Inter-operator Co-existence and Co-ordination Guidelines for BFWA Systems Operating in the Band 27.5 - 29.5GHz


*
pdf logo version (41kb)

1

Introduction

Licences for Broadband Fixed Wireless Access (BFWA) in the 28GHz band cover operation in three paired-spectrum blocks as indicated in Section 3. Additionally these three paired-blocks have been assigned in a number of geographical regions throughout the UK. The close location of co-frequency and adjacent frequency systems requires that certain measures are required in order to enable substantially interference free operation for the licensees.

The Radiocommunications Agency (the Agency) is not anticipating playing a major role in the co-ordination process. However, to facilitate the minimum of difficulties, the guidelines detailed in this document are set out to provide a basis for co-ordination. If any cases of difficulty arise, which are ultimately referred back to the Agency, the guidelines will be used as a basis to examine whether adequate steps have been taken to avoid problems. Where possible, these guidelines are based upon work carried out not only by the Agency but also by other international regulatory and standardisation bodies involved in this field.

It may not be possible to provide an environment that is completely interference free, where co-existence without some degree of constraint does not arise. Therefore, operators are encouraged to both take into account the range of possibilities set out in this document and to take their own steps to examine further enhancements that might take advantage of their particular deployment situations.

A degree of co-operation between operators would be beneficial to make the most of specific radio equipment parameters or deployment scenarios that may lead to "closer" co-existence.

These guidelines have been developed in consultation with BFWA industry partners through the Agency consultation groups and should be enhanced as operational experience is gathered.

2

Scope

These guidelines cover two scenarios for inter-operator co-existence and co-ordination:

  • Scenario 1 - Operators using the same frequency blocks in neighbouring geographical regions.
  • Scenario 2 - Operators in the same geographical region using adjacent frequency blocks.

The guidelines cannot anticipate every deployment situation. For scenario 1, maximum levels of expected interference are detailed as a trigger for "inter-operator" action. For scenario 2, reference is made to analysis methods and results from other bodies. Specifically, reference is made to ideas developed, or under development, within CEPT, ETSI and IEEE as well as work carried out directly by the Agency.

3

Frequency band and BFWA spectrum packages

3.1

Frequency band

The 27.5GHz to 29.5GHz band is shared on a co-primary basis between the Fixed Service (FS), the Fixed Satellite Service (FSS) [Earth to space] and the Mobile Service (MS). The BFWA spectrum has been planned in accordance with the CEPT T/R 13-02 recommended channel plan. Two frequency blocks of 392MHz are available and are given by 28.0525GHz to 28.4445GHz paired with 29.0605GHz to 29.4525GHz. The layout of frequency band, showing the BFWA spectrum, is given in Figure 1.

Notes:
1) The use of the band 29.1 GHz to 29.5 GHz [Earth to space] by the fixed satellite service is limited to geostationary satellite systems and feeder links to non geostationary satellite systems in the mobile satellite service.

2) Currently no planned use with the UK.

Figure 1 - 27.5GHz to 29.5GHz frequency band

The allocation of parts of the band in Europe to either the Fixed Service or Fixed Satellite Service is detailed in ERC Decision ERC/DEC(00)09.

3.2

BFWA spectrum packages

BFWA licences cover 11 English regions, Scotland, Wales and Northern Ireland with up to three licensees per region. The Agency has applied 28MHz guard bands between the three licensed frequency blocks in a region. The resulting three spectrum packages are detailed here and shown in Figure 2.

  • Package 1 28.0525 - 28.1645GHz (BFWA 1) paired with 29.0605 - 29.1725GHz (BFWA 1')
  • Package 2 28.1925 - 28.3045GHz (BFWA 2) paired with 29.2005 - 29.3125GHz (BFWA 2')
  • Package 3 28.3325 - 28.4445GHz (BFWA 3) paired with 29.3405 - 29.4525GHz (BFWA 3')

Figure 2 - BFWA spectrum packages

4

The Role of the Agency

4.1

General

The Agency will undertake to support the BFWA licence holders within the band 27.5GHz to 29.5GHz by:

  • providing advice and guidance on best practices and co-ordination processes to facilitate inter-operator co-existence;
  • protecting assignments by the registration of BFWA deployments through the UK national and international ITU procedures;
  • registering deployments on the Radiocommunications Agency Unified Licensing Executive System (RULES) database;
  • acting as arbitrator in co-existence issues if co-operation between operators fails; and
  • protecting the assignments and acting on behalf of BFWA operators in addressing both national and inter-national co-ordination and policy issues.

4.2

Arbitration

The Agency, through the guidelines set out in this document, encourages operators to resolve co-existence difficulties themselves. However, if either party encounters difficulties, bi-lateral negotiation may, at any time, be requested by the Agency to resolve the issue.

Evidence of application of the guidelines in this document will be viewed by the Agency as an indication of the will of operators to resolve any issues.

4.3

Inter-operator co-operation

The BFWA Licence states:

"The Radio Equipment shall be operated in accordance with any co-ordination procedure notified to the Licensee in writing by the Radiocommunications Agency to ensure that operation does not cause undue interference to equipment in adjacent areas or frequency bands."

Therefore the BFWA operators have a duty of care to the operators in adjacent areas or frequency blocks, not to cause harmful interference.

Guidelines and measures are detailed to help minimise inter-operator co-existence difficulties and their consequent effect on deployment of BFWA. However, these guidelines and measures cannot cope with every variation in equipment and deployment characteristic but are put forward as a baseline having made assumptions about anticipated typical parameters.

Therefore, it is entirely possible that more detailed co-ordination between neighbouring operators (by area or frequency block) can reduce the impact of co-existence difficulties. To carry this out it may be necessary for operators to co-operate to some degree including exchanging technical information relevant to resolving co-existence difficulties.

At a minimum this information should be sufficient to enable any neighbouring operator to assess the impact of any potentially interfering deployment on his ability to serve his customers. Account should be taken also of customer base expansion.

In cases of difficulty, evidence of negotiation will be requested by the Agency.

5

Technical basis for co-existence limits

The scenario 1 co-ordination trigger and "acceptable" co-existence limit is based on an agreed degradation of the receiver thermal noise floor (interference to noise (I/N) ratio) and consequent impact on link budget. Scenario 2 co-existence guidelines are based upon frequency separation (and spatial separation if appropriate) justified by statistical analysis of the likelihood of interference degrading link performance below a given level.

6

Frequency band planning

It is important to note that the guidelines detailed in this document make no assumption about FDD/TDD or harmonisation of the frequency plan.

The CEPT/ERC Recommendation on 27.5-29.5GHz band [1] recommends the following harmonised arrangement:

"that in the case of deployment of FDD systems the upper subband should be used for the transmission from the terminals to the central station (hub) and the lower for the transmission from the central station to the terminals;"

Therefore the following is recommended for FDD systems only:

  • The lower sub-band 28.0525 - 28.4445GHz is to be used for central station to terminal station transmission;
  • The upper sub-band 29.0605 - 29.4525GHz is to be used for terminal station to central station transmission.
   

7

Maximum recommended EIRP levels

In order to ensure the adequacy of the co-existence guidelines the following maximum EIRP levels are strongly recommended:

Central/Base station Point to Multipoint (P-MP) systems 0.5dBW/MHz

Terminal/Subscriber stations/Multipoint to Multipoint (MP-MP) stations

11.5dBW/MHz
Point to Point (P-P) stations 11.5dBW/MHz

An Automatic Transmitter Power Control (ATPC) range of at least 15dB is assumed for all P-MP terminal station transmitters and for all MP-MP and P-P transmitters.

Any major departures from these recommended maximum EIRP values would require re-evaluation of the inter-operator guidelines.

8

Methods for Inter-operator co-existence and co-ordination

There are two scenarios to consider:

  • Scenario 1 - Operators using the same frequency blocks in neighbouring geographical regions.
  • Scenario 2 - Operators in the same geographical region using adjacent frequency blocks.

The following methods proposed apply to all types of Fixed Service system deployed in the BFWA frequency ranges identified in Section 3.2 irrespective of network architecture. However, certain assumptions have been made in developing the guidelines so care is required when considering systems that have system parameters/characteristics that depart substantially from those assumed (see Annex B).

8.1

Scenario 1

For each station deployed within the licensed area, the operator shall carry out a calculation of the PFD level at or beyond the licensed area boundary which shall be compared to the boundary PFD trigger level.

If the boundary PFD trigger level is exceeded there are two routes to resolve this:

  1. The "preferred route" is negotiation between operators in adjacent regions to investigate whether the exceeded PFD trigger level could be acceptable. For example it may be possible that the threshold evaluation location can be moved by negotiation.
  2. The "secondary route" is to take the necessary steps to reduce the PFD to be less than or equal to the PFD trigger level.

The overall process is illustrated in the flow diagram at Annex A.

The boundary PFD trigger level = -102.5 dBW/MHz/m2.

The derivation of this figure is given in Annex B. Additionally there is a report [2] that provides a full examination of these calculations that is available from the Agency website.

When stations are deployed along or near a coastline, and the coastline of another licensed area is less than 60km away from the deployed station, then the remote coastline should also be considered as part of the licence area boundary for the purposes of checking the boundary PFD level.

8.1.1

Calculating the boundary PFD

In carrying out the calculation of the boundary PFD resulting from the deployment of any transmitting station (i.e. central, terminal, repeater or in-band P-P link) the operator should advantageously make use of the appropriate propagation tools and terrain as opposed to a worst case free space loss calculation.

It is recommended that the operator employs methods consistent with ITU-R P.452-9 [3]. To assess the excess loss due to time varying effects a figure for percentage time equal to 50% is recommended.

Sample calculations are given in Annex C.

8.1.2

Adequacy of the PFD trigger level

The value has been set having considered a balance between minimising the constraints on deployment against the probability of unacceptable interference in a neighbouring area. Meeting the PFD trigger level does not in itself guarantee interference free operation in the neighbouring area. However, statistical modelling [2] has demonstrated that when allowance is made for the limited line of sight between interferer and victim stations and the realistic deployment of antennas that application of this limit will ensure substantially interference free co-existence.

Annex B lists the typical parameters used for deriving the trigger value and testing its adequacy in multiple interferer scenarios.

8.2

Scenario 2

Referencing work that considers this interference scenario, it is generally concluded that some frequency separation between operator deployments in adjacent frequency blocks is required for reasonably interference free operation and unco-ordinated deployment. (Ref: [2], [4], [5] and [6]) Additionally, when considering the deployment of P-P systems it is recommended [6] that angular discrimination will require consideration possibly in conjunction with higher performance antennas.

8.2.1

Guard band/spatial separation guidelines

Between FDD system assignments operating in a harmonised sub-band plan detailed in Section 6 and employing channelisation schemes up to 28MHz, one guard band equal to 28MHz is recommended ([1] and [4]).

Systems that are not operating in accordance with any harmonised sub-band plan should ensure adequate spatial separation between central stations when deploying P-MP systems. CEPT [1] recommends a minimum of 500m in conjunction with one guard band. In circumstances where spatial separation is not possible, a larger guard band may be required and operators should co-operate to fairly apportion the increased guard band requirement.

For network architectures that do not employ central stations, guidance suggests again that a single channel guard band is adequate for acceptable performance [5].

It is recognised that further study of these issues is required for the consideration of mixed system type deployments.

8.2.2

Guard band adequacy

The guidelines detailed in 8.2.1 above are based on the conclusions of ERC Report 99 [4]. The executive summary of that report highlights the limitations of the work which has not considered systems employing modulation schemes more complex than 4 level, channel spacings other than 28MHz or the sensitivity of the conclusions to radio system performance.

However, one 28MHz single channel guard band between licensed frequency blocks is included in the BFWA assignment plan detailed in Section 3. Therefore, as suggested by report [2], there should be sufficient protection inherent in the assignment plan, under most circumstances detailed above, to minimise the inter-operator co-ordination and co-operation required.

However, operators in the same area must accept that no reasonable guard band can guarantee complete interference free operation. There will always be a likelihood that a small part of their coverage area will be subject to an unacceptable level of interference. As a benchmark an area of around 1% (so-called interfered area [4] or %KO [6]) is reasonable and has been assumed in verifying guard band widths in these references. Operators should therefore co-operate to some extent to minimise the impact on their deployments.

Testing the adequacy of a particular guard band size is complicated and dependent upon many specific operational and deployment characteristics. The references cited above detail a variety of analysis methods which may be used to verify the adequacy of any specific guard band size.

9

References

[1] CEPT/ERC Recommendation (01)03 "Use of Parts of the Band 27.5-29.5GHz for Fixed Wireless Access".
[2] Agency Report - "Co-ordination between Broadband Fixed Wireless Access systems in the 28 and 42GHz Frequency Bands" (http://www. radio.gov.uk).
[3] ITU-R Rec. P.452-9 "Prediction procedure for the evaluation of microwave interference between stations on the surface of the Earth at frequencies above about 0.7GHz".
[4] CEPT/ERC Report 99 "Preliminary Report on the analysis of the coexistence of two FWA cells in the 24.5-26.5 GHz and 27.5-29.5 GHz bands".
[5] IEEE 802.16, Recommended Practice for Coexistence of Fixed Broadband Wireless Access Systems.
[6]

ETSI TR 101 853 "Rules for Coexistence of P-P and P-MP systems using different access methods in the same frequency band".

For further information contact:

RA2/BFWA
Radiocommunications Agency

Wyndham House
189 Marsh Wall
London, E14 9SX

Tel: 020 7211 0679/0128/0255
Fax: 020 7211 0203
E-mail: bfwa@ra.gsi.gov.uk

Top button

*

Annex A
Process for Scenario 1 - Operators using the same frequency blocks in neighbouring geographical regions

Top button

*

Annex B
Derivation of the boundary PFD trigger level

Derivation of the co-ordination triggers for base stations (Hubs)

There are two stages to the process of defining co-ordination triggers resulting initially in a co-ordination zone and secondly in an associated boundary PFD trigger level. These can be derived using the following procedure:

Using typical operational characteristics of both the transmitting station (interferer) and the co-channel victim receiving system calculate the minimum separation distance based upon a directly aligned minimum coupling loss calculation and an agreed maximum tolerable interference level at the receiver input.

Having established the minimum separation distance for the worst case alignment divide the distance equally about the boundary of the two licensed areas. With the same assumptions about the victim receiver system re-calculate the PFD at the mid-point which is the licensed area boundary. This will be the boundary PFD trigger level.

Assessment of the co-ordination triggers for base station to subscriber stations alignment

Having determined the acceptable PFD level at the boundary based on the base station to base station case above, this can be checked using an interfering subscriber station to see whether the limit is adequate or needs adjustment to cater for the different characteristics. In the directly aligned case the victim base station is assumed to be set back from the boundary by the distances calculated in the process above. The interfering subscriber station is assumed to pointing towards a base station located at the licensed area boundary looking into its own service area. Subscriber station ATPC is assumed and for the directly aligned case, correlated rain fading is assumed. It is further assumed that the subscriber station will be operating at maximum EIRP when located at the cell edge.

For the parameters assumed below, a maximum cell radius can be calculated to determine how far into the interfering network area the subscriber should be for the worst case interference scenario. The resultant interfering power from the subscriber station can now be calculated at the victim base station.

If this is below the interference threshold then this implies that the previously calculated PFD is adequate for this scenario also.

In order to assess the co-ordination distance requirement, it is assumed that the subscriber station EIRP in the scenario above is reduced by the rain fade margin for the directly aligned case. However care needs to be taken about this assumption at angles away from the bore sight condition where rain fade and maximum EIRP may not be correlated although antenna discrimination can be taken into account.

Examples of these calculations are given below.

Assumed system parameter values

For the purposes of calculating appropriate PFD trigger levels, the following system, deployment and propagation parameter values were assumed:

Assumed parameters for boundary PFD derivation:

Nominal channel bandwidth: 28 MHz
Base station EIRP: 15 dBW = 0.5 dBW/MHz
Base station antenna gain: 15 dBi
Base station antenna radiation pattern: EN 301 215-2 class CS2
Base station antenna downtilt 9 degrees
Subscriber station EIRP: 26 dBW = 11.5 dBW/MHz
Subscriber station ATPC assumed: RX input level maintained at 5dB above the threshold for BER=10-6.
Subscriber station antenna gain: 32 dBi (P-MP); 26i dB (mesh)
Subscriber station antenna 3dB beam width: 4° (P-MP); 9° (mesh)
Subscriber station antenna radiation pattern: EN 301 215 class TS1
Subscriber station receiver threshold (10-6 BER):

-111 dBW (QPSK)
-125.5 dBW/MHz

Nominal operating level (threshold +5dB): -106 dBW
Receiver noise figure: 7 dB
Interference limit (kTBF - 10 dB): -147 dBW/MHz
Atmospheric attenuation: 0.12 dB/km
Rain attenuation: 4.6dB/km

Worst case interferer calculations

Base station to base station

 
Basic link budget equation: Prec = EIRPtx - FSPL - Latmos + Grec
  Where:
  Prec is the interference power at the receiver input
  FSPL is the free space path loss =20 log (4Rmin/)
  Latmos is the atmospheric loss (0.12Rmin dB at 28GHz)
  Grec is the receiver antenna gain in the direction of the interferer
  Rmin is the minimum separation distance.
To meet the interference criteria detailed above:  
  Rmin = 55km for 27.5GHz
Therefore,  
Co-ordination distance = 27.5km at 27.5Ghz
   
Antenna aperture Ae = Grec + 10 log (2/4)
  = -35.24 dBm2 at 27.5GHz and a 15dBi antenna gain.
   
Power Flux Density: PFD = Prec - Ae
  Prec at 27.5km for 27.5GHz = -137.7dBW/MHz
   
Therefore boundary PFD: = -102.5dBW/MHz/m2

Subscriber station interference

A maximum cell size, Rmax, needs to be determined based upon the parameter values above. From the maximum base station EIRP, subscriber station antenna gain and nominal subscriber receiver operating level a maximum path attenuation can be calculated.

Maximum path attenuation  
(FSPL + atmospheric loss + rain fade) = 153dB.
Therefore maximum cell size: Rmax = 4.1km

It is assumed that worst case interference occurs when the subscriber station is at the cell edge and looking towards a serving base station at the boundary and beyond to a victim base station located within the neighbouring network by the co-ordination distance.

Therefore worst case distance: = 31.6km (27.5km + Rmax)

Maximum EIRP = 11.5dBW/MHz, assuming the path in the cell is subject to rain fading, the effective EIRP at the victim is assumed to be reduced by the cell radius multiplied by the rain attenuation figures given above.

Interfering power: Prec = EIRPtx - FSPL - Latmos + Grec
Therefore the interfering power at the victim base station = -147.4dBW/MHz

This is marginally below the interference limit (-147dBW/MHz) detailed above.

Allowing for the effective EIRP after rain fading, co-ordination distances can be calculated.

Co-ordination distance: = 13km

However, it is possible that a combination of non direct alignment close to the antenna bore-sight and of rain fading not affecting the interference path could cause higher EIRP in the direction of the boundary.

Assuming a maximum EIRP from the subscriber station and a 10° off-boresight angle towards the boundary, then by reference to the antenna pattern referred to above, the maximum EIRP towards the boundary could be -5.5dBW/MHz.

Therefore,

Co-ordination distance: = 16km at 27.5GHz

This is less than the distance required for base station co-ordination, therefore the same trigger level is adequate for the subscriber station case.

Top button

*

Annex C
Sample boundary PFD calculation

Remote PFD at range Rkm = Ptx + Gtx - 20logR - Alosses - 71- L452 dBW/MHz/m2
  Where:
  Ptx = transmitter power
  Gtx = transmitting antenna gain
  R = distance to the boundary in km
  Alosses = atmospheric losses (0.12dB/km at 28GHz)
  L452 = additional losses derived from ITU-R Rec P.452-9 resulting from diffraction and clutter as appropriate.

Remember: The PFD threshold is based on a typical victim antenna gain of 15dBi (Annex B).

Consider the following scenarios:

P-MP Central Station (CS) located 15km from the boundary, antenna = 60° sector, 15dBi gain, EIRP (Ptx + Gtx) = -3dBW/MHz:

Case 1

Nearest boundary point is on CS antenna boresight, clear line of sight with first fresnel zone clearance (i.e. L452 = 0dB).

Therefore boundary PFD = -99.3dBW/MHz/m2 - action needed

Case 2

As case 1 but antenna boresight 45degrees to the boundary. (Antenna is EN 301 215-2 Class CS2, gain = -20dB relative at 45degrees.)

Therefore boundary PFD on boresight = -103.1dBW/MHz/m2 - no action needed

PFD at nearest point on boundary = -119.3dBW/MHz/m2 - no action needed

Case 3

Terminal station associated with the above CS located 2km further away pointing towards the CS and the boundary. EIRP consistent with CS RSL +5dB = -120.5dBW/MHz. Therefore EIRP = -8dBW/MHz nominally. Antenna is EN 301 215-2 TS1, gain = 28dBi on boresight, 4dBi at 45 degrees off boresight.

Therefore PFD on TS boresight = -109.1dBW/MHz/m2 - no action needed

PFD towards nearest point on boundary = -129.3dBW/MHz/m2 - no action needed

Note that in deriving the latter result for Case 3 the correlation of rain fade cannot be assumed. Therefore if a maximum ATPC range of 25dB is assumed then the PFD towards the boundary increases to -104.3dBW/MHz/m2 - still no action needed.

It can be seen that ATPC action could increase the PFD over the trigger threshold but ATPC operation is time dependent. Therefore in marginal cases a more rigorous calculation may be appropriate to assess the percentage time against EIRP increase due to ATPC.

Top button
*

RA390 (Rev1)
JULY 2001
RA Home