopt a switch based design. Accordingly, the Director
concludes that BT should make an adjusted charge of £42 per 64kbit/s
circuit for the use of the IN for FRIACO calls with effect from 1 August
2001 to 31 May 2002, based on a weighted average using the proportion
of the DLEs as weights.
S.7 Although this
investigation was initiated by a complaint from Cable and Wireless which
was later supported by Energis, the Director considers that there is
not an existing dispute between Cable & Wireless or Energis and
BT within the meaning of Regulation 6(6) of the Telecommunications (Interconnection)
Regulations 1997 (the ‘Regulations’). Therefore, the Direction is made
using the Director’s powers under Regulation 6(3) of the Regulations,
with consideration of the matters set out in Regulation 6(1) of the
Regulations. In particular, under Regulation 6(1) of the Regulations
the Director, in exercising his functions under the Regulations, shall
encourage and secure adequate interconnection in the interests of all
users, exercising his responsibility in a way that provides maximum
economic efficiency and gives the maximum benefit to end-users, and
in doing so shall have regard to, inter alia, the need to stimulate
a competitive market.
S.8 If BT was allowed
to charge above the efficiently incurred cost of providing the FRIACO
service, competition between BT and the purchasers of FRIACO in downstream
markets would be distorted. Therefore, preventing BT from doing this
is necessary to ensure effective competition to the benefit of end users.
S.9 Therefore pursuant
to Regulation 6(3) of the Regulations the Director directs that BT shall
no longer have the right to make a charge for the use of the IN to route
FRIACO calls with effect from 1 June 2002. Furthermore, the Director
directs that BT shall make an adjusted charge of £42 per 64kbit/s circuit
per annum with effect from 1 August 2001 to 31 May 2002. Thus BT will
be required to repay all purchasers of FRIACO the IN charge paid since
1 June 2002, together with the refund of the difference between the
adjusted charge and what was charged in relation to the period from
1 August 2001 to 31 May 2002, plus interest in accordance with paragraph
13.13 of the Standard Interconnection Agreement.
S.10 In addition,
it is noted that the cost of signalling required for FRIACO circuits
is reflected in the price of a 2Mbit/s IEC (Interconnection Extension
Circuit) link. Therefore, the Director also directs that BT shall no
longer have the right to make an additional charge for the use of its
STP network to route FRIACO calls. It is noted that BT has never made
an additional charge for use of STP signalling arrangements for FRIACO.
S.11 In relation
to ongoing congestion management issues, the Director wishes to encourage
wider industry discussions on the appropriate protection mechanisms,
and will take steps to facilitate a suitable forum for such discussions.

Chapter
1 Background
1.1 This chapter
sets out the background to the Direction. The period during which responses
to the consultation on the draft Direction were invited ended on 7 May
2003, and a list of respondents is set out in annex A. As set out in
the summary above, the consultation followed an investigation which
had been initiated by a complaint received from Cable & Wireless
on 30 March 2001, which was later supported by Energis in February 2002,
about BT’s additional charge for using the IN to route FRIACO calls.
Some service providers have also expressed concern about the level of
BT’s IN charge associated with FRIACO.
1.2 Set out below
is a brief history of FRIACO in the United Kingdom.
1.3 In December
1999, a dispute between Worldcom and BT (the ‘Dispute’) was referred
to the Director. WorldCom complained that BT was supplying unmetered
products to consumers, without making available a comparable wholesale
product which would enable its competitors to provide equivalent unmetered
services.
1.4 On 26 May 2000
the Director issued a direction relating to the Dispute requiring BT
to provide FRIACO (the ‘First Direction’).The First Direction required
BT to offer only DLE FRIACO, that is, wholesale flat rate internet access
from its local exchanges. This allowed those Other Licensed Operators
(‘OLOs’) interconnecting at the local exchange level to purchase wholesale
unmetered call origination in order to offer services to compete with
BT’s SurfTime internet products, launched on 1 June 2000. For those
OLOs which were interconnected at the DMSU, the Director required BT
to offer a service for the conveyance of internet traffic from each
enabled DLE to any Point of Connection of the OLO at the DMSU. BT fulfilled
this requirement by offering IECs.
1.5 Under paragraph
4.3 of the First Direction, BT was permitted to make a reasonable additional
charge for any IN or STP service provided by BT to the OLOs for the
purpose of using the FRIACO service. Paragraph 53 of the explanatory
memorandum of the First Direction explained that the IN was needed for
identifying the 1k number blocks allocated for FRIACO.
1.6 In addition,
paragraph 33 of the recitals to the First Direction explained that:
"the Director [has not] determined the charge for IN services since
he believes that, where possible, charges should be set by negotiation
between the parties. Nevertheless, he may intervene should BT’s charges
for IN capability give rise to dispute. BT will, therefore, be free
to provide such services on request and to charge for them. The Director
understands that BT proposes to charge £64 per 64kbit/s circuit for
IN capability. The Director also understands that, at present, BT takes
the view that all signalling charges are effectively included in the
price of a 2 Mbit/s IEC link and therefore does not propose to raise
additional charges for STP signalling where used."
1.7 However, as
the original request from WorldCom was for interconnection at the DMSU,
some aspects of the dispute remained unresolved. Following BT’s submission
that the expected increase in unmetered internet traffic would exceed
the capacity of the Public Switched Telephone Network, Oftel obtained
advice from technical experts on the options available to enable unmetered
interconnection at the tandem layer. The Director made a second FRIACO-related
Direction (the ‘Second Direction’), published on 15 February 2001, requiring
BT to make Single Tandem (‘ST’) FRIACO available from its tandem exchanges,
with the implementation occurring in stages (see the Second Direction
for details).
1.8 The Director
made a third FRIACO-related Direction, published on 15 May 2002 (the
‘Third Direction’). The Third Direction amended, inter alia, paragraph
4.3 of the First Direction to allow BT to make a reasonable additional
charge for any IN service provided by BT for ST FRIACO. This was simply
to bring the arrangements for ST FRIACO into line with DLE FRIACO and
was without prejudice to the outcome of this investigation (which was
ongoing in May 2002).
1.9 Although this
investigation was initiated by a complaint from Cable & Wireless
which was subsequently supported by Energis, the Director considers
that there is not an existing dispute between Cable & Wireless or
Energis and BT within the meaning of Regulation 6(6) of the Telecommunications
(Interconnection) Regulations 1997 (the ‘Regulations’). Therefore, the
Director has issued a Direction using his powers under Regulation 6(3)
of the Telecommunication (Interconnection) Regulations, having considered
the provisions of Regulation 6(1) of the Regulations.
1.10 Regulation
6(3) of the Regulations allows the Director to make a direction that
changes be made to interconnection agreements already concluded in exceptional
circumstances where it is justified to either ensure effective competition
or interoperability of services for users or both. Under Regulation
6(1) of the Regulations the Director, in exercising his functions under
the Regulations, shall encourage and secure adequate interconnection
in the interests of all users, exercising his responsibility in a way
that provides maximum economic efficiency and gives the maximum benefit
to end-users. In doing so the Director shall have regard to the matters
set out in Regulation 6(1) (a) to (g) of the Regulations. In particular,
sub-paragraph (b) of Regulation 6(1) refers to the need to stimulate
a competitive market.
1.11 Having investigated
the complaint made by Cable & Wireless (later supported by Energis),
the Director believes that for the reasons set out in this explanatory
memorandum it is justified in the circumstances to make a direction
under Regulation 6(3) removing BT’s right to make a charge for the IN,
with effect from 1 June 2002, and adjusting BT’s charge for the IN between
1 August 2001 and 31 May 2002. This is justified in order to ensure
effective competition. The Direction will enable purchasers of FRIACO
to buy the service at a price which reflects the efficiently incurred
costs of the service, which will encourage more effective competition
to the benefit of end users of unmetered internet access. Having considered
Regulation 6(1) the Director believes that to make such a direction
provides maximum economic efficiency and gives maximum benefit to end-users,
and is required in order to stimulate a competitive market.
1.12 In addition,
the Direction clarifies the position in relation to additional charges
for use of the STP network to route FRIACO calls. Notwithstanding the
provision which allows BT to make an additional charge for these services,
all the costs have in fact always been included in the charge for the
IEC link. The Director sees no reason why this will change in the foreseeable
future and therefore is amending the FRIACO directions referred to above
to remove the right to make an additional charge.
1.13 The structure
of this explanatory memorandum is as follows. Chapter 2 sets out the
responses to the consultation on the draft Direction. The functionality
of the IN for FRIACO is discussed in chapter 3, and chapter 4 sets out
the Director’s conclusion that to continue to allow BT to make an additional
charge for the IN would not be appropriate since it would prevent more
effective competition in internet termination and ultimately in unmetered
internet access from emerging to the benefit of end users. Furthermore,
it would lead to excessive charges and economic inefficiency which would
be contrary to the interests of end-users. For similar reasons, an additional
charge for STP, when the costs are recovered elsewhere, is not appropriate.

Chapter
2 Responses to the consultation
2.1 Oftel received
responses to the consultation on the Draft Direction from BT, Energis,
ntl, Thus, Tiscali, and NIACT. In addition, Oftel received two confidential
responses from service providers.
2.2 Non confidential
responses to the consultation can be viewed on Oftel’s website in the
Publications section under the classification Responses
to Oftel consultations. They can also be viewed at Oftel’s Research
and Information Unit. Appointments must be made in advance by phoning
020 7634 8761 or sending an e-mail
to infocent@oftel.gov.uk.
BT
2.3 In its response,
BT argued that technical functionality to implement a switched based
solution has existed only since May 2002, when the number of call gapping
slots was increased, the algorithm on System X switches (a particular
type of switch in BT’s local exchanges) was changed, and low rate gapping
became possible. However, BT argued that such a switch based call gapping
solution would provide a severely degraded quality of service to all
end users of FRIACO-based services and in extreme circumstances could
result in complete switch failure.
2.4 In particular,
BT stated that the IN controls prevent any high call rate incident focussed
on one OLO/ISP affecting calls to other OLOs/ISPs. BT stressed that
implementation of a FRIACO design incorporating call gapping would result
in increased end user impact and extended timeframes of disruption caused
by network incidents. It suggested that service disruption would be
experienced by all FRIACO operators and their ISPs in the event of a
network incident in another FRIACO operator’s network. BT further argued
that use of the IN was vital to meet its obligations under Condition
20 of its licence (which covers essential requirements and essential
public interests).
2.5 However, BT
later confirmed that although it believes an IN-based solution for FRIACO
offers congestion management advantages over a switch based solution,
some of the controls had not been implemented until very recently, therefore
it accepted that these advantages are unlikely to be as significant
as suggested previously.
2.6 The Director
welcomes BT's confirmation, as it provides support for the Director's
view that the use of the IN for FRIACO calls is not strictly necessary
and so BT should not be permitted to charge for it in addition to the
FRIACO virtual circuit charges. In the light of this statement from
BT, the Director does not consider it necessary to address all the detailed
technical points made in BT's published response in this explanatory
memorandum, although the main technical issues are discussed in chapter
3 below.
2.7 However, in
its response, BT also argued that it would be impossible to operate
IN and switch based solutions for FRIACO in parallel. If a switch based
call gapping solution was adopted for FRIACO, all OLOs would have to
migrate to that solution, regardless of whether they would be prepared
to pay for the higher quality of service offered by the IN.
2.8 The Director
does not accept the validity of this argument, but in any event, as
the Director emphasised in the explanatory memorandum accompanying the
Draft Direction, whether or not the IN will continue to be used for
FRIACO is a decision for BT. The Direction simply removes BT’s right
to make a reasonable additional charge as from 1 June 2002, and adjusts
the charge with effect from 1 August 2001 to 31 May 2002.
Cost recovery
issues
2.9 BT stated that
it has invested a significant sum in the IN to facilitate DLE grooming
for dial-IP services and FRIACO should recover a substantial part of
this investment. BT has stated that, if there were to be no charge for
the IN from December 2001, there would be a deficit to recover.
2.10 On the basis
of the evidence provided by BT on the unit costs of the IN and the number
of FRIACO ports in use in 2000-01 and 2001-02, the Director is not convinced
that the recovery of costs through the IN charge, or the deficit, is
of the magnitude that BT has stated. Indeed, as noted in the consultation
on the Draft Direction, since the actual usage of the IN by FRIACO circuits
was rather less than allowed for in the IN charge that is set by BT,
this might have resulted in over recovery of the costs.
2.11 BT has further
stated that investment was made in a Service Control Point (‘SCP’) pair
to support the IN for FRIACO, and that if BT were unable to make a charge
for the IN for FRIACO this would leave BT with a stranded asset.
2.12 The Director
clearly indicated in the consultation on the Draft Direction that since
the IN is part of a multifunction platform and can support many services
including FRIACO, any investment that would have been made would only
be considered as investment brought forward and would not necessarily
be stranded. In the recent consultation on the draft Direction, the
Director suggested that the cost of brought forward investment could
be relevant if certain conditions applied, although the Director provisionally
concluded that it appeared likely that at least one of the four conditions
did not apply. The conditions as set out for the consultation were:
(i) if BT needed
to expand the capacity of its IN platform in order to serve FRIACO
for the short run period of May 2000-November 2001;
(ii) if there
was a material cost of such additional capacity; and
(iii) if such
capacity would have been left unused for a material period of time
after November 2001 in the (hypothetical) scenario that BT had stopped
using the IN for FRIACO after that date. The growth over time in use
of the IN of other (ie non-FRIACO) traffic means that at most any
IN capacity installed for FRIACO would have represented an investment
brought forward.
(iv) if the investment
cost (if any) multiplied by BT's cost of capital for the period of
time such capacity was unused (if any) were materially larger than
the excess of FRIACO IN revenue over cost in the period May 2000-November
2001.
2.13 BT has not
provided the Director with any evidence to show that these four conditions
have been met, or to challenge the conditions. Therefore, the Director
concludes that the issue of brought forward investment is not relevant.
2.14 BT also raised
the issue of ongoing costs, but has not provided any details to substantiate
the argument. It should be noted that the Director has already taken
such ongoing costs into consideration as he has considered the fully
allocated costs when addressing the issue of cost recovery. BT has also
referred to STP probe capital costs. However, BT has not provided any
details to substantiate these costs.
2.15 BT has suggested
that if regulatory action is justified, then a mechanism such as a charge
control might be more appropriate, as this would not only encourage
efficient design network by BT, but also does not involve any necessity
for Oftel to engage in detailed network design exercises.
2.16 The Director
reiterates that while he has concluded that there is no justification
for a charge on the use of the IN for FRIACO, he has made no conclusion
on whether the IN should be used or not. The use of the IN should be
a commercial decision between BT and the operators. The Director has
not engaged in any network design operations or mandated any single
network design option.
2.17 Having made
the conclusion that there is no justification to charge for the IN,
the Director also believes that the use of a charge control is a totally
inappropriate method to require BT to refund the charges paid by operators
since 1 June 2002. This is because the level of the charge has never
been subject to price control and to include it within a basket for
regulated charges will distort the incentives that BT is given with
respect to the regulated charges. This would be economically inefficient
and reduce the benefits of the charge control mechanism.
2.18 BT has further
stated that it has incurred significant capital costs made specifically
to support STP signalling which have not been recovered yet. BT proposes
to introduce a cost oriented charge for the use of the STP network to
support narrowband data dial services, one of which is FRIACO.
2.19 The charges
for the use of STP signalling are currently reflected in the charge
for IECs. It is not clear to the Director what separate charge BT is
intending to make. However, should it wish to, the charge control mechanism
allows BT the flexibility to de-average the IEC charges in order to
separately charge for the cost of STP signalling, as long BT’s obligations
under the price cap are still met. In accordance with its obligations,
the Director expects BT to notify him about any changes it makes to
the IEC charges.
2.20 BT also argued
that the Director’s proposals to make retrospective changes to the FRIACO
IN charge, pursuant to Regulation 6(3), were inconsistent with the Director’s
reasoning made in the consultation on Charges for Emergency Service
(999) calls, published on 5 May 2003, which can be viewed at www.oftel.gov.uk/publications/pricing/2003/bt9990303.htm.
2.21 As explained
in the later Statement on 999 calls, which was published on 23 June
2003 (www.oftel.gov.uk/publications/pricing/2003/bt9990603.htm)
the Director did not have any power to consider retrospection to those
charges, as his intervention was not on the basis of ensuring effective
competition, but rather to ensure that the quality and security of the
emergency services is maintained. In contrast, the Director’s removal
of BT’s right to make an additional charge for use of the IN to route
FRIACO calls, and the adjustment of the charge between 1 August 2001-31
May 2002, are based on the need to ensure effective competition.
Energis
2.22 Although Energis
broadly welcomed the Director’s proposals, it argued that the IN charges
should be remedied retrospectively from July 2001 and not December 2001
or May 2002. The basis for this argument was that the charges were for
the express purpose of providing switch decode, and not as an interim
solution for protecting the STP network or for congestion management
purposes. Energis was concerned that the justification of these charges
sets a precedent which risks circumventing the normal contractual process,
as BT has not followed the proper procedures to discuss the functionality
of the IN with other operators. In particular, Energis has argued that
if any control was necessary, the process set out in the SIA should
have been followed by BT before any solution was imposed.
2.23 The Director
has carefully considered the appropriate date from which the Direction
should take effect, and has concluded for the reasons set out in chapters
3 and 4 below that the appropriate date for removal of BT’s right to
make an additional charge for use of the IN is 1 June 2002, and that
the appropriate period for an adjusted charge is 1 August 2001 to 31
May 2002.
2.24 Energis has
also argued that the Director would be acting beyond his regulatory
powers if he accepted that the use of the IN for FRIACO calls is justified
for congestion management control. Energis alleged that it would be
a disproportionate and unjustified extension of the charging regime
set out in the First Direction, as the original basis on which Oftel
permitted BT to make a reasonable additional charge for use of the IN
was that it was a necessary consequence of Oftel’s decision to allocate
FRIACO numbers in blocks of 1,000 numbers.
2.25 In the exercise
of his regulatory powers, the Director considers all relevant information
and evidence. In this case, although the original justification for
the IN charge was BT’s need to use the IN to route numbers allocated
in 1k blocks, the Director must also consider relevant evidence and
information which has come to light since the date of the First Direction.
This includes evidence on congestion management issues.
Ntl
2.26 Ntl welcomed
the Director’s proposals, but expressed concern about the delay which
occurred before the Director was made aware that the decode limitation
was no longer an issue. Ntl confirmed that during discussions with BT,
BT has never described the IN charge in terms of congestion management
or to aid number portability. Ntl suggested, that in the light of BT’s
assumption of a higher usage of FRIACO circuits than is the case, a
review of the other costs relating to FRIACO should take place.
2.27 The Director
notes this suggestion, but it is outside the scope of this current investigation.
The further suggestion from nlt that Oftel should have considered the
charges relating to other number blocks allocated to Operators at the
1,000 number block level also falls outside the scope of this Direction.
Thus
2.28 Thus supported
Oftel’s technical assessment of the capabilities of the IN platform,
accepting that it is not an essential feature required to support either
traffic routing or a network protection capability. However, Thus urged
the Director to widen the scope of the Direction to include all Number
Translation Services (NTS) and Surftime calls.
2.29 Issues relating
to NTS and Surftime fall outside the scope of this Direction.
Tiscali
2.30 Tiscali expressed
support for Oftel’s proposal to remove BT’s right to make additional
charges for use of the IN to route FRIACO calls and for STP signalling
services for FRIACO. Tiscali also believes that the proposal to make
this Direction effective from 1 December 2001 is fair, since the use
of the IN was no longer justified after November 2001.
2.31 However, Tiscali
has also requested Oftel to direct BT to pass on any rebates on FRIACO
to ISPs who contracted with BT to take Surfports.
2.32 As a general
matter of policy and practice, the Director does not direct third parties
who might benefit from any refund paid under the provisions of such
a direction to make rebates to their customers. That is a matter for
commercial negotiation between the parties concerned.
NIACT
2.33 From a consumer
point of view, NIACT welcomed Oftel’s proposals. NIACT believes that
the proposals will help stimulate competition, lower costs and overall
improve the services for telecommunications consumers.
Chapter
3 Functionality of the Intelligent Network for FRIACO
3.1 Intelligent
Networks have a wide variety of possible applications, from the routing
of complex call types (eg time of day routing), to the provision of
value-added call termination services using intelligent peripherals
(eg messaging services). Set out below is a summary of those applications
that BT has argued to be relevant to FRIACO.
Routing of numbers
allocated in 1k blocks
3.2 The original
justification given by BT for the use of the IN to route FRIACO calls,
and the basis on which Oftel permitted BT to make an additional reasonable
charge for use of the IN, was that it was a necessary consequence of
Oftel’s decision to allocate FRIACO numbers in blocks of 1,000 numbers.
3.3 Since 14 February
2000, Oftel has adopted a policy of allocating numbers for internet
services in blocks of 1,000 numbers rather than the 10,000 number blocks
previously used, and still used, for the majority of non-internet services
such as most calls to geographic numbers. This policy applies to all
new allocations of numbers for both metered internet services and unmetered
internet services using FRIACO, and has since been extended to some
other designated number ranges, for example, geographic numbers in conservation
areas. It is based on the need to conserve numbers and the experience
of the exhaustion of the 0906 and 0905 premium rate numbering ranges.
Oftel believes that allocating in blocks of 10,000 numbers may result
in the inefficient use of numbers, with ranges being exhausted within
a relatively short period of time.
3.4 DLEs have traditionally
routed calls by decoding the dialled number, one digit at a time, starting
with the most significant digit, and comparing the result with routing
tables stored on the switch. This process of ‘switch decode’ continues
until sufficient digits have been analysed for the routing of the call
to be uniquely determined.
3.5 If the number
of digits which must be analysed increases, this will result in an increase
in the amount of switch decode required at each DLE. If FRIACO numbers
had been allocated in blocks of 10,000, then it would only have been
necessary to decode the first six digits of the dialled number in order
uniquely to determine the owner of the number block, and hence route
the call. However, because FRIACO numbers are allocated in blocks of
1,000 it is necessary to decode the first seven digits of the dialled
number in order to route each call.
3.6 At the time
when FRIACO was introduced, BT was of the view that there was insufficient
switch decode at each of its DLEs to support the routing of FRIACO numbers
allocated in blocks of 1,000. BT therefore adopted an alternative solution,
which was to offload the detailed analysis of the dialled number to
an external processor. The external processor carries out the detailed
analysis of the called number and returns the required routing information
to the DLE. The specific solution adopted was based on BT’s existing
IN platform, under which the DLE acts as an IN Service Switching Point
(SSP), whilst the external processor and associated database constitute
an IN Service Control Point (SCP). This process is commonly referred
to as an ‘IN dip’.
3.7 At the time
the FRIACO service was launched in May 2000, Oftel accepted that in
comparison to calls to numbers in blocks of 10,000, such as the majority
of geographic numbers, the routing of FRIACO calls to numbers in blocks
of 1,000 required additional switch decode. This switch decode was not
available, and the use of BT’s IN was one method of carrying out the
additional processing that was required. Therefore, the Director permitted
BT to make a reasonable additional charge for use of the IN to route
FRIACO calls because of the additional processing required to route
calls where numbers are allocated in blocks of 1,000 numbers.
3.8 However, Oftel
understands that the shortage of switch decode is no longer a concern,
as the situation was remedied in July 2001 (although there was regular
dialogue with BT throughout the investigation, this information only
became apparent to Oftel in February 2003). On the basis of this increase
in resource availability and both current and forecast future demand
for FRIACO, the Director concludes that sufficient switch decode has
existed since 1 August 2001 to enable FRIACO calls to numbers allocated
in 1,000 number blocks to be delivered without necessitating an IN dip.
Congestion control
3.9 During the course
of the investigation, and in its response to the consultation, BT has
stated that the IN is not just required to route numbers allocated in
blocks of 1,000 numbers, but also plays a central role in the management
of network congestion. Oftel is unable to provide a detailed explanation
of BT’s arguments due to commercial confidentiality. However, the Director
has fully evaluated BT’s technical arguments, and his conclusions are
set out below.
3.10 BT has expressed
particular concern about the need to protect its originating network,
and possibly other operators’ transit networks, from overload conditions
triggered by the failure of a component in the terminating operator’s
network. Such a failure would be expected to trigger an unanticipated
mass call event, as subscribers attempt to re-establish their dial-up
connections to the internet. A mass call event triggered in this manner
may be particularly severe, due to the aggressive redial characteristics
associated with the software auto-diallers frequently used for internet
calls.
3.11 Oftel acknowledges
that the use of the IN dip for congestion has a number of benefits,
at least in principle. The use of the IN dip allows congestion controls
to be applied at the point of call origination, which is where such
controls will be most effective, whilst the use of an IN-based network-wide
call threshold represents a particularly effective solution to the problem
of focussed overload.
3.12 However, despite
these benefits, it is not obvious that the use of the IN dip to control
congestion represents a necessary or proportionate response to any specified
problem. BT’s Standard Interconnection Agreement specifies that interconnecting
operators agree appropriate network management procedures for congestion
management. Oftel understands that BT has not notified interconnecting
operators that it is using the IN dip for congestion control, and the
responses to the consultation support this position.
3.13 BT has identified
three specific congestion issues that are being addressed by its use
of the IN dip. These are described below.
Protection
of DLEs from local overload
3.14 One of the
main concerns expressed by BT is the need to protect its DLEs from overload.
BT has addressed this issue by limiting the rate at which IN queries
can be triggered from each DLE. This in turn limits the number of FRIACO
call attempts.
3.15 Oftel acknowledges
that this is a way of protecting the DLE from a local overload condition,
but also notes that it is closely equivalent to the permanent application
of call-gapping to FRIACO numbers. Since the use of permanent call-gapping
would not require the use of an IN dip, Oftel has discussed with BT
why this solution was not adopted.
3.16 BT has cited
three reasons why IN-based rate-limiting was preferred to permanent
call-gapping until the end of May 2002:
- BT argued that
only a limited number of call-gap slots were available until May 2002;
- BT argued that
it was impossible to apply a call-gap of less than one second until
May 2002; and
- BT argued that
the algorithm used by DLEs for call gapping could not have supported
FRIACO traffic until the end of May 2002.
3.17 Although the
Director provisionally concluded in the Draft Direction that none of
the reasons given by BT, as set out above, was a major constraint on
BT’s ability to control congestion using permanent call gapping, BT
has provided more detailed evidence in response to the Director’s proposals.
3.18 In particular,
BT has provided evidence on the algorithms used by DLEs for call gapping.
The algorithm which was initially used for call gapping was replaced
in a software rollout across all BT’s System X DLEs between early April
and the end of May 2002. BT has demonstrated to the Director’s satisfaction
that prior to the completion of that software rollout, the algorithm
previously deployed, while capable of protecting the DLEs, would have
caused an unacceptable level of call rejection on FRIACO calls even
under normal traffic loadings.
3.19 Having carefully
considered that evidence, the Director concludes that, until the end
of May 2002, it would not have been possible for BT to provide functionality
using a switch based solution which would have been comparable to the
functionality provided by the IN.
3.20 Therefore,
the Director concludes that there is a legitimate requirement to protect
DLEs from overload conditions, but that it has been possible for this
requirement to be adequately met since the end of May 2002 by the permanent
application of call-gapping. The ability to apply congestion controls
using call gapping is already available, and so this approach should
not require BT to incur any significant additional cost. The Director
is not seeking to require that BT should put call-gapping in place.
However, Oftel believes that OLOs should pay only efficiently incurred
costs of protecting DLEs from overload and hence concludes that there
is no justification for imposing the significantly higher IN charge
in this respect.
3.21 However, the
Director notes that BT only needed to upgrade the call gapping algorithm
on its System X switches. Therefore, the Director concludes that the
other DLEs would have been able to provide comparable functionality,
using call gapping, to the functionality provided by the IN, from 1
August 2001 (as the switch decode issue was resolved in July 2001).
As explained in the next Chapter, the Director is adjusting BT’s IN
charge for the period 1 August 2001-31 May 2002 to a weighted average
of the relevant charge for that period, to reflect this.
Protection
of the STP network from focussed overload
3.22 FRIACO was
one of the first services deployed by BT to make extensive use of a
STP network for interconnect signalling links. The benefit of this approach
is that it allows multiple operators to share signalling links to BT’s
DLEs. This is much more efficient than requiring every operator to maintain
dedicated signalling links to every DLE. However, a consequence of this
shared use of signalling links is that signalling congestion due to
a failure in one terminating operator’s network will impact on the quality
of service for all calls that use the shared signalling network.
3.23 The specific
concern raised by BT in discussion with Oftel, prior to the publication
of the draft Direction, was that the volume of call attempts that could
be generated by its DLEs, even after the local application of IN-based
rate-limiting, was greater than could be handled by its STP network.
This is because the STP network originally deployed by BT was not a
purpose-built STP network, but was based on System X switches which
were no longer required as DMSUs.
3.24 Prior to the
publication of the draft Direction, BT informed Oftel that its solution
to this issue was to use the IN to set a network-wide limit for the
number of calls that can be carried to each FRIACO operator. This ensures
that the aggregate volume of call attempts generated by all BT’s DLEs
does not exceed the capacity of the STP network. However, BT deployed
purpose-built STPs in November 2001. These have sufficient throughput
to be able to handle any load likely to be generated by the DLEs. Accordingly,
based on the information available at the time, the Director set out
in the draft Direction his view that there was a need to use the IN
to protect the STP network prior to November 2001 but not subsequently.
3.25. Having considered
the responses to the draft Direction, the Director has reached a different
view. Further information has shown that, while there may have been
a theoretical problem relating to the protection of the STP network
prior to November 2001, BT was not in practice using the IN actively
to manage this problem. Accordingly, the Director no longer believes
the issue of protection of STP network is relevant to considering whether
BT needed to use the IN in relation to FRIACO.
Protection
of interconnecting networks from focussed overload
3.26 BT has argued
that the use of the IN may also protect elements within the networks
of interconnecting operators from any overload condition.
3.27 Oftel acknowledges
that the use of the IN may provide a means of protecting interconnecting
operators’ networks, as well as the ISPs they serve. However, this does
not appear to be a consideration in BT’s current use of the IN overload
controls, since BT has not made any contact with interconnecting operators
in order to establish an appropriate threshold for the congestion control.
Indeed, BT has confirmed that such controls have only been implemented
very recently, and therefore any congestion management advantages of
the use of the IN appear not to have been realised. In any case, it
is the responsibility of interconnecting operators to manage congestion
within their own networks, rather than for BT to impose a solution.
3.28 Interconnecting
operators are free to enter into commercial negotiations regarding the
use of the IN dip for this purpose, if they wish to do so. The Director
concludes that, in the absence of such agreement between operators,
the use of the IN is not required to protect the networks of interconnecting
operators from overload conditions.
Number portability
3.29 During the
course of this investigation, BT has argued that the use of an IN dip
for FRIACO may also provide an efficient means of supporting number
portability in relation to FRIACO numbers.
3.30 The technical
implementation of number portability in the UK relies on the terminating
switch forwarding a call to a ported number, and this can be difficult
to implement in cases where the terminating switch is actually a modem
bank, as may be the case for FRIACO calls. Even where it is possible
for the terminating switch to forward calls, this tends to result in
calls being routed in an inefficient manner. An alternative approach
is to use an IN dip from the originating exchange to identify the destination
of each call, and then route accordingly.
3.31 Oftel acknowledges
the potential benefits of this approach to number portability, and has
set out its own proposals in this area (Proposals to change the framework
for number portability, 20 December 2002, www.oftel.gov.uk/publications/numbering/2002/nupo1202.htm).
However, Oftel also notes that the formal responsibility for the provision
of FRIACO number portability lies with the operator who owns the FRIACO
number block, and not with BT as an originating operator.
3.32 Interconnecting
operators are free to enter into commercial negotiations regarding the
use of the IN dip for this purpose, if they wish to do so. The Director
concludes that, in the absence of such agreement between operators,
the use of the IN is not required for the purposes of number portability
of FRIACO numbers.
Conclusion
3.33 The Director
has considered all the arguments made by BT as to why an IN charge is
justified to handle FRIACO traffic and has concluded that there is no
longer any justification for such a charge. Indeed, the Director has
concluded that the justification fell away after the end of May 2002.
3.34 When FRIACO
was launched the Director accepted the use of the IN was necessary because
of the shortage of switch decode in the DLE, however this problem was
remedied in July 2001. The Director also accepts that prior to the end
of May 2002, BT would not have been able to use a switch based solution
for FRIACO calls due to the limitations of the algorithm in use at BT’s
System X DLEs at that time. In respect of the other reasons provided
by BT during the course of the investigation as to why the use of the
IN is necessary for FRIACO traffic and so why an IN charge is justified,
the Director does not accept that any of these can justify the use of
the IN at BT’s current charges in the absence of commercial agreement
with other interconnecting operators in respect of those particular
matters. Accordingly, the Director is removing BT’s right to make an
additional charge for the use of IN to route FRIACO calls with effect
from 1 June 2002, and is reducing the charge with effect from 1 August
2001 to 31 May 2002. The next chapter discusses why this is appropriate
in the light of the Director’s technical analysis.

Chapter
4 The
Director’s decision and reasoning
Director’s decision
4.1 The Direction
removes BT’s right to make an additional charge for use of the IN to
route FRIACO calls with effect from 1 June 2002, and adjusts the charge
for the period 1 August 2001-31 May 2002. It also removes BT’s right
to make an additional charge for STP signalling services for FRIACO.
4.2. As explained
in the previous chapter, the Director has concluded that use of the
IN was no longer justified after the date when the call gapping algorithm
on BT’s System X switches was upgraded. BT has informed the Director
that this had occurred by the end of May 2002 and therefore this Direction
requires BT to repay all purchasers of FRIACO the IN charge paid since
1 June 2002, together with interest on the repayments in accordance
with Clause 13.13 of the Standard Interconnection Agreement.
4.3 In addition,
the Director has concluded that although the upgraded algorithm was
not installed at the System X switches until the end of May 2002, the
other types of DLEs would have been able to provide comparable functionality
to the functionality provided by the IN, from 1 August 2001 (as the
switch decode issue was resolved in July 2001). Therefore, the Director
is adjusting BT’s IN charge for the period 1 August 2001-31 May 2002,
to a weighted average of the relevant charge for that period, to reflect
the fact that the algorithm only needed to be upgraded on the System
X switches. This Direction requires BT to repay all purchasers of FRIACO
the difference between the IN charge paid in relation to the period
1 August 2001 to 31 May 2002, and the £42 per 64kbit/s circuit specified
in this Direction, together with interest on the repayments in accordance
with Clause 13.13 of the Standard Interconnection Agreement.
4.4 Further, BT’s
right to make an additional charge for STP signalling services for FRIACO
is removed, as signalling costs are reflected within the IEC charge.
The Director notes that BT accepted in May 2000 that all signalling
charges were effectively included in the price of a 2 Mbit/s IEC link
(see paragraph 33, the First Direction). The Director also notes that
currently, no such additional charge is made for STP signalling services
for FRIACO. By removing the right for BT to make an additional charge
for STP signalling services, the Director is therefore simply seeking
to clarify that no additional charges should be made for STP signalling
services.
Director’s reasons
4.5 As explained
in the previous chapter the Director has concluded that since the end
of May 2002 there has been no justification for using the IN to route
FRIACO traffic. The Director believes that the routing service that
the IN currently provides can be provided through the DLE by the increased
efficiency of use of switch decode which resulted from a switch software
development in July 2001. Similarly, protection of the DLE from overload
can be managed through permanent call-gapping at the DLE since the end
of May 2002. The Director also considers that BT has market power in
the relevant market (see below) and therefore for BT to charge in excess
of cost of providing FRIACO services (given that the use of the IN is
no longer justified) would adversely affect competition in the relevant
market to the detriment of end users.
4.6 Accordingly,
the Director considers that it is justified in this case to amend existing
interconnection agreements using his powers under Regulation 6(3) of
the Regulations to remove BT’s ability to make an additional charge
for the IN and STP signalling services for the purpose of FRIACO services,
in that to do so will ensure the development of effective competition
in the services using FRIACO. Further, having considered Regulation
6(1) of the Regulations the Director believes that to make such a direction
promotes maximum economic efficiency and maximum benefit to end-users,
and is necessary in order to stimulate a competitive market. In the
absence of the Direction BT would be effectively charging for the FRIACO
service in excess of costs, as it would be making a charge where the
costs are zero, since there is no need to use the service to which the
charge relates. The effect of this would be to require purchasers of
FRIACO to pay an excessive amount and so hinder the development of more
effective competition in internet termination and ultimately unmetered
internet access and so operate against the interests of end users.
The relevant
market
4.7 The Director
has considered what is the relevant market in which to assess whether
BT has market power in relation to the provision of FRIACO and various
applications of the IN.
4.8 Chapter 3 has
discussed the various applications of the IN that BT has cited with
respect to FRIACO. Each of the applications, namely routing, congestion
control, protection of DLEs from local overload, and protection of the
STP and interconnecting networks from focussed overload, is related
to the origination of FRIACO numbers. FRIACO is a call origination product
and therefore is part of the market for call origination. Hence in determining
the relevant market, it is necessary to examine if the different applications
that the IN provides are part of the market for call origination.
4.9 Due to the different
functions that each application provides, a purchaser of call origination
will not view any of these as a substitute for call origination itself.
Further, any supplier offering these applications would not be able
to easily enter into the provision of call origination due to the significant
sunk and fixed costs involved in providing call origination services.
4.10 The Director
believes that a provider of call origination services will seek to provide
all types of call origination services because of the economies of scope
present in doing so. Therefore providers of call origination would compete
to provide a range or basket of services across a customer’s exchange
line rather than offering only limited services across many exchange
lines. Such competition means customers choose the provider who can
provide the range of services at the lowest price. The fact that wholesale
call origination services face a common pricing constraint suggests
that all call origination services should be treated as part of the
same wholesale market.
4.11 In a similar
manner, the provider of call origination will provide the applications
associated with the call origination since the functionalities of such
services are a value added element to the basic call origination service.
As argued above, a common pricing constraint operates for the provider
of such applications and therefore such services would be part of the
market for call origination. The relevant market for the assessment
of market power is therefore wholesale call origination.
BT’s Market Power
4.12 Although BT
faces competition in call origination from other providers of direct
access networks, its market share in call origination is greatly in
excess of those of its competitors. The Director estimates BT's current
market share for call origination by volume to be around 75 per cent
across all customers or 82 per cent for residential customers over the
last three years (1999-00–2001-02). In addition, substantial barriers
to entry are faced by new entrants due to the significant sunk costs
required in providing such services.
4.13 The Director
therefore concludes that BT has market power in the market for wholesale
call origination. This implies that in addition to having market power
in the provision of FRIACO, BT also has market power in the provision
of applications such as routing FRIACO calls.
Consequences
4.14 In the light
of the Director’s conclusion that BT has market power in the relevant
market and the Director’s finding that use of the IN to handle FRIACO
traffic is not required (see chapter 3), the Director has considered
the consequences of continuing to allow BT to make a charge for the
use of the IN. He believes that these will lead to economic inefficiency,
distort competition and so not be in the interests of end users.
4.15 The Director
believes that the routing service that the IN currently provides can
be provided through the DLE by the enhanced switch decode capability
available since July 2001. Similarly, protection of the DLE from overload
can be managed through permanent call gapping at the DLE. The costs
of the switch decode and signalling links are already recoverable by
BT through the average charges for the Call Originating Local Exchange
Segment and the IEC links. To permit BT to recover the costs of the
IN for provision of the above applications would lead to higher costs
to users of FRIACO, and consequently, higher costs to end-users. This
would not be economically efficient, as it would price the applications
above the true cost of providing the services.
4.16 Furthermore,
allowing BT to charge above the true cost of providing the services
would distort competition in downstream markets between BT and the purchasers
of FRIACO and therefore preventing BT from doing this is necessary to
ensure effective competition to the benefit of end users.
4.17 The current
charge for the IN constitutes 17.4 per cent of the cost of purchasing
a FRIACO circuit. This is a significant cost for operators who need
to purchase large volumes of FRIACO circuits to meet the demands of
their customers. A high charge for purchasing FRIACO, including the
IN dip, is likely to impact adversely on the strength of such operators
to compete effectively with BT in the internet termination market. Operators
particularly face a higher risk than BT in pre-ordering FRIACO circuits
in anticipation of demand from ISPs and retail consumers. The Director
takes the view that BT does not face similar risks when its position
is assessed on an end-to-end basis. Any transfer charges incurred by
BT Retail Systems Business for purchasing FRIACO circuits would be purely
notional and be offset by notional profits in its Network Business.
There are two reasons for this.
4.18 First, the
IN charge paid to BT's Network Business (both by BT Retail Systems Business
and OLOs) is significantly above the marginal cost incurred by BT Network
Business in providing FRIACO IN dips. This means that BT's actual costs
at the margin of the IN service per FRIACO circuit are substantially
lower than the IN charges made by OLOs purchasing FRIACO circuits. Secondly,
BT Network Business does not incur the marginal cost of the IN unless
there is traffic flowing on a FRIACO circuit. Until FRIACO traffic actually
flows on the circuit, no FRIACO IN dips will be triggered and no marginal
cost will be incurred. However, OLOs are required to pay the standard
charge for IN per FRIACO circuit irrespective of whether they use it
or not. In addition, if BT is allowed to continue to charge for the
IN, this, as explained above, will mean one of the key input services
into the provision of retail unmetered internet access would be inflated
above its efficiently incurred costs. This is likely to hamper the development
of effective competition in internet termination and unmetered internet
access. The effect would be to require purchasers of FRIACO to pay an
excessive amount for FRIACO which would feed through to excessive retail
prices and so reduce the benefit end users.
4.19 Therefore,
the Director believes that there are exceptional circumstances which
make it appropriate for him to intervene in interconnection agreements
to ensure effective competition. Also, to allow BT to make an additional
charge for STP when the costs are already recovered would result in
FRIACO being purchased in excess of its true costs and so for the same
reasons as discussed above, the Director is proposing to remove this
right.
4.20 It should be
noted in this context that in the Director’s recent consultation document
published on 17 March 2003, which related to FRIACO and internet termination,
he set out the provisional conclusion that there was no individual or
collective Significant Market Power in the internet termination market.
A copy of the consultation document is at www.oftel.gov.uk/publications/eu_directives/2003/eu_narrow_term/index.htm.
However, such
a conclusion was predicated on the basis of appropriate regulation of
the wholesale call origination market. The appropriate regulation that
is considered to be relevant for unmetered Internet termination is the
regulation relating to FRIACO. Amongst other things this includes ensuring
that the charges for the FRIACO service reflect the costs of the service
and so do not include the IN charge for which there is no justification.
Accordingly the Director believes this Direction is consistent with
the proposals made in the wholesale unmetered narrowband internet termination
market review.
4.21 Whether or
not the IN will continue to be used for FRIACO will be a decision for
BT. It is for BT to decide how to provide services over its network
so long as they satisfy regulatory requirements. However, for the reasons
set out above the Director’s conclusion is that use of the IN for FRIACO
calls is not necessary and so BT should not be permitted to charge for
it in addition to the FRIACO virtual circuit charges.
Implementation
4.22 The Director
has considered when the Direction should take effect. As discussed in
chapter 3, the switch decode capability at the DLE was enhanced by July
2001 and the algorithm used for call gapping was upgraded by the end
of May 2002. Therefore the Director concludes that there was no justification
for using the IN to route FRIACO calls after 31 May 2002.
4.23 It might be
argued that retrospective adjustment of charges would not benefit effective
competition or end users because it is unclear whether there will be
matching retrospective rebates to downstream customers. Even if this
were the case, the Director considers that retrospection is important
in this case. Whilst the Director cannot fetter his discretion in future
cases, he seeks to ensure that the Direction provides the right signals
in relation to other cases for BT to make appropriate charges only when
there is a justification for doing so. A failure to apply retrospection
in this case would mean that BT would retain a financial benefit from
its overcharging and it might presume that it would similarly benefit
were it to behave in a similar manner in other cases ie BT would still
have an incentive to make a charge until such time that an investigation
is concluded. In contrast the application of retrospection in this case
removes the benefit to BT from its overcharging and, by reducing the
incentive to overcharge in other cases, seeks to ensure effective competition
for the benefit of end users. The Director believes that it is his duty
to ensure effective competition which protects end-users from incurring
charges that are not justified. Accordingly, the Director is removing
BT's right to make a reasonable additional charge as from 1 June 2002.
4.24 In addition,
the Director has considered the issue of the deployment of the upgraded
algorithm across all BT System X switches by the end of May 2002. The
Director considers that the other types of DLEs would have been able
to provide comparable functionality to the functionality provided by
the IN, from 1 August 2001 (as the switch decode issue was resolved
in July 2001). The Director has obtained the relative numbers of System
X switches, compared to BT’s other types of DLEs, from the data set
out in the Network Information Publication Principles (‘NIPP’) data,
for October 2001. On the basis of that information, the Director has
calculated the appropriate charge for the period 1 August 2001 to 31
May 2002, using a weighted average. Therefore, the Director is adjusting
BT’s IN charge for the period 1 August 2001-31 May 2002 to a weighted
average of the relevant charge for that period, to reflect the fact
that the algorithm only needed to be upgraded on the System X switches.
On this basis, the Director considers that the appropriate charge for
the period 1 August 2001-31 May 2002 is £42 per 64kbit/s circuit per
annum. Therefore, this Direction requires BT to repay all purchasers
of FRIACO the difference between the IN charge paid in relation to the
period 1 August 2001 to 31 May 2002, and the £42 per 64kbit/s circuit
specified in this Direction, together with interest on the repayments
in accordance with Clause 13.13 of the Standard Interconnection Agreement.
Cost recovery
4.25 The Director
does not dispute that use of the IN for FRIACO was necessary initially
from May 2000, but has concluded that it became unnecessary after 31
May 2002. In addition, the Director has also concluded that the charge
paid by Operators for use of the IN for FRIACO calls between 1 August
2001 and 31 May 2002 should be adjusted, as explained above at Paragraph
4.24. The Director has therefore considered whether BT has had the opportunity
to recover its reasonably incurred costs relevant to the provision of
IN for FRIACO in the period May 2000-May 2002.
4.26 It is clear
that BT's charges for FRIACO IN in the period May 2000-August 2001,
and BT’s adjusted charge (as a result of this Direction) between 1 August
2001 and the end of May 2002, covered the relevant operating and capital
costs reasonably incurred in that period. Firstly, the charges were
set based on BT’s fully allocated costs. Secondly, since IN costs are
caused on a per 'dip' or per call basis, the charge was based on an
assumed number of FRIACO calls per circuit, reflecting a mature usage
level. The Director does not consider such an approach to be unreasonable.
Indeed, in principle it is consistent with the way in which the Director
has himself set the adjustment ratio which is used in the derivation
of the FRIACO circuit charge (Review of Adjustment Ratio for DLE FRIACO,
which is at www.oftel.gov.uk/publications/internet/2002/dlefriaco0702.htm).
However, the Director notes that the actual usage of the IN by FRIACO circuits
was rather less than allowed for in the IN charge set by BT ie the actual
number of calls per circuit was less than BT's assumption. This feature,
although not unreasonable in itself, ensured in the view of the Director
that BT's revenue from FRIACO IN at least matched its costs
in the period May 2000-May 2002.
4.27 As explained
at paragraph 2.12 above, in the consultation on the Draft Direction,
the Director recognised that any brought forward investment might carry
an opportunity cost, and he suggested that the cost of brought forward
investment could be relevant if certain conditions applied. BT has not
provided the Director with any evidence to show that these four conditions
have been met, or to challenge those conditions. Therefore, the Director
concludes that the issue of brought forward investment is not relevant.
4.28 The IN charge
is based on an assumed number of FRIACO calls per circuit, reflecting
a mature usage level of the circuit. Since the actual usage of the IN
by FRIACO circuits during May 2000-May 2002 was rather less than allowed
for in the IN charge set by BT, this might have resulted in over-recovery
for that reason. Consequently the Director has considered the question
of retrospective rebates during this period as a result of this form
of over-recovery.
4.29 However, the
Director believes that the basis for charging for the IN is consistent
with the approach used in the Adjustment Ratio in the derivation of
the FRIACO charge. The methodology for the adjustment ratio reflects
the importance of deriving FRIACO charges that capture cost causation
and are reasonably stable and sustainable. In a similar manner, the
Director does not consider it unreasonable for the level of the IN charge
to have been stable by basing it on the mature number of calls per FRIACO
circuit during the period of May 2000-May 2002 in which levying an IN
charge was legitimate. Stability has the advantage of facilitating business
planning for operators by providing reasonable predictability of the
IN charge. Therefore, to allow operators with retrospective rebates
on the basis of the actual number of calls rather than the mature number
of calls will be inconsistent with the aim of providing stability in
the charge. The Director clearly stated that this was his approach in
the Determination on the Adjustment Ratio when he stated that "one
of the important principles adopted by Oftel in deriving FRIACO charges
is that certainty about the charge should be promoted to facilitate
business planning. Therefore the Director considers that changes in
the adjustment ratio should not apply retrospectively". Accordingly,
the Director considers it inappropriate to provide operators with retrospective
rebates on the basis of differences between forecast and actual usage
for the period May 2000-May 2002.
Interest charges
4.30 In accordance
with Clause 13.13 of the Standard Interconnection Agreement, BT will
pay interest on repayments made under this Direction to operators from
1 August 2001. The applicable annual rate set out in Clause 13.13 as
the "Oftel Interest Rate" is the London Inter-Bank Offered
Rate (LIBOR) plus 3/8 per cent.
Continuation
notices
4.31 This Direction
will be the subject of a Continuation Notice which will be published
before 25 July 2003 to ensure that this Direction continues to have
effect after 25 July 2003. Although the Director consulted on the proposed
Continuation Notices from 3 July 2003 to 14 July 2003, it was not possible
to include this Direction in that consultation due to the timing of
the publication of this Direction.

Chapter
5 Proposals for industry discussion
5.1 In this explanatory
memorandum which accompanies the Direction, the Director has set out
why he is removing BT’s right to make an additional charge for the use
of the IN to route FRIACO calls. However, although the Director has
not been persuaded by BT’s arguments that use of the IN is essential
for congestion management, the Director recognises the IN may have a
useful role to play in tackling congestion management issues in the
future. In particular, it appears that it is particularly important
to ensure that a major failure of one ISP or its serving OLO does not
impact on the ability of others to continue providing services, given
the potential increase in calling rates for unmetered services which
can be triggered during a failure. Additionally, individual ISPs and
operators may wish to have pro-active means for protecting their networks
from focussed overloads.
5.2 The Director
also considers that the present method of managing congestion within
BT’s network may not be optimum, being a compromise between protecting
its signalling network and protecting the DLEs. It may also be the case
that any unforeseen overload on voice services using IN might impact
on Internet access.
5.3 The Director
considers that this investigation highlights the importance of multilateral
industry discussion and consensus in addressing such issues, and considers
a unilateral approach by operators to resolving the issues to be unsatisfactory.
Therefore, the Director wishes to encourage wider industry discussions
on the appropriate protection mechanisms, and will take steps to facilitate
a suitable forum for such discussions.

Annex
A List of respondents
- BT;
- Energis;
- Tiscali;
- Ntl;
- Thus;
- NIACT;
- service provider
1; and
- service provider
2.
Annex
B Glossary of terms and acronyms
DLE (Digital Local
Exchange) – The telephone exchange to which customers are connected,
usually via a local concentrator.
DMSU (Digital Main
Switching Unit) – The main type of tandem switch, primarily used for
conveying long distance calls.
FRIACO – Flat Rate
Internet Access Call Origination
IEC – Interconnection
Extension Circuit
IN (Intelligent
Network) – A telecommunications network in which the network intelligence
is centralised and separated from the switching function.
STP (Signalling
Transfer Point) – A facility whereby C7 signalling messages can be passed
between exchanges without requiring a discrete circuit between them.


|