18 January 2002
Contents
Chapter
2 Background
Chapter
5 Consultation an timetable for responses
Annex
A Schedule of Operators in the Telewest group of companies
Annex
B Schedule of Operators in dispute with BT
Glossary
Draft
Direction under the provisions of Regulation 6(6) of the Telecommunications
(Interconnection) Regulations 1997 of disputes between British Telecommunications
plc ("BT") and:
(i) Cable &
Wireless Communications (Mercury) Limited ("C&W"); and
(ii) Telewest Communications plc & other Operators in the Telewest
group of companies as set out in Annex A to this Direction ("Telewest");
- concerning termination rates payable by BT to Operators based reciprocally
upon BT’s own termination charges under the Network Charge Control Regime:
WHEREAS:
(A) the Secretary
of State for Trade and Industry granted to British Telecommunications
on 22 June 1984 a licence ("the BT licence") under section
7 of the Telecommunications Act 1984 ("the Act") for the running
of telecommunications systems specified in the BT licence;
(B) by virtue of
section 109 of, and paragraph 20 of Schedule 5 to, the Act the BT licence
has effect as if granted to British Telecommunications plc ("BT");
(C) the Secretary
of State for Trade and Industry has granted to Cable & Wireless
Communications (Mercury) Limited ("C&W"), and to Telewest
Communications plc and other Operators in the Telewest group of companies
as set out in Annex A to this Direction ("Telewest"), licences
under section 7 of the Act for the running of a telecommunications system
as specified in that licence;
(D) Regulation 6(6)
of the Telecommunications (Interconnection) Regulations 1997 (the "Interconnection
Regulations"), provides that, where there is a dispute concerning
interconnection between organisations, the Director General of Telecommunications
("the Director General") shall, at the request of either party,
take steps to resolve the dispute within six months of the date of the
request;
(E) C&W entered
into a Standard Interconnect Agreement with BT on 1 May 1998 and each
of the Operators in the Telewest group entered into a Standard Interconnect
Agreement with BT on the dates set out in Annex A to this Direction;
(F) C&W issued
an Operator Charge Change Notice ("OCCN") to BT on 5 July
2001 setting out charges payable by BT (effective 1 October 2001) for
calls from the BT network terminating on the C&W network. Telewest
issued an Operator Charge Change Notice ("OCCN") to BT on
6 July 2001 setting out charges payable by BT (effective 1 October 2001)
for calls from the BT network terminating on the Telewest network. BT
rejected both OCCNs on 13 July 2001 when it issued its own OCCNs for
the same services to C&W and Telewest respectively. Both C&W
and Telewest rejected BT’s OCCN within 14 days;
(G) Both C&W
and Telewest are unable to agree with BT on this matter and are therefore
in dispute;
(H) On 31 August
2001 both C&W and BT referred, in accordance with the provisions
of regulation 6(6) of the Interconnection Regulations, this dispute
to the Director General for his determination. On 26 September 2001
Telewest referred the same matter to the Director General for his determination;
(I) The Director
General has considered, inter alia, the information provided by the
parties and the matters set out in regulation 6(8) of the Interconnection
Regulations. The principal points are summarised in the Explanatory
Memorandum that accompanies, and is published with, this Direction.
The Explanatory Memorandum also contains a full statement of the Director
General’s reasons for making this Direction;
(J) a draft of this
Direction and the Explanatory Memorandum was issued to interested parties
on [.....]. Comments were invited by [....];
NOW
THEREFORE, THE DIRECTOR GENERAL, PURSUANT TO REGULATION 6(6) OF THE
INTERCONNECTION REGULATIONS, AND HAVING CONSIDERED THE VIEWS OF THE
PARTIES AND THOSE MATTERS SET OUT IN REGULATION 6(8) OF THOSE REGULATIONS,
HEREBY MAKES THE FOLLOWING DETERMINATION TO RESOLVE THE DISPUTES BETWEEN
BT AND BOTH C&W AND TELEWEST:
1. Cable & Wireless
Communications (Mercury) Limited is not required to sign and return
the OCCN of 13 July 2001 issued to it by BT or to apply the charges
for call termination set out therein.
2. Telewest Communications
plc and other Operators in the Telewest group of companies as set out
in Annex A to this Direction are not required to sign and return the
OCCN of 13 July 2001 issued to it by BT or to apply the charges for
call termination set out therein.
Keith
Long
Director of Compliance
A person duly
authorised under paragraph 8 of Schedule 1 of the Telecommunications
Act 1984
This direction takes
affect on the date it is published.
Draft
Direction under the provisions of Regulation 6(6) of the Telecommunications
(Interconnection) Regulations 1997 of disputes between British Telecommunications
plc ("BT") and: (iii) Inclarity plc ("Inclarity");
and (iv) The Operators set out in Annex B to this Direction; - concerning
termination rates payable by BT to Operators based reciprocally upon
BT’s own termination charges under the Network Charge Control Regime:
WHEREAS:
(A) the Secretary
of State for Trade and Industry granted to British Telecommunications
on 22 June 1984 a licence ("the BT licence") under section
7 of the Telecommunications Act 1984 ("the Act") for the running
of telecommunications systems specified in the BT licence;
(B) by virtue of
section 109 of, and paragraph 20 of Schedule 5 to, the Act the BT licence
has effect as if granted to British Telecommunications plc ("BT");
(C) the Secretary
of State for Trade and Industry has granted to Inclarity plc ("Inclarity")
(formerly ABS Telecom plc) and each of the Operators set out in Annex
B to this Direction ("the Operators") a licence under section
7 of the Act for the running of a telecommunications system as specified
in that licence;
(D) Regulation 6(6)
of the Telecommunications (Interconnection) Regulations 1997 (the "Interconnection
Regulations"), provides that, where there is a dispute concerning
interconnection between organisations, the Director General of Telecommunications
("the Director General") shall, at the request of either party,
take steps to resolve the dispute within six months of the date of the
request;
(E) Inclarity entered
into a Standard Interconnect Agreement with BT on 27 November 1997 and
each of the Operators entered into a Standard Interconnect Agreement
with BT on the dates set out in Annex B to this Direction;
(F) BT issued an
Operator Charge Change Notice ("OCCN") on 13 July 2001 to
Inclarity and each of the Operators. Inclarity and the Operators are
deemed to have rejected the OCCN by failure to sign within the agreed
contractual timescales;
(G) BT is unable
to agree with Inclarity and each of the Operators on this matter and
is therefore in dispute with each;
(H) On 31 August
2001 BT referred, in accordance with the provisions of regulation 6(6)
of the Interconnection Regulations, this dispute to the Director General
for his determination;
(I) The Director
General has considered, inter alia, the information provided by the
parties and the matters set out in regulation 6(8) of the Interconnection
Regulations. The principal points are summarised in the Explanatory
Memorandum that accompanies, and is published with, this Direction.
The Explanatory Memorandum also contains a full statement of the Director
General’s reasons for making this Direction;
(J) a draft of this
Direction and the Explanatory Memorandum was issued to interested parties
on [.....]. Comments were invited by [....];
NOW
THEREFORE, THE DIRECTOR GENERAL, PURSUANT TO REGULATION 6(6) OF THE
INTERCONNECTION REGULATIONS, AND HAVING CONSIDERED THE VIEWS OF THE
PARTIES AND THOSE MATTERS SET OUT IN REGULATION 6(8) OF THOSE REGULATIONS,
HEREBY MAKES THE FOLLOWING DETERMINATION TO RESOLVE THE DISPUTES BETWEEN
BT AND INCLARITY, AND BT AND EACH OF THE OPERATORS:
1. Inclarity plc
and each of the Operators listed at Annex B to this Direction is required
to apply those call termination charges proposed to it in BT’s OCCN
of 13 July 2001.
2. The charge shall
have effect from 1 October 2001.
3. If the net amount
payable by BT is greater than that previously payable under charges
for the same service in effect prior to BT’s OCCN of 13 July 2001, BT
shall pay to Inclarity or the Operator as appropriate the amount of
the difference together with interest calculated in accordance with
Clause 13.13 of BT’s Standard Interconnect Agreement.
4. If the net amount
payable by BT is lower than that previously payable under charges for
the same service in effect prior to BT’s OCCN of 13 July 2001, Inclarity
or the Operator as appropriate shall pay to BT the amount of the difference
together with interest calculated in accordance with Clause 13.13 of
BT’s Standard Interconnect Agreement.
Keith
Long
Director of Compliance
A person duly
authorised under paragraph 8 of Schedule 1 of the Telecommunications
Act 1984
This direction takes
affect on the date it is published.
Draft
Direction under the provisions of Regulation 6(6) of the Telecommunications
(Interconnection) Regulations 1997 of disputes between British Telecommunications
plc ("BT") and: (i) Cable & Wireless Communications (Mercury)
Limited ("C&W"); (ii) Telewest Communications plc &
other Operators in the Telewest group of companies as set out in Annex
A to this Direction ("Telewest"); (iii) Inclarity plc ("Inclarity");
and (iv) The Operators set out in Annex B to this Direction; - concerning
termination rates payable by BT to Operators based reciprocally upon
BT’s own termination charges under the Network Charge Control Regime:

Explanatory Memorandum
Chapter 1
Summary
1.1 The Director
General of Telecommunications ("the Director General") has
issued a draft Direction pursuant to his powers under the Telecommunications
(Interconnection) Regulations 1997 ("the Regulations"), for
the resolution of disputes between BT and C&W, BT and Telewest,
BT and Inclarity, and BT and each of the Operators listed at Annex B
to this Direction under the terms of their Standard Interconnect Agreements
("SIA"). This draft Direction sets out the Director General’s
proposed decision on these disputes concerning the application of call
termination charges payable by BT to Operators based reciprocally upon
BT’s own charges under the Network Charge Controls.
1.2 On 13 July 2001
BT issued 96 Operator Charge Change Notices ("OCCNs") to relevant
Operators setting out terms for reciprocal call termination and charges
to be applied from 1 October 2001. A number of Operators either formally
rejected BT’s OCCN or failed to sign and return it within agreed contractual
timescales. BT therefore referred such Operators to the Director General
as in dispute on this matter by letter of 31 August 2001. C&W referred
the same matters to the Director General also by letter of 31 August
2001. Telewest referred the matter to the Director General by letter
of 26 September 2001. The Director General has sought the views of all
parties to the disputes and has considered the submissions made by BT
and Operators and has issued a draft Direction in respect of these disputes
and this Explanatory Memorandum on 17 January 2002 to the industry as
a whole for consultation. Comments are requested and will be taken into
account in making a final Direction.
1.3 The details
of the Director General’s consideration of the submissions made by BT
and Operators, together with the reasons for making his draft Direction,
are set out in Sections 3 and 4. In summary, the Director General is
minded to conclude that:
(i) Neither C&W
nor Telewest shall be required to sign and implement the call termination
charges proposed in BT’s OCCN of 13 July 2001; and
(ii) Inclarity and
the Operators at Annex B to this Direction are required to sign and
return BT’s OCCN of 13 July 2001 implementing charges for call termination
services effective from 1 October 2001. This Direction provides that
the Operators who, since 1 October 2001, have been receiving payments
based on previously agreed termination charges, will repay to BT the
amount of any difference plus interest from that date in accordance
with Oftel’s applied interest rate of the London Inter Bank Offered
Rate ("LIBOR") plus 3/8 percent.
1.4 Having considered
the facts specific to this dispute and the matters set out in Regulation
6(8) of the Telecommunications (Interconnection) Regulations 1997, this
draft Direction, in the opinion of the Director General, represents
a fair balance between the interests of the parties in each case, having
regard to the Director General’s wider duties to the development of
the Telecommunications industry in the UK and the encouragement of adequate
interconnection in a way that provides maximum economic efficiency and
gives the maximum benefit to end users.

Chapter 2 Background
Call termination
2.1 The terminating
network is the network to which a customer who receives a call is
directly connected. Call termination on BT’s network is defined from
the termination switch to the customer (noting that call termination
excludes all access costs).
2.2 The calling
party and not the called party pays for call termination. Operators,
who are competing at the retail level, need to buy call termination
services from each other in order to be able to provide end-to-end calls
between customers on different networks. As an interconnection service,
however, call termination has particular characteristics that arise
from the ‘call termination externality’. An externality may be said
to exist where the actions of an individual or organisation cause costs
to be incurred by others (or benefits to be gained by others), but that
individual or organisation has no incentive to take such effects into
account. The externality in call termination arises because the retail
price of a call is paid by the caller, not the call recipient. The caller
has little if any influence over the call recipient’s choice of network
and accordingly, over the call termination charge to be paid. The characteristics
of call termination that arise which are important in this context are:
(i) charges
for call termination are paid by the customers of other Operators,
which will be competing with the terminating Operator in retail
markets. Consequently, Operators have incentives to set high call
termination charges which raise their competitors’ costs; and
(ii) operators
have weak incentives to minimise costs and charges of call termination
because the implications of high charges are faced by the customers
of competing Operators.
Reciprocity
2.3 In a statement
issued in July 1997, Network Charges from 1997, the Director General
supported the principle of reciprocal charging for Operators’ call termination
charges. This principle required that Operators’ charges were calculated
on a reciprocal basis to BT’s own call termination charges, taking into
account the different network topologies. BT’s own charges were regulated
under the Network Charge Controls from 1997. The aim of reciprocity
was to ensure competitive neutrality between BT and Operators and to
remove the distortive effects of the call termination externality. The
Director General, whilst publicly supporting the principles of reciprocity,
believed it was a matter for industry to agree to the practical implementation
of the most appropriate approach to reciprocity from a number of options
identified.
2.4 In 1997 the
industry reached agreement on the application of reciprocity to call
termination charges. The agreement took account of the different termination
charges paid to BT by Operators derived from differences in the mix
of Points of Interconnection ("POIs") (ie the mix of local
exchanges ("DLEs") and tandem exchanges ("DMSUs")).
Operators which interconnected only at DMSU received (and paid) single
tandem rates. Those with a mix of interconnection at DLE and DMSU received
(and paid) charges reflecting the proportion of Operator traffic routed
via DLEs and DMSUs.
Industry
negotiation of current reciprocity agreement
2.5 The reciprocity
agreement implemented by the industry in 1997 ran for the period covering
the Network Charge Controls until 30 September 2001. From March 2001
BT and a group representing Operators opened discussions aimed at reaching
agreement on a new reciprocity agreement to run from 1 October 2001.
2.6 The proposed
new agreement distinguished between Operators with single-switched status
and Operators with multi-switched status. Single switched termination
calls are calls that terminate on an end-user’s network termination
point connected directly to the switch where BT hands over a call to
the Operator. Multi-switched calls are calls that terminate on an end-user’s
network termination point that is connected to a different Operator
switch from that where BT hands over the call. In the case of multi-switched
calls, BT agreed to pay Operators a higher termination charge to reflect
the additional work undertaken in Operator networks to terminate such
calls. Under the proposed agreement, Operators with a significant proportion
of calls terminating via multi-switched routes would apply for Multi-Switched
Operator ("MSO") status and receive higher termination payments
from BT to reflect additional work carried out in Operator networks
to terminate such calls. All other Operators would receive termination
payments based on their status as a Single-Switched Operator ("SSO").
2.7 The Director
General understands that broad agreement was reached between BT and
the Operator Group on the proposed agreement in respect of Single-switched
Operators ("SSOs"), notwithstanding some remaining issues
of concern put forward by specific Operators discussed in further detail
below. There remained further outstanding issues in respect of Multi-switched
Operators ("MSOs") that could not be resolved in the context
of the negotiations between BT and the Operator Group. These issues
were to be pursued by BT and the relevant Operators by means of bilateral
negotiation.
The
OCCN process
2.8 Clause 13 of
BT’s SIA describes the process used by Operators, including BT, for
offering and amending charges in payment for access to another Operator’s
services. Where BT proposes to change the price paid to the terminating
operator for terminating calls, it issues an Operator Charge Change
Notice ("OCCN"). The operator receiving the OCCN has 14 days
to decide whether to accept or reject the new charge and to notify the
originator of the OCCN. Failure to notify within 14 days signals a rejection
of the proposal. Where the proposal is rejected, both operators have
a further 14 days to settle the resultant dispute. If after this second
period the dispute remains unsettled, either operator may refer the
dispute to Oftel. On referral of a dispute, the Director is under an
obligation to carry out a full investigation and take steps to determine
the outcome within six months.
2.9 On 5 July 2001
C&W issued an OCCN to BT setting out proposed charges for C&W’s
call termination services. On 6 July 2001 Telewest issued an equivalent
OCCN to BT. Both Operators proposed charges reflecting their understanding
that significant proportions of their calls were multi-switched.
2.10 On 13 July
2001 BT issued an OCCN to all relevant setting out the proposed reciprocity
agreement, the methodology of calculating individual Operator call termination
charges, and the proposed charges for all Operators calculated on the
basis that all calls were single-switched. All Operators were required
to agree to the methodology and the charges proposed in this OCCN, including
those Operators which believed they would in fact qualify for MSO status
and appropriately higher charges under the proposed methodology. BT
proposed that such Operators should agree to the SSO rates proposed
within the OCCN and then apply for MSO status, and that acceptance of
the OCCN would not prohibit application of MSO rates as agreed at a
later date.
Disputes
referred to the Director General
2.11 A number of
Operators failed to agree to BT’s OCCN. C&W and Telewest have rejected
the OCCN due to their desire for MSO status, remaining concerns over
elements of the reciprocity agreement and unwillingness to sign up to
SSO rates in a written agreement whilst negotiations on MSO rates continued.
Inclarity plc ("Inclarity", formerly ABS Telecom) has objected
to BT’s proposed charges as Inclarity stated they have the effect of
implementing lower charges for call termination (payable by BT to Inclarity).
A number of other Operators are deemed to have rejected the OCCN by
failure to return the signed OCCN within contractual timescales.
2.12 On 31 August
2001 BT referred its dispute with those Operators failing to sign its
OCCN of 13 July 2001 to the Director General for determination. C&W
also referred the matter to the Director General on 31 August 2001.
Telewest referred the same matter on 26 September 2001.
2.13 The Director
General is aware that negotiations continue between BT and both C&W
and Telewest (as well as other Operators not in dispute with BT on this
matter) in respect of agreeing MSO status and appropriate termination
charges. BT has referred C&W and Telewest as in dispute in the context
of this determination as neither Operator has, in the meantime, agreed
to BT’s OCCN of 13 July 2001. Representations have been made by BT,
C&W and Telewest to the Director General in respect of the progress
of MSO negotiations. The Director General considers, however, that at
present the dispute he has been asked to resolve (and is required to
resolve under the Regulations) relates solely to Operators’ failure
to agree to the OCCN (and the charges proposed therein) of 13 July 2001.
Information
sought by the Director General
2.14 Following referral
of these disputes, the Director General has consulted the parties concerned.
The relevant submissions are outlined below in section 3. A number of
parties to this dispute, however, have failed to provide reasons for
failing to accept BT’s proposals as set out in its OCCN. The Director
General has issued four information requests in an attempt to secure
a response from such Operators. The Director General wrote to all Operators
referred by BT as in dispute on these matters on 6 September 2001. On
28 September 2001 he wrote again, by recorded mail, to those Operators
failing to provide a response to his initial letter. On 1 November 2001
the Director General issued a third letter by recorded mail to the registered
office address of those Operators from which he had heard no reply.
On 3 January 2002 the Director General issued a further request for
information by recorded mail. The Director General believes he has made
all reasonable endeavours to solicit an understanding of Operators’
positions in respect of these disputes with BT before reaching his preliminary
conclusions outlined in the draft Direction and accompanying explanatory
memorandum.

Chapter 3 Submissions
of the parties
3.1 BT, C&W
and Telewest made submissions orally and in writing on their respective
disputes. Inclarity made a written submission. A number of other Operators
provided limited response to the Director General’s requests for information
but failed to provide reason for rejecting or failing to agree to BT’s
OCCN of 13 July 2001, or suggesting any alternative.
BT’s
general submissions
3.2 BT stated that
on 13 July 2001 it issued an OCCN to 96 Operators under the terms of
its SIA. This OCCN sought to agree termination rates payable by BT to
Operators on a reciprocal basis to BT’s own termination charges under
the Network Charge Controls. BT’s proposals represented an offer to
cover the period 1 October 2001 to 30 September 2005 using the principles
already established under the previous reciprocity agreement.
3.3 BT stated that
the Operators it referred as in dispute had either formally rejected
BT’s OCCN or failed to sign and return the OCCN within the 14 days required
under the terms of the SIA. Subsequent negotiations failed to reach
commercial agreement within contractual timescales. BT advised that,
subsequent to its initial referral, a number of Operators have since
reached commercial agreement with BT. BT remained in dispute only with
C&W, Telewest, Inclarity and the Operators listed at Annex B to
this Direction.
3.4 BT argued that
its proposals are based on the same general principles as contained
in the reciprocity agreement running from 1 October 1997 to 30 September
2001. Operators are treated as having either single-switched (SSO) or
multi-switched (MSO) status, based upon the work carried out in their
networks in order to terminate traffic. BT said that its OCCN proposed
SSO status for all Operators so that all Operators received the same
reasonable offer. The proposed process then allowed Operators who felt
they would qualify to apply for MSO status. BT stated that it had agreed
in negotiation with the Operator Group to reduce the threshold of multi-switched
traffic required in order for an Operator to qualify for MSO status.
3.5 BT stated in
respect of all Operators in dispute with it on this matter that any
Direction made by the Director General should endorse both the methodology
and principles proposed by BT, ie that the methodology for the calculation
of charges is reasonable and correctly applied, and that charges payable
to Operators should be applied reciprocally, based upon BT’s LRIC call
termination charges. The Director General should determine that the
charges proposed by BT are reasonable and should be applied by Operators.
3.6 BT argued that
its preferred course of action would have been for Operators seeking
MSO status to sign the SSO OCCN without prejudice to their request for
MSO status. BT stated that a number of Operators have indeed taken this
option. BT confirmed that it had previously advised all such Operators
that they could reject the SSO OCCN and continue negotiations in respect
of MSO status as BT had, at the time, expected to be able to reach agreement
on MSO status in the near future. Consequently, those Operators that
did not sign the OCCN were referred as part of the overall process as
in dispute with BT over the proposed SSO charges. BT argued that a percentage
of an MSO’s calls would be single switched, therefore BT’s OCCN had
sought to agree to the relevant balance of DLE/ Single Tandem weighting
for the SSO element. BT said in offering SSO rates to all Operators
it had sought to treat all Operators consistently.
3.7 BT pointed out
that termination charges were an issue not just between BT and any individual
Operator, but for the industry as a whole. Termination charges would
be paid not only by BT, but also by any other Operator originating geographic
traffic that terminated on another Operator’s network.
3.8 BT stated it
was aware that a number of the Operators which had failed to agree to
its OCCN of 13 July 2001 were either in administration or undergoing
novation. BT argued, however, that such Operators must still be required
to agree appropriate termination charges. BT said that when an Operator
went into administration it did not cease trading immediately. In practice,
BT’s relationship with the Operator might continue for some time - the
alternative would be that all of an Operator’s customers would be cut-off
immediately and left without telephony services. In terms of Operators
undergoing novation, BT stated that in terms of whom BT was contracted
to under its SIA, the status of an Operator might not change for a considerable
period of time. It was therefore essential for BT to agree Operator
termination charges with all such Operators while they retained the
contractual ability to terminate geographic traffic.
C&W’s
submissions
3.9 C&W’s initial
submission to the Director General expressed surprise that BT had referred
it as in dispute on the matter whilst negotiations continued between
the parties. C&W said that it had made its own referral due to contractual
obligations in the negotiation process, but was of the opinion that
whilst commercial negotiation continued between BT and C&W there
was not a genuine dispute for resolution.
3.10 C&W argued
that it was misleading for BT to argue that MSO Operators should not
necessarily have any concerns with the SSO OCCN issued on 13 July 2001.
C&W believed that these concerns cannot be separated from its ongoing
negotiations with BT in respect of MSO status. It was therefore inappropriate
for BT to seek C&W to agree to the SSO OCCN in the interim. C&W
argued it was irrelevant that other Operators seeking MSO status had
signed BT’s OCCN setting out SSO charges. Such Operators may not have
the same concerns as C&W or be affected in the same way by the SSO
calculation methodology.
3.11 C&W stated
that BT’s proposal for the SSO OCCN to be signed by Operators without
prejudice to ongoing negotiations on MSO status, was not set out in
the MSO registration pack sent to Operators seeking MSO status, nor
in any other relevant correspondence.
3.12 C&W argued
that it could not sign the OCCN agreeing to SSO charges because the
MSO charge was, in part, derived from the SSO charge. BT uses the percentage
mix of Operator to BT DLE/ Single Tandem egress traffic and assumes
a reciprocal mix in the opposite direction to calculate appropriate
charges. C&W stated that this assumption, whilst having some validity
four years ago, is no longer valid following C&W’s subsequent network
build into the DLE layer. As C&W has been routing egress geographic
traffic onto these routes, BT is benefiting (as a result of the reciprocal
assumption) by way of a lower termination charge whilst undertaking
no work itself in network or routing. This would discourage further
network build into BT’s DLE layer.
3.13 C&W raised
further concerns with the reciprocity agreement as proposed and on which
it continues to negotiate with BT. C&W is concerned that BT has
attempted to change the definition of a multi-switched call to exclude
calls where C&W has number ranges at a 1K level or below hosted
on different switches. BT chooses not to route below a 10K number block.
C&W believes that where the relevant information is made available
to BT it should be required to pay for any resulting multi-switched
call. C&W remains concerned that the reciprocity agreement may not
enable C&W to exit from the four-year term of the agreement if it
so wished. C&W also raised concern as to BT’s intentions in respect
of whether it may attempt to switch to near-end hand over from far-end
hand over, with resulting implications for Operators on the cost of
terminating calls. C&W also argued that the reciprocity agreement
should be reciprocal upon BT’s own call termination charges.
BT’s
submissions on its dispute with C&W
3.14 BT confirmed
that it remains in commercial negotiation with C&W seeking to agree
appropriate MSO rates. BT said that whether an Operator was an MSO was
not black and white as it depended on the verification of appropriate
traffic samples. This was the process that BT was engaged in with C&W.
BT said that the process had taken longer than it had originally anticipated
due to problems receiving all the necessary data from Operators.
3.15 BT stated it
had advised Operators seeking MSO status that the preferred course of
action would be for such Operators to sign the SSO OCCN. The MSO terms
would then be subsequently documented as appropriately agreed based
on the SSO OCCN. BT said that the SSO methodology for the calculation
of charges to OLOs was of a generic nature and equally applied to all.
C&W’s concerns would be taken into account in the process of agreeing
MSO rates.
3.16 BT stated it
had always agreed that it should pay for multi-switched calls where
numbers are hosted on switches and split below the 10K range and where
C&W has made the appropriate information in respect of this available
to BT. BT said it fully accepted this providing that C&W were willing
to allow BT to route calls directly to the appropriate switches should
BT choose to decode below a 10K block.
3.17 BT argued that
the ‘reciprocity agreement’ refers to BT payments to Operators for call
termination services, with the effect that Operators charges are based
reciprocally upon BT's LRIC call termination charges. BT believed it
was therefore inappropriate for the terms of the reciprocity agreement
to be reciprocal upon BT’s own call termination services. BT not only
had multi-switched calls but Local, Single Tandem and Double Tandem
segments, depending on the switch connection and its relationship in
the hierarchy. The obligation on BT is more granular/complex (i.e. 5
different standard service terminating segments).
Telewest’s
submissions
3.18 Telewest stated
it had issued its own OCCN to BT on 6 July 2001 due to concern that
ongoing negotiations between BT and the Operator Group would not reach
satisfactory agreement on reciprocal charging before the proposed implementation
date of 1 October 2001. Telewest saw no alternative but to notify BT
of its proposed pricing for the service of call termination. Telewest
subsequently received BT’s OCCN of 13 July 2001 and, in line with the
procedural advice given to it by BT, rejected the OCCN on the basis
that it wished to apply for MSO status. Bilateral negotiation and discussion
continued between Telewest and BT following rejection of the OCCN, and
for this reason Telewest stated it was surprised by BT’s actions in
referring the matter as a dispute to the Director General. Telewest
did not regard its rejection of the OCCN of 13 July 2001 as bringing
it into dispute with BT.
3.19 On 26 September
2001, Telewest itself referred the matters to the Director General for
resolution, concerned that it had not been offered appropriate MSO rates
by BT. Telewest pointed out that the OCCN issued by BT was for SSO termination
charges. Telewest rejected this offer on the basis that it wished to
apply for and negotiate appropriate MSO rates, a course of action recommended
by BT to MSOs. Telewest was concerned that BT’s failure to offer it
appropriate MSO rates was linked to an allegation by BT that Telewest’s
status as an MSO Operator under the former reciprocity agreement was
not justified, an allegation that Telewest rejected. Telewest expressed
concern at the level of control BT had in setting the charges of other
Operators under the reciprocity agreement. It believed the fact that
BT had refused to differentiate between SSO and MSO Operators in the
charges set out in its OCCN of 13 July 2001 was indicative of the extent
to which BT controlled the timing and procedure of a process that set
the charges of other Operators.
3.20 Telewest argued
that BT had in fact failed to offer qualifying Operators call termination
rates for the period 1 October 2001 to 30 September 2005 which were
appropriate to their multi-switch status. Telewest believed that BT’s
offer of uniform call termination rates for all Operators, regardless
of whether they carry out multi-switch or single-switch termination,
was in fact contrary to the principles of reciprocity established in
both the former and proposed agreements.
BT’s
submissions on its dispute with Telewest
3.21 BT confirmed
that it remains in commercial negotiation with Telewest seeking to agree
appropriate MSO rates, but that agreement had not been possible to date
because of difficulties in verification of appropriate traffic samples.
BT said that whether an Operator was an MSO was not clear-cut as it
depended on this verification process. This was the process that BT
was engaged in now with Telewest. BT stated that BT’s query of Telewest’s
status under the previous reciprocity agreement was in no way related
to ongoing negotiations of the current proposed agreement. BT rejected
Telewest’s assertion that it had failed to offer rates appropriate to
its MSO status as it was still in the process of calculating what such
rates might be. BT said that this process had taken longer than it had
originally anticipated due to problems receiving all the necessary data
from Operators. BT further rejected Telewest’s allegation that it had
undue control over the process of agreeing termination charges. BT said
it had made an offer to all Operators in respect of SSO charges and
has entered into negotiations with those Operators seeking MSO status.
If there is failure to reach agreement on MSO issues then the Director
General may be asked to adjudicate on the relevant issues at such time.
Inclarity’s
submissions
3.22 Inclarity stated
that it objected to BT’s proposals as Inclarity’s termination charges
set under the new agreement would be lower than under the previous agreement.
Inclarity argued that the change would adversely affect its cash flow
and revenue streams. Inclarity argued that BT’s proposal favoured BT
in that it cut down on the rebate due to alternative carriers whilst
keeping a larger share of the initial call charge for itself.
BT’s
submissions on its dispute with Inclarity
3.23 BT stated that
Inclarity was mistaken to assert that BT would be retaining a larger
proportion of call charges for itself under the proposed new agreement.
BT pointed out that the Daytime termination rate payable by BT to Operators
will in fact increase under the charges proposed in BT’s OCCN of 13
July 2001.

Chapter
4
The Director
General’s considerations
The
disputes
4.1 BT has referred
C&W, Telewest, Inclarity and the Operators at Annex B as in dispute
for failure to agree to call termination charges proposed in its OCCN
of 13 July 2001. BT stated that any Direction issued by the Director
General resolving these disputes should endorse the methodology proposed
by BT, that the methodology for the calculation of charge is reasonable
and correctly applied, and that the charges payable to Operators should
be applied reciprocally based upon BT’s LRIC call termination charges.
At the least, the Director General should determine that the charges
proposed by BT are reasonable and should be applied by Operators.
4.2 For the sake
of clarity, the Director General has separated, for the purpose of this
Direction and Explanatory Memorandum, his conclusions into four separate
issues;
(i) Dispute between
BT and C&W;
(ii) Dispute between
BT and Telewest;
(iii) Dispute between
BT and Inclarity; and
(iv) Disputes between
BT and those Operators failing to provide a substantive response outlining
why they have not agreed to the OCCN of 13 July 2001 (Operators listed
in Annex B);
Market
power in call termination
4.3 The calling
party and not the called party pays for call termination, but the calling
party has little or no choice of network or Operator on which the call
is to be terminated. An Operator therefore faces little competitive
pressure on its call termination service. This confers market power
on the providers of call termination in fixed networks. This view in
terms of fixed network termination is consistent with the Director General’s
conclusions in his Review of Charge Controls on Calls to Mobiles issued
on 26 September 2001, in which he concluded that a separate call termination
market for each mobile network was the most appropriate market definition.
The
Director General’s view of reciprocity
4.4 The Director
General reiterated the principle of reciprocity for Operator call termination
charges in his Guidelines on the Operation of the Network Charge Controls
from October 2001 issued on 5 December 2001. This was to ensure competitive
neutrality and to remove the distortive effects of the call termination
externality (see paragraph 2.2 above).
Assessment
of BT’s proposals in its OCCN of 13 July 2001
4.5 BT’s methodology
for calculating SSO call termination is as negotiated between BT and
an Operator Group and on which broad agreement is understood to have
been reached.
4.6 The methodology
for calculating SSO charges in the proposals outlined by BT is the same
as that contained within the previous reciprocity agreement running
from 1 October 1997 to 2001. Charges are based, for each individual
Operator (or Operator ‘group’ or ‘entity’), on the measurement of total
Operator to BT Local Exchange and BT Single Tandem traffic conveyed
during a sample month of May, and applied for a 12 month period thereafter
commencing on 1 October in each year. BT uses the percentage mix of
Local Exchange and Single Tandem traffic and assumes that the percentage
mix is reciprocal to traffic in the opposite direction. The termination
charge payable by BT to an Operator is therefore calculated on a percentage
mix of BT’s own charges. Operators for whom insufficient traffic data
exists to calculate the ratio for the relevant period are assumed to
have 100% single tandem for the purposes of reciprocal calculation.
4.7 BT’s proposals
in its OCCN of 13 July 2001 in respect of MSO status are not relevant
to the disputes in hand. Those Operators that have applied for MSO rates
under the proposed agreement (C&W and Telewest) remain in commercial
negotiation with BT in attempt to secure agreement of appropriate charges.
These negotiations are being pursued on a bilateral basis and are outwith
the generic offer made by BT to all Operators in its OCCN of 13 July
2001.
4.8 BT’s proposals,
as far as SSO charges are concerned, broadly comply with one of four
approaches to reciprocity identified by the Director General in his
statement on Network Charges from 1997 issued in July 1997. This approach
was to calculate a charge for Operator call termination as a weighted
average of BT’s local exchange segment and single tandem segment charges,
using Operator to BT traffic to compute the weights. In the statement,
the Director General identified this approach as one of two preferred
options out of four considered as it reflected most closely the economic
arguments underlying competitive neutrality.
4.9 The Director
General identified one drawback with this approach, however, that Operators’
make or buy decisions would be distorted. Call termination charges are
calculated on the percentage mix of Operator to BT egress traffic terminating
on BT’s network via DLE or Single Tandem. As an Operator builds out
to connect at BT’s DLE layer, its revenue received from BT falls even
where there is no change in the actual service of termination carried
out by the Operator in its own network. Operators therefore face a disincentive
to interconnect at BT’s DLE since their receipts from BT would fall
as would their payments to BT, but the fall in receipts would not reflect
a change in costs incurred on the OLO network. Consequently, the sound
pricing signals for OLOs to choose appropriate points of interconnection
(the differential between the BT charges for the local exchange segment
and the single tandem segment) would be adversely affected.
4.10 This disadvantage
is offset to a degree in the previous and proposed agreements by the
fact that the weighting of traffic is based on data from the previous
year’s mix. This encourages the development of interconnection at DLEs
since the benefit of reduced out payments to BT is felt immediately
by the Operator, but the decreased receipts from BT are deferred.
4.11 The disincentive
for Operators to connect at DLEs could be avoided if, instead of de-averaging
call termination charges to the level of individual Operators, there
was instead a single Operator call termination charge and all Operator
interconnection traffic with BT was used to set the weights (or if Operators
were grouped into a small number of categories). An Operator building
out to BT’s DLE layer would experience only limited reduction in the
level of its receipts, unless it was sufficiently large enough for its
decisions to have a significant impact on all-Operator average traffic
mix. Other Operators, however, could also be affected by any Operator
making changes to its POIs with BT. If any Operator undertook a significant
build out to BT’s DLE layer, all Operator receipts for call termination
(or Operator receipts in that category of Operators) would fall in line
with the change in the percentage mix of traffic, even though such Operators
would not gain any benefit in terms of reduced out-payments to BT.
4.12 The Director
General does not believe that a single weighted average of traffic used
to calculate a single charge for call termination for all Operators
(or for a small number of categories of Operators) is desirable in resolving
this dispute given the disadvantages that also exist in these approaches,
and the reluctance of industry to enter into such an option in the previous
agreement and current proposals. The Director General is also aware
that the effect of imposing a single weighted average on those Operators
in dispute with BT on this matter would, for the majority of Operators
in dispute, result in a decrease in the call termination charge revenue
payable by BT (although this may not necessarily be the case using the
more complicated approach of classifying Operators into a small number
of groups). There would also be a matter of consistency with those Operators
that have already agreed with BT to calculate termination rates based
on a weighted average of their own individual egress traffic to BT.
The
Director General’s preliminary conclusions
(i)
Dispute between BT and C&W
4.13 C&W is
continuing to negotiate with BT in an attempt to secure MSO rates that
it believes are appropriate to its MSO status. C&W argued that it
could not sign the OCCN agreeing to SSO charges because the MSO charge
was, in part, derived from the SSO charge. BT uses the percentage mix
of Operator to BT DLE/ Single Tandem egress traffic and assumes a reciprocal
mix in the opposite direction to calculate appropriate charges. C&W
stated that this assumption, whilst having some validity four years
ago, is no longer valid following C&W’s subsequent network build
into the DLE layer. As C&W has been routing egress geographic traffic
onto these routes, BT is benefiting (as a result of the reciprocal assumption)
by way of a lower termination charge whilst undertaking no work itself
in network build or routing. C&W’s argument centres on the drawback
in the current reciprocity agreement outlined in paragraph 4.9. C&W’s
concerns in this respect remain part of its ongoing negotiations with
BT in respect of MSO call termination charges.
4.14 C&W has
also stated that it was not prepared to sign BT’s OCCN of 13 July 2001,
setting out SSO charges only, on the promise that MSO charges would
be negotiated afterwards. Notwithstanding an understanding that such
negotiation would proceed, C&W was not prepared to commit itself
to an agreement in writing to apply the charges for call termination
proposed in BT’s OCCN.
4.15 BT’s methodology
attached to its OCCN of 13 July 2001 makes it clear that certain Operators
will receive call termination payments from BT based upon the level
of multi-switching that occurs in terminating traffic on their networks.
BT has not made any representation that it believes that C&W will
not qualify for some level of MSO payments under the methodology proposed
in its OCCN of 13 July 2001. It appears unreasonable to the Director
General, therefore, for BT to require C&W to agree to an OCCN setting
out charges that are not intended to apply once commercial negotiation
of MSO charges are complete. The Director General believes that it is
more appropriate to await the conclusion of appropriate negotiations
and apply the agreed rate retrospectively to the commencement date of
the agreement, namely 1 October 2001.
4.16 The Director
General is therefore minded to conclude that C&W should not be required
to apply the charges set out in the OCCN of 13 July 2001 issued to it
by BT. Should commercial negotiation of appropriate MSO charges fail
then it remains open to either party to refer a dispute separately to
the Director General for resolution.
(ii)
Dispute between BT and Telewest
4.17 Telewest, in
rejecting BT’s OCCN of 13 July 2001, has not argued against the principle
of reciprocal charging for call termination services. It has also not
argued in principle against the methodology for calculating call termination
charges set out in BT’s proposals. BT’s OCCN of 13 July 2001 required
all Operators to agree to the SSO charges set out to it, including those
Operators that sought to agree MSO status with BT on the understanding
that BT and the Operator would subsequently negotiate appropriate charges.
4.18 Telewest and
BT remain in commercial negotiation regarding the application of call
termination charges. Telewest has stated that it is not prepared to
sign BT’s OCCN in the meantime as it requires Telewest to agree to SSO
charges which Telewest believes are not appropriate to its status as
an MSO. Telewest argued that BT had failed in its OCCN of 13 July 2001
to offer it call termination rates for the period 1 October 2001 to
30 September 2005 that are appropriate to its MSO status.
4.19 BT’s methodology
makes it clear that certain Operators will receive call termination
payments from BT based on the level of multi-switching that occurs in
terminating traffic on their networks. BT has not made any representation
that it believes that Telewest will not qualify for some level of MSO
payments under the methodology proposed in its OCCN of 13 July 2001.
It appears unreasonable to the Director General, therefore, for BT to
require Telewest to agree to an OCCN setting out charges that are not
intended to apply once commercial negotiation of MSO charges are complete.
The Director General believes that it is more appropriate to await the
conclusion of appropriate negotiations and apply any agreed rate retrospectively
to the commencement date of the agreement, namely 1 October 2001.
4.20 The Director
General is therefore minded to conclude that Telewest should not be
required to apply the charges set out in the OCCN of 13 July 2001 issued
to it by BT. Should commercial negotiation of appropriate MSO charges
fail then it remains open to either party to refer a dispute separately
to the Director General for resolution.
(iii)
Dispute between BT and Inclarity
4.21 Inclarity’s
argument in rejecting BT’s OCCN of 13 July 2001 is that it favours BT
to the extent that BT is paying lower termination charges to Inclarity.
4.22 BT’s termination
charges are regulated by the Network Charge Controls and are subject
to RPI-X% controls. Operators therefore gain the benefit of reductions
in termination charges payable to BT. Given that Operators’ termination
charges are based reciprocally on BT’s costs and charges, Operators’
revenues for call termination received from BT will also reduce in line
with the charge controls. Since the RPI-X% price controls have a similar
effect on Operator payments to BT as on Operator receipts from BT for
termination, the Director General does not consider that the OCCN of
13 July 2001 unduly favours BT.
4.23 Inclarity has
proposed no alternative in its submission to the Director General to
the proposals set out by BT in its OCCN of 13 July 2001. In view of
this fact and the matters considered at paragraphs 4.5 to 4.11 and 4.22
above, the Director General is minded to conclude that Inclarity should
be required to sign and return BT’s OCCN of 13 July 2001 implementing
charges for call termination services effective from 1 October 2001.
(iv)
Disputes between BT and Operators listed in Annex B;
4.24 BT’s proposals
and the charges contained within its OCCN of 13 July 2001 (in terms
of SSO Operators) have been made following negotiation of the issues
with an Operator Group. The Operators at Annex B have failed to explain
why they have failed to agree to BT’s OCCN of 13 July 2001. The Director
General is aware that a number of these Operators may currently be in
administration or undergoing novation. These Operators, however, remain
under contract with BT in the meantime and have contractual ability
to terminate geographic traffic. It is the Director General’s view that
all such Operators, therefore, must be subject to application of appropriate
call termination charges.
4.25 Given that:
(a) there is
an absence of any substantive communication from any of the Operators
at Annex B giving reason or argument as to why BT’s OCCN of 13 July
2001 is unreasonable;
(b) that the
proposals in BT’s OCCN of 13 July 2001 in terms of SSOs were the
subject of negotiation and agreement between BT and an Operator
Group;
(c) that the
proposals in BT’s OCCN represent the same methodology and approach
to reciprocity as agreed between BT and Operators under the previous
reciprocity agreement running from 1 October 1997 to 30 September
2001; and
(d) the Director
General’s considerations as outlined in paragraphs 4.5 to 4.12 above,
that BT’s proposals in respect of SSOs are reasonable and broadly
conform with one of the Director General’s preferred approaches
to reciprocity;
the Director General
is minded to conclude that each of the Operators at Annex B should be
required to sign and return BT’s OCCN of 13 July 2001 implementing charges
for call termination services effective from 1 October 2001.
Interest
Charge
4.26 In accordance
with Clause 13.13 of BT’s SIA, this Direction provides that Inclarity
and the Operators at Annex B, in respect of those Operators who, since
1 October 2001, have been receiving payments based on previously agreed
termination charges at a lower rate, will repay to BT the amount of
any difference plus interest from that date. The applicable interest
rate set in Clause 13.13 is the London Inter Bank Offered Rate (LIBOR)
plus 3/8 per cent.
Chapter 5
Consultation
and timetable for responses
5.1 This draft Direction
has been made in response to the submissions made by the parties to
this dispute and applies only to BT, C&W, Telewest, Inclarity and
those Operators listed at Annex B. OFTEL seeks comments from all interested
parties on the proposed decisions detailed in the Draft Direction.
5.2 Please e-mail
or send comments in writing to:
Richard Thompson
Oftel
50 Ludgate Hill
London
EC4M 7JJ
Telephone: (020)
7634 8983
Fax: (020) 7634 8943
E-mail: richard.thompson@oftel.gov.uk
5.3 Comments on
this consultation must be sent to OFTEL by Thursday 14 February 2001.
OFTEL does not intend on this occasion to hold any comments-on-comments
phase during which observations may be made on the representations made
by others. Nevertheless, in the interests of transparency, all non-confidential
representations will be published.
5.4 Confidential
responses should not be sent via e-mail. Written comments will be made
publicly available in OFTEL’s Research and Intelligence Unit, except
where a respondent indicates that a response, or part of it, is confidential.
Respondents are therefore asked to separate any confidential material
into a clearly marked annex. In the interests of transparency, respondents
are asked to avoid confidential markings wherever possible.
5.5 The final Direction
will be made as soon as possible after the end of the above mentioned
consultation period.
Annex A to the
Direction
Schedule of Operators
in Telewest group of companies
|
Operator
|
Date
of agreement
|
|
Telewest
Communications plc
|
15/01/1998
|
|
Birmingham
Cable Ltd
|
22/10/1997
|
|
Cable London
|
20/10/1997
|
|
General
Cable TCC
|
24/10/1997
|
|
General
Cable YCC
|
24/10/1997
|
|
Eurobell
(South West) Limited
|
28/06/1997
|
|
Eurobell
(Sussex) Limited
|
28/06/1996
|
|
Eurobell
West Kent Limited
|
24/10/1997
|

Annex
B to the Direction Schedule of Operators in dispute with BT
|
Operator
|
Date
of agreement
|
|
IDT Global
Ltd
|
21/04/1999
|
|
Mannesmann
Ipulsys UK Ltd
|
19/02/1999
|
|
Opera Telecom
Ltd
|
16/02/2000
|
|
RSL Com
UK Ltd
|
04/11/1997
|
|
Star Telecommunications
Inc
|
15/01/1998
|
|
Starcomm
Ltd
|
02/11/1999
|
|
Torc Europe
Ltd
|
08/10/1997
|
|
Viatel
Global Communications Ltd
|
21/04/1998
|
|
Worldxchange
Communications Ltd
|
17/10/1997
|
Glossary
Digital
Local Exchange (DLE) -
the telephone exchange to which customers are directly connected.
Digital
Main Switching Unit (DMSU) –
a trunk exchange primarily used for connecting long distance calls.
Externality
- An externality
exists where the actions of an individual or organisation cause costs
to be incurred by others (or benefits to be gained by others), but that
individual or organisation has no incentive to take such effects into
account
Long
Run Incremental Costs (LRIC)
Costs that arise
in the long run as a result of providing a given 'increment', eg, an
additional amount of numbers. Long run costs assume that the supply
of numbers is variable (not fixed).
Points
of Interconnection
(POI) –
also known as a Switch Connections ie where an operator’s network interconnects
with BT usually at a Digital Main Switching Unit (DMSU) or Wide Area
Tandem (WAT).
Terminating
network –
the network to which a customer who receives a call is directly connected.
Terminating
operator –
the operator on whose network the call terminates.


|