Contents
The
draft Direction
Explanatory memorandum
Chapter
1 Summary
Chapter
2 Background
Chapter
3 History of the dispute
Chapter
4 Submissions of the parties
Chapter
5 The Director General’s considerations
Chapter
6 Consultation and timetable for responses
DRAFT
DIRECTION UNDER REGULATIONS 6(6) OF THE TELECOMMUNICATIONS (INTERCONNECTION)
REGULATIONS 1997 RELATING TO A DISPUTE BETWEEN CABLE AND WIRELESS U.K("C&W")
AND BRITISH TELECOMMUNICATIONS PLC ("BT") OVER THE PROVISION
OF OVERFLOW CAPACITY FOR DQ118 TRAFFIC
WHEREAS:
(A) The Secretary
of State granted to British Telecommunications on 22 June 1984 a licence
(the "BT licence") under section 7 of the Telecommunications
Act 1984 (the "Act") for the running of telecommunications
systems specified in that Licence;
(B) By virtue of
section 109 of and paragraph 20 of Schedule 5 of the Act the BT licence
has effect as if granted to British Telecommunications plc ("BT");
(C) The Secretary
of State has granted to Cable and Wireless U.K. (formally Cable and
Wireless Communications (Mercury) and Mercury Communications Limited)
("C&W") on 5 December 1991 a licence under Section 7 of
the Act for the running of telecommunications systems specified in that
licence;
(D) On 1 January
1998, the European Parliament and Council Directive 97/33/EC came into
force and was implemented in the UK through the Telecommunications (Interconnection)
Regulations 1997 (the "Regulations") and conditions in the
licences of operators;
(E) Regulations
6(6) of the Regulations provides that where there is a dispute concerning
interconnection between organisations, the Director General of Telecommunications
(the "Director") shall, at the request of either party, take
steps to resolve the dispute within six months of the date of the request.
The direction which the Director makes to resolve the dispute must represent
a fair balance between the legitimate interests of the parties, and
must be notified to the parties in accordance with Regulation 8(3).
The parties are entitled to a full statement of the reasons on which
the direction is based;
(F) C&W entered
into an interconnection agreement with BT on 1 May 1998;
(G) In July 2002
BT agreed that directory enquiry services traffic using the new 118
code ("DQ118" traffic) and carried on BT’s network for termination
on C&W’s network could be routed over the interconnection capacity
already used for number translation service ("NTS") traffic
carried on BT’s network for termination on C&W’s network. However,
rather than allow C&W to use the same routing plan as for C&W’s
NTS traffic, BT required C&W to submit a separate routing plan for
DQ118 traffic. BT refused to provide alternative routing of C&W’s
DQ118 traffic from one BT switch that interconnects with C&W’s network
to another BT switch that interconnects with C&W’s network ("Overflow");
(H) BT is also seeking
to withdraw the provision of overflow for NTS traffic by way of a Contractual
Review Notice amending Annex A to BT’s Standard Interconnect Agreement.
This is in response to the Director’s Determination of 28 June 2001
to resolve a dispute between BT and a number of other licensed operators
regarding a proposal to charge for NTS links (the "NTS Links Determination").
The NTS Links Determination established that the responsibility for
interconnection links used for terminating NTS traffic originating or
transiting on BT’s network for termination on other operators’ networks
should transfer from BT to the terminating operator. BT’s proposed withdrawal
of the provision of Overflow for NTS traffic is currently the subject
of a separate interconnection dispute between BT and 5 other licensed
operators;
(I) C&W considers
that BT does not have the right to refuse to provide overflow for DQ118
traffic and is therefore in dispute with BT;
(J) On 23 August
2002, in accordance with the provisions of Regulation 6(6) of the Regulations,
C&W referred this dispute to the Director for determination;
(K) The Director
has a duty to encourage and secure adequate interconnection in the interests
of all users in a way which provides maximum economic efficiency and
gives maximum benefit to end-users;
(L) The Director
has considered, inter alia, the information provided by the parties
and the matters set out in Regulation 6(8) of the Regulations. The principle
points are summarised in the explanatory memorandum, which accompanies,
and is published with, this direction;
(M) A draft of this
direction and the explanatory memorandum was issued to interested parties
on 17 January 2003. Comments were invited by 17 February 2003.
NOW, THEREFORE:
PURSUANT TO REGULATION
6(6) OF THE INTERCONNECTION REGULATIONS, AND HAVING CONSIDERED THE VIEWS
OF THE PARTIES AND THOSE MATTERS SET OUT IN REGULATION 6(8) OF THOSE
REGULATIONS, THE DIRECTOR MAKES THE FOLLOWING DIRECTION TO RESOLVE THE
DISPUTE BETWEEN C&W AND BT:
1.BT shall offer
to provide Overflow for DQ118 traffic terminating on C&W’s network
within 30 days after receiving a written request for Overflow from C&W.
2. BT shall not
make a separate charge to C&W for the provision of Overflow for
DQ118 traffic in addition to the amount BT already charges C&W for
the conveyance of DQ118 traffic terminating on C&W’s network.
3. This direction
shall form part of the interconnection agreement in force between BT
and C&W and, if necessary, BT and C&W shall modify their interconnection
agreement to give effect to and implement this direction.
4. Except as otherwise
defined in this direction, words or expressions used shall have the
same meaning as in the Act, the BT licence or BT’s Standard Interconnect
Agreement as appropriate.
5. This direction
shall take effect on the date it is published.
Heather Clayton
Director of Investigations
A person authorised
under paragraph 8 of Schedule 1 of the Telecommunications Act 1984
[17 January 2003]

Explanatory
memorandum
Chapter
1
Summary
1.1 The Director
of Telecommunications ('the Director') has issued a draft direction
in accordance with the provisions of Regulation 6(6) of the Telecommunications
(Interconnection) Regulations 1997 ('the Regulations') for the resolution
of a dispute between Cable & Wireless U.K. ('C&W') and British
Telecommunications plc ('BT').
1.2 C&W referred
this dispute to the Director on 23 August 2002. Arguments submitted
in relation to this dispute by C&W and BT are set out in chapter
4. The Director has considered the submissions made by C&W and BT
and has issued this draft direction in respect of the dispute. Comments
are requested and will be taken into account in making a final direction.
1.3 C&W requested
that the Director require BT to provide alternative routing ('overflow')
for directory enquiry services traffic using the new 118 code ('DQ118
traffic'), that BT carries on its network for termination on C&W’s
network. BT has agreed to carry C&W’s DQ118 traffic on the interconnect
capacity between BT’s and C&W’s networks already used to carry C&W’s
number translation services ('NTS') traffic.
1.4 The details
of the Director’s consideration of the submissions made by C&W and
BT, together with the reasons why the Director General is minded to
make this draft direction, are set out in chapter 5.
1.5 In summary,
the Director is minded to direct that BT should be required to provide
alternative routing for DQ118 traffic from one BT switch interconnected
with the C&W network to another such switch connection, regardless
of the type of interconnect capacity used to carry the DQ118 traffic.
1.6 Having considered
the facts specific to this dispute and the matters set out in Regulation
6(8) of the Regulations, this draft direction, in the opinion of the
Director, represents a fair balance between the interests of the parties
in this case, having regard to the Director’s wider duties to promote
the development of the telecommunications industry in the UK and to
encourage and secure adequate interconnection in the interests of all
users in a way that provides maximum economic efficiency and gives the
maximum benefit to end users.

Chapter
2
Background
Description of
DQ118 traffic
2.1 In September
2001, the Director decided to withdraw the existing national and international
directory enquiry (DQ) services codes. These codes, which effectively
tied consumers to one provider, were to be replaced with new numbers
beginning with 118, and these were to be allocated to individual service
providers wishing to provide a paid-for national and/or international
DQ service.
2.2 The new DQ118
services were launched on 10 December 2002. The existing short numbers
used for DQ services (for example 192) will continue to work in parallel
until at least the end of August 2003.
2.3 This dispute
concerns the provision of a facility for overflow (as described below)
to ensure that DQ118 calls carried on BT’s network for termination on
C&W’s network do not fail due to congestion at the designated point
of interconnection between BT’s network and C&W’s network.
Description of
overflow
2.4 Within the context
of this dispute, overflow describes the provision of alternative routing,
from one BT switch connection with an operator’s network to another
BT switch connection with that operator’s network, for traffic that
has either originated on BT’s network or originated on a third party
network and has been transited via the BT network. This is sometimes
known as ‘sideways overflow’. The provision of an overflow facility
ensures call completion in situations where congestion prevents conveyance
at the designated point of interconnection between the BT network and
the other operator’s network.
Overflow for
other traffic types
2.5 Overflow is
currently provided for number translation service ("NTS")
traffic being conveyed from BT’s network to an operator’s network. However,
BT is seeking to withdraw the provision of overflow for NTS traffic
by way of a Contractual Review Notice amending Annex A to BT’s Standard
Interconnect Agreement ('SIA'). This is in response to the Director’s
Determination of a dispute between BT and a number of operators regarding
a proposal to charge for NTS links from January 1 2001 – 28 June 2001
(the 'NTS Links Determination') (see
www.oftel.gov.uk/publications/pricing/ntsp0601.htm).
The NTS Links Determination established that the responsibility for
interconnection links used for carrying NTS traffic should transfer
from BT to the terminating operator. As a result of this change in 'ownership'
of NTS links, BT is proposing to change traffic routing rules and remove
the facility for overflow,which BT historically provided for NTS traffic
(ie when BT owned the links). This issue is currently the subject of
a separate interconnection dispute between BT and five operators, including
C&W, who have refused to sign an amendment to their respective interconnection
agreements with BT to this effect.
2.6 In contrast,
overflow is not currently provided for indirect access ('IA') traffic.
Indeed, BT’s SIA expressly excludes the alternative routing of IA traffic
from one BT switch connection to another BT switch connection (see further
below).
Routing principles
2.7 The routing
principles for traffic from BT’s network to an operator’s network and
vice versa are set out in paragraph 5.1.1 of annex A to the SIA.
Paragraph 5.1.1
of Annex A sets out a general rule that:
"Each Party
shall route the other Party’s traffic in accordance with the following
routing principles:
(a) routing
within a Party’s System shall be equivalent to the routing of similar
types of traffic for the generality of such Party’s customers including
alternative routing where appropriate."
2.8 Paragraph 5.1.2
sets out another general rule that:
"The Parties
shall develop and apply network management strategies and procedures
to maintain customers’ service quality and to protect the Parties’
Systems as are appropriate. Full details of the network management
provisions are set out in the Operations and Maintenance Manual.
These shall include:
(b) establishment
of overflow procedures."
2.9 The general
rules in paragraph 5.1 however are subject to more specific routing
rules in paragraph 5.4, which differ according to the traffic type in
question. Paragraph 5.4.5.1 (c) for example, states in relation to IA
traffic that:
"For Indirect
Access Calls received at a BT Switch Connection and on the Operator’s
written request, BT shall arrange not less than one alternative
path to be provided to the Operator System. Routing from the nominated
BT Switch Connection to the Operator System shall be limited to
Traffic Routes from that BT Switch connection."

Chapter
3
History of the
dispute
3.1 The record of
industry discussions relating to the contractual issues surrounding
the introduction of DQ118 services demonstrates BT’s intention to apply
the same routing rules to DQ118 traffic as apply to IA traffic, and
other traffic that BT does not ‘own’. BT has made it clear that its
intention was that there would be no alternative routing for DQ118 traffic
from one BT switch interconnected with the operator’s network to another,
i.e. no overflow would be provided.
3.2 In June 2002
BT agreed to C&W’s request that C&W’s DQ118 traffic could be
routed on the interconnect capacity that is also used for C&W-owned
NTS traffic (ie the NTS links between BT’s and C&W’s networks).
The Director has been provided with correspondence from both parties
demonstrating that there were a number of discussions between the parties
relating to the routing plans that were to be submitted for C&W’s
DQ118 traffic.
3.3 Correspondence
from July 2002 shows that C&W considered that overflow should be
provided for DQ118 traffic, although BT had already sent 118 product
descriptions to C&W which contained routing rules stating that there
would be no overflow for DQ118 traffic. A meeting was subsequently held
between C&W and BT to discuss DQ118 routing rules in which BT agreed
to consider whether overflow should be provided for C&W’s DQ118
traffic. There is disagreement between the parties as to what was agreed
at this meeting. However, BT confirmed to C&W via an email dated
12 August 2002 that overflow for DQ118 traffic was not available.
3.4 In August 2002
C&W submitted DQ118 routing plans to BT which provided for overflow.
Following communications between BT and C&W, C&W re-submitted
a revised routing plan on 20 August 2002, which did not provide for
overflow.

Chapter
4
Submissions of
the parties
C&W’s arguments
4.1 In referring
this dispute to the Director for determination, C&W stated that
it had been in discussions with BT regarding the routing of DQ118 traffic
since July 2002.
4.2 C&W stated
that BT had originally required all DQ118 traffic to be routed on routes
used for IA traffic. Following objections from C&W, however, BT
agreed to route DQ118 traffic terminating on C&W’s network on routes
used for NTS traffic and, according to C&W, BT initially agreed
that DQ118 numbers could be added to C&W’s NTS routing plan. C&W
stated that shortly before the deadline for submitting its revised routing
plan, BT informed C&W that it should submit a separate routing plan
for DQ118 traffic and that this routing plan should not include a provision
for overflow. Despite objecting, C&W were compelled, due to time
constraints, to prepare a routing plan for DQ118 traffic without provision
for overflow, in order that C&W’s DQ118 services could be launched
on time.
4.3 C&W noted
that BT wished to amend the Standard Interconnect Agreement such that
operators would no longer have the right to the provision of overflow
for NTS traffic. C&W argued, however, that BT was contractually
obliged to provide it with overflow on NTS routes until such time as
BT agreed an amendment to the interconnection agreement in force between
C&W and BT, or the matter was referred as a dispute to the Director
and resolved.
4.4 C&W asserted
that the routing rules (which are currently disputed) applicable to
NTS traffic and which allowed for overflow, should apply equally to
DQ118 traffic which used the same interconnect capacity as for NTS traffic.
4.5 C&W argued
further that IA traffic and DQ118 traffic were not sufficiently similar
for both services to be treated the same way under the Standard Interconnect
Agreement. C&W argued that when a customer dialled an Indirect Access
code the customer was aware of the network provider carrying the call.
C&W claimed that if a call failed, the customer could simply re-route
the call to the BT network by redialling without the IA code. However,
when a customer dialled a DQ118 number, as with NTS, the underlying
operator terminating the DQ service might not be visible. If the call
encountered congestion at the point of interconnection between the BT
network and the operator network and there was no overflow facility,
the call would fail, and there would be no ‘workaround’ available to
the customer. There was therefore an added reason for providing overflow
in relation to DQ118 traffic, which did not exist for IA traffic.
BT’s arguments
4.6 BT put forward
three main arguments in support of its decision not to provide overflow
to C&W for DQ118 traffic:
- BT argued that
overflow should be provided on the basis of traffic type and not on
the basis of the interconnect capacity used to carry the traffic.
BT argued that traffic types in the direction ‘BT to operator’ that
the operator ‘owns’ (such as IA traffic and DQ118 traffic) should
not be provided with overflow;
- BT argued further
that it could not recover the costs of providing such overflow services;
and
- BT asserted that
some operators would be inclined to misuse the overflow facility by
deliberately under-providing interconnect capacity on the primary
route, and by relying excessively on overflow in order to ensure that
calls to their services were successful.
Routing rules
for DQ118 traffic
4.7 BT submitted
to the Director a record of the industry discussions related to the
introduction of DQ118 services and the routing rules applicable to DQ118
traffic. BT stated that the industry was briefed through the relevant
DQ118 industry group that there would be no overflow for DQ118 traffic.
4.8 BT stated that
communications between BT and C&W took place as a result of C&W’s
request to route DQ118 traffic on the interconnect capacity used for
C&W owned NTS traffic.
Ownership
of traffic
4.9 BT argued that
all traffic types in the direction "BT to operator" that the
operator owns should be subject to the same routing rule (ie no alternative
routing from one interconnected BT switch to another). In BT’s view
DQ118 traffic should be treated appropriately from the outset based
on ownership of the traffic.
4.10 BT argued that
where an operator ‘owns’ the traffic, and it has responsibility for
dimensioning the capacity of the interconnection links between itself
and BT (as set out for NTS traffic in the NTS Links Direction), BT cannot
effectively control the use of overflow. When BT owned the links, however,
BT faced correct incentives to provide links in the most efficient way,
as BT would bear the cost of any network congestion that resulted from
insufficient capacity on links between itself and an interconnecting
operator. However, where BT no longer owns the links, BT will still
bear the cost of network congestion where a link is not ‘fully provided’
(ie able to meet peak demand in normal circumstances), but it can no
longer upgrade the links between itself and an operator to ameliorate
the congestion.
Recovery of
costs
4.11 BT argued that
DQ118 traffic destined for an Operator’s network that is allowed to
overflow would also "drive intra-BT switch network expansion and so
result in additional costs for BT, with the Operator making no additional
payment for the calls that drive the network augmentation."
4.12 BT argued that
calls following an alternative routing path would not attract any additional
network usage charge. It was not possible to identify whether a call
had used an alternative routing within the call accounting records.
Correct dimensioning
of interconnect capacity
4.13 Further, BT
argued that providing overflow would create a situation where routes
into an operator’s network would effectively be used as ‘high usage’
routes (ie able to meet most demand, but at peak times relying on overflow
to other links to ensure satisfactory quality of service) instead of
being dimensioned on a ‘fully provided’ basis.
4.14 In BT’s view,
some operators would exploit the availability of overflow in order to
avoid having to purchase extra interconnect capacity. BT argued that
it was not reasonable to jeopardise the grade of service of calls already
using parts of the BT network on a primary basis by enabling such calls
to be affected by the implementation and use of alternative routing
as requested.
4.15 BT has further
argued that BT must rely on contractual provisions with operators to
ensure that links are fully provided. BT pointed out that preventing
an operator from exploiting these contractual provisions is very difficult,
due to difficulties in identifying instances of ‘genuine’ temporary
use of overflow facilities.
Further comments
4.16 BT accepted
C&W’s request that DQ118 traffic be handed over to the C&W network
using the same interconnect capacity as used for C&W-owned NTS traffic,
on the basis that operator-owned traffic could be handed over to the
operator network using any operator-owned interconnect capacity (except
FRIACO and Single Tandem FRIACO capacity).
4.17 BT noted that
the routing rules specified in the Standard Interconnect Agreement were
applicable to a traffic type. BT therefore disputed C&W’s assertion
that NTS routes were provided with overflow, because overflow is provided
for traffic, not routes.
Chapter
5
The Director’s
proposed decision and reasons
5.1 Having duly
considered the representations made by C&W and BT in response to
this request for a direction, the Director is minded to conclude that
BT should be obliged to provide overflow for DQ118 traffic.
5.2 In reaching
this view, the Director has considered his general obligations under
Regulation 6(1) of the Regulations to encourage and secure adequate
interconnection in the interests of all users, and in a way that provides
maximum economic efficiency and gives maximum benefit to end-users.
In so doing, the Director has considered whether C&W’s request for
overflow for DQ118 traffic is a reasonable request given the nature
of the service requested, the ability of BT to provide such a service
and the effects of BT failing to provide overflow for DQ118 traffic.
5.3 The Director
has also ensured that his decision represents a fair balance between
the interests of the parties to the dispute, taking into account the
matters set out in Regulation 6(8) of the Regulations, in particular
the interests of users, the regulatory constraints on the parties, the
relative market position of the parties and the promotion of competition.
BT’s regulatory
obligations
5.4 Pursuant to
Regulation 4(1) of the Regulations, BT has been determined as having
Significant Market Power ('SMP'), inter alia, in the market for fixed
public telephone networks and services. BT is obliged to offer to interconnect
in this market with all other operators who fall within Schedule 2 of
the Regulations and who have made a reasonable request for such interconnection.
BT’s contractual
obligations
5.5 The Director
has considered the existing contractual obligations imposed on BT in
relation to the provision of overflow under BT’s Standard Interconnect
Agreement.
5.6 The Director
accepts BT’s argument that it is the routing rules for each traffic
type specified in the Standard Interconnect Agreement that determine
whether overflow is provided or not, rather than the type of interconnect
capacity that is used to carry the traffic.
5.7 However, notwithstanding
this analysis, the Director does not propose to make his decision based
simply on an interpretation of the provisions of the Standard Interconnect
Agreement and BT’s current contractual obligations towards C&W.
The Director has been asked to resolve a dispute concerning the provision
of overflow for DQ118 services and this draft direction represents his
decision in resolving that dispute.
Relevant market(s)
and the position of the parties to the dispute
5.8 C&W is in
dispute with BT concerning overflow for DQ118 traffic from the BT network
to the C&W network that has either originated on the BT network
or has transited the BT network from another operator’s network for
termination on the C&W network. BT’s relationship with C&W in
terms of this dispute is as an originator of DQ118 traffic, as a transit
operator of DQ118 traffic originating on another operator’s network,
and as the provider of interconnection between BT’s and C&W’s networks.
For the purposes of the current network charge controls imposed on BT
(see the February 2001 Network Charge Control Statement: www.oftel.gov.uk/publications/pricing/pcr0101.htm),
call origination and interconnection specific services have been designated
as being non-competitive, ie they are services in which there is little
or no competition. Inter-tandem transit services, on the other hand,
have been designated as being prospectively competitive services ie
they are not currently fully competitive, but are expected to become
more competitive over the life of the network charge control.
5.9 C&W also
competes with BT in the newly liberalised market for the provision of
DQ118 termination services.
5.10 C&W requested
that BT provide overflow for DQ118 traffic in order to secure robustness
in call completion of DQ118 traffic terminating on C&W’s network.
As noted in section 4, BT has argued that it should not be required
to offer this service because:
- as a general
principle overflow should not be provided for operator-owned traffic
types;
- BT would not
be able to recover its costs in providing overflow; and
- BT believed that
some operators would be inclined to misuse overflow.
Ownership of
traffic
5.11 The Director
has considered BT’s view that BT to operator DQ118 traffic is owned
by the terminating operator, and that BT should not be obliged to offer
any more than the basic conveyance from BT’s network to the operator’s
nearest point of interconnection.
5.12 The Director
recognises that the incentives to correctly dimension links between
BT’s network and an operator’s network are different depending upon
who has responsibility for the traffic type and interconnection capacity
used to carry that traffic. In the Director’s view it is possible for
BT and the industry to develop and agree mechanisms that will ensure
that overflow is used appropriately and that operator links are correctly
dimensioned on a fully provided basis, as is in fact required under
the terms of the Standard Interconnect Agreement. This issue is considered
again in paragraphs 5.21 and 5.22. Whilst recognising BT’s concerns,
in the Director’s view, overflow is required for DQ118 traffic regardless
of the ‘ownership’ of this traffic type.
Recovery of costs
5.13 The Director
has considered BT’s argument that forcing BT to provide overflow for
DQ118 traffic will result in BT incurring additional network costs that
it will not be able to recover. BT argued that it was currently unable
to identify when a call has been re-routed (ie where overflow has been
provided).
5.14 In the Director’s
view it is reasonable that if BT is required to provide overflow for
any DQ118 traffic it should be able to recover the costs of doing so.
5.15 BT’s conveyance
and access charges are regulated through the network charge controls,
which are fixed periodically by the Director. The controls were last
set in 2001, for a four-year period through to 2005. Charges are subject
to RPI-X controls where the value of X is set so as to bring forecast
basket revenues into line with costs, including the cost of capital,
in the final year of the control. The values of X therefore reflect
expected cost reductions, which in turn reflect assumptions about future
efficiency gains, market volumes, market share and routing factors,
among other things. The charges for conveyance services are derived
from forecast component cost and volumes, to which forecast routing
(usage) factors are applied (for a fuller discussion, see the February
2001 Network Charge Control statement).
5.16 The Director
notes that differences between forecast and actual costs, volumes and
routing factors will result in BT over or under recovering its network
costs. As the Director understands that BT provided overflow facilities
(to itself) when the forecasts were last set (2001), it is to be expected
that BT will recover the costs of providing the amount of overflow that
was forecast to occur at that time. Therefore, for the conveyance of
existing traffic types, it is apparent that a level of cost recovery
for overflow is factored into the controls.
5.17 The introduction
of the new DQ118 services was not factored into the cost, volume and
routing forecasts in the 2001 controls. Two effects could be expected
as a result of this:
- the actual volumes
of DQ118 conveyance traffic are additional to the volume estimates
for underlying conveyance services (eg local-tandem conveyance) put
in place at the start of the charge control. This difference between
forecast and actual call volumes means that there is an opportunity
for cost over-recovery, because economies of scale in BT’s network
mean that percentage increases in actual volumes are greater than
percentage increases in network costs. Therefore, the additional DQ
traffic volumes mean that BT’s costs will increase, but not to the
same extent that revenues will. (Oftel estimates the relationship
between volumes and costs formally as a cost-volume elasticity. The
estimate is between 0.2 and 0.3 for inland conveyance, meaning that
a 1 per cent increase in call volumes will lead to only a 0.2–0.3
per cent increase in cost); and
- the provision
of overflow for DQ118 traffic may result in actual component costs
for underlying conveyance services exceeding forecasts. Charges for
access to the standard conveyance services (eg local-tandem conveyance)
are set on the basis of their component costs, expected volumes and
expected usage of components. The provision of overflow, which results
in extra switching stages, could result in some standard services
on average using more of the underlying network components than forecast.
This could offset, to some degree, BT’s gain from higher call conveyance
volumes.
5.18 These effects
on call volumes, component costs and routing factors will last over
the life of the current network charge control. The Director notes that
BT would have to demonstrate that there was likely to be a material
cost under-recovery before any adjustment to the controls would be considered.
In practice, this seems unlikely. Aside from the Director’s view that
it is very likely that BT will benefit from an increased demand for
call conveyance services , DQ118 traffic is only likely to represent
a very small fraction of total traffic on the BT network. In the setting
of future charge controls, the changes in volumes and routing factors
will be incorporated into new forecasts.
5.19 In the Director’s
view, providing operators are prevented from exploiting overflow (see
paragraph 5.22) the forecast for network routing factors will not differ
significantly from those actually achieved. BT should, therefore, recover
the cost of providing overflow during the current charge control period
(see further below in relation to the correct dimensioning of interconnection
capacity).
5.20 In the Director’s
view, BT should be obliged to provide overflow as a facility for which
it already has the opportunity to sufficiently recover costs, as explained
above. BT should not, therefore, make a separate charge to C&W for
the provision of overflow for DQ118 traffic in addition to the amount
BT already charges C&W for the conveyance of DQ118 traffic terminating
on C&W’s network.
Correct dimensioning
of interconnect capacity
5.21 Under the terms
of paragraph 5.3.1 of annex A to the Standard Interconnect Agreement,
interconnection capacity (links) must be fully provided. This ensures
that there is sufficient capacity on an interconnection link to carry
the operator’s traffic, according to traffic forecasts, and that overflow
is used only as an occasional ‘back-up’ for periods when an interconnection
point is congested. The Director notes BT’s concerns that operators
may be tempted to run routes ‘hot’, ie to provided insufficient capacity
on a particular link, and rely on BT overflowing calls from one BT switch
interconnected with the operator’s network to another such BT switch.
5.22 In the Director’s
view, BT should negotiate with operators to agree methods of measuring
the extent to which any overflow facility is being used, through local
traffic management statistics. If there is clear evidence that operators
are running routes ‘hot’, and operators refuse to augment such links
within a reasonable period of time, the operators may possibly be in
breach of their obligations under their respective interconnection agreements
with BT.
Promotion of
competition
5.23 It appears
to the Director that, if BT refused to provide overflow for DQ118 traffic,
it would lead to BT’s downstream activities having a competitive advantage.
5.24 As noted earlier,
interconnect capacity between BT’s network and an operator’s network
can be dimensioned on a ‘fully provided’ basis or a ‘high usage’ basis.
Operators are required under the terms of the Standard Interconnect
Agreement to fully provide interconnect links. However BT has no corresponding
need to fully provide the links carrying DQ118 calls that originate
and terminate on its own network. This is due to the existence of multiple
alternative routing options within BT’s network, which mean that a satisfactory
quality of service can be obtained without the need to fully provide
the links carrying the traffic. This provides BT with a cost advantage,
because it is likely to be cheaper to run certain links as high usage,
at least for certain periods of time when demand may be uncertain.
5.25 A refusal to
supply operators with an overflow facility is therefore likely to give
BT’s retail DQ product, and other service providers terminating DQ calls
on BT’s network, a competitive advantage. These services will be able
to take advantage of BT’s ability to dimension its own network incorporating
‘high usage’ routes with overflow, where it is efficient to do so. Requiring
BT to provide overflow to other operators should result in an equivalent
quality and cost of service for DQ call conveyance to that which BT
provides itself. It is therefore in the interests of promoting competition
to require BT to provide overflow for DQ118 traffic destined for an
operator’s network.
Economic efficiency
5.26 Sub-optimal
investment decisions by operators may also arise as a result of BT’s
refusal to provide overflow. Forcing operators to invest in higher capacity
links where only a small amount of overflow may be required will result
in inefficient over-dimensioning of links, and distortion of the ‘build
or buy’ decision. C&W was particularly concerned about situations
where its network was expanded, as demand on these routes would be uncertain
and capacity requirements would be subject to a certain amount of adjustment.
Denial of overflow might in these circumstances result in an excessive
amount of conservatism in network design. Requiring BT to provide overflow
should therefore minimise the cost of interconnection and therefore
of producing DQ services (increasing productive efficiency).
Interests of
end-users
5.28 The Director
believes that it is in the interests of end-users of DQ118 services
that BT be required to provide overflow for DQ118 traffic terminating
on C&W’s network. In the absence of an overflow facility, there
is a risk that calls will fail if there is congestion which prevents
the conveyance at the designated point of interconnection between the
BT network and the C&W network.
Conclusions
5.29 Having duly
considered the representations made by C&W and BT in response to
this request for a direction and the matters set out in Regulation 6(8)
of the Telecommunications (Interconnection) Regulations 1997, the Director
is minded to conclude that BT should be obliged to provide overflow
for DQ118 traffic terminating on C&W’s network. The Director considers
that it is reasonable to require BT to comply with this obligation within
30 days after receiving a written request for overflow from C&W.
5.30 In the Director’s
view C&W’s request for overflow for DQ118 traffic is a reasonable
request given the nature of the service requested, the ability of BT
to provide such a service and the effects of BT failing to provide overflow
for DQ118 traffic.
5.31 The Director
considers that this direction represents a fair balance between the
interests of the parties to the dispute, and takes into account the
interests of users, the regulatory constraints on the parties, the relative
market position of the parties and the promotion of competition.

Chapter
6
Consultation and
timetable for responses
6.1 The Director’s
draft direction is being made available to interested parties, together
with the Director’s reasons, so that they may have a reasonable opportunity
to make representations.
6.2 Please email
or send comments in writing to:
Katherine Dinsdale
Oftel
50 Ludgate
Hill
London
EC4M 7JJ
tel: 020 7634 5358
fax: 020 7634
8772
e-mail:
katherine.dinsdale@oftel.gov.uk
6.3 Comments on
this consultation must be sent to Oftel by 17 February 2003. Oftel does
not intend on this occasion to hold any comments-on-comments phase during
which observations may be made on the representations made by others.
6.4 Confidential
responses should not be sent via e-mail. Written comments will be made
publicly available in Oftel’s Research and Intelligence Unit, except
where a respondent indicates that a response, or part of it, is confidential.
Respondents are therefore asked to separate any confidential material
into a clearly marked annex. In the interests of transparency, respondents
are asked to avoid confidential markings where possible.
6.5 The final direction
will be made as soon as possible after the end of the above mentioned
consultation period.


|